| Kollam Project HD |
| Date: 12/11/2020 |
Work has been completed | 100% Completed
work completed
| Kollam Project HD |
| Date: 15/08/2020 |
Work in progress | 90% Completed
90 % of Work completed except fitting of 2 nos flowmeter
| Kollam Project HD |
| Date: 26/06/2020 |
Work in progress | 85% Completed
85 % of Work completed except electric connection,trial run and fitting of 2 nos flowmeter