Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Kozhikode Project Dn AE5
Date: 22/09/2021

Work has been completed | 100% Completed

Work completed, Total expenditure Rs.36373563/- final Bill paid to contractor on 27.07.2021 including Road restoration charges .

Kozhikode Project Dn AE2
Date: 21/04/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 19/04/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 17/04/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 15/04/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 12/04/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 08/04/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 07/04/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 05/04/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 03/04/2021

Work has been completed | 100% Completed

work completed, final bill under preparation.

Kozhikode Project Dn AE2
Date: 31/03/2021

Work has been completed | 100% Completed

work completed, final bill under preparation.

Kozhikode Project Dn AE2
Date: 29/03/2021

Work has been completed | 100% Completed

work completed, final bill under preparation.

Kozhikode Project Dn AE2
Date: 27/03/2021

Work has been completed | 100% Completed

work completed, final bill under preparation.

Kozhikode Project Dn AE2
Date: 25/03/2021

Work has been completed | 100% Completed

work completed, final bill under preparation.

Kozhikode Project Dn AE2
Date: 23/03/2021

Work in progress | 98% Completed

Total length of pipe - 39.584 KM( 110 MM PVC -39084 M, 100 MM GI-500 M) Pipe laid-38.80 Km, Balance to be laid 0.784 km. Pipe laying ,Interconnection and Road reformation work under progress.

Kozhikode Project Dn AE2
Date: 18/03/2021

Work in progress | 98% Completed

Total length of pipe - 39.584 KM( 110 MM PVC -39084 M, 100 MM GI-500 M) Pipe laid-38.80 Km, Balance to be laid 0.784 km. Pipe laying ,Interconnection and Road reformation work under progress.

Kozhikode Project Dn AE2
Date: 15/03/2021

Work in progress | 98% Completed

Total length of pipe - 39.584 KM( 110 MM PVC -39084 M, 100 MM GI-500 M) Pipe laid-38.80 Km, Balance to be laid 0.784 km. Pipe laying ,Interconnection and Road reformation work under progress.

Kozhikode Project Dn AE2
Date: 08/03/2021

Work in progress | 95% Completed

Total length of pipe - 39.584 KM( 110 MM PVC -39084 M, 100 MM GI-500 M) Pipe laid-38.612 Km, Balance to be laid 0.972 km. Pipe laying ,Interconnection and Road reformation work under progress.

Kozhikode Project Dn AE2
Date: 03/03/2021

Work in progress | 95% Completed

Total length of pipe - 39.584 KM( 110 MM PVC -39084 M, 100 MM GI-500 M) Pipe laid-38.612 Km, Balance to be laid 0.972 km. Pipe laying ,Interconnection and Road reformation work under progress.

Kozhikode Project Dn AE2
Date: 23/02/2021

Work in progress | 95% Completed

work in progress

Kozhikode Project Dn AE2
Date: 16/02/2021

Work in progress | 94% Completed

Interconnection and pipeline laying work in progress

Kozhikode Project Dn AE2
Date: 05/02/2021

Work in progress | 94% Completed

Pipe line laying and road reformation works in progress

Kozhikode Project Dn AE2
Date: 26/01/2021

Work in progress | 94% Completed

Total length of pipe - 39.584 KM( 110 MM PVC -39084 M, 100 MM GI-500 M) Pipe laid-37.612 Km,Balance to be laid 1.972 km.Pipe laying ,Interconnection and Road reformation work under progress. Quoted PAC- 4.22 cr Bill submitted-2.98cr

Kozhikode Project Dn AE2
Date: 06/01/2021

Work in progress | 91% Completed

Total length of pipe - 39.584 KM( 110 MM PVC -39084 M, 100 MM GI-500 M) Pipe laid-36.751Km,Balance to be laid2.833km.Pipe laying ,Interconnection, Road reformation and pipe line charging work under progress. Quoted PAC- 4.22 cr Bill submitted-2.98cr

Kozhikode Project Dn AE2
Date: 30/12/2020

Work in progress | 90% Completed

Total length of pipe - 39.584 KM( 110 MM PVC -39084 M, 100 MM GI-500 M) Pipe laid-36.295Km,Balance to be laid3.289km.Pipe laying ,Interconnection, Road reformation and pipe line charging work under progress. Quoted PAC- 4.22 cr Bill submitted-2.36cr

Kozhikode Project Dn AE2
Date: 10/12/2020

Work in progress | 84% Completed

Total length of pipe - 39.584 KM( 110 MM PVC -39084 M, 100 MM GI-500 M) Pipe laid-33.624Km,Balance to be laid 5.96km.Pipe laying ,Interconnection, Road reformation and pipe line charging work under progress. Quoted PAC- 4.22 cr Bill submitted-2.36cr

Kozhikode Project Dn AE2
Date: 04/12/2020

Work in progress | 81% Completed

Total length of pipe - 39.584 KM( 110 MM PVC -39084 M, 100 MM GI-500 M) Pipe laid-31.978Km,Balance to be laid 7.606km.Pipe laying ,Interconnection, Road reformation and pipe line charging work under progress. Quoted PAC- 4.22 cr Bill submitted-2.36cr

Kozhikode Project Dn AE2
Date: 26/11/2020

Work in progress | 78% Completed

Total length of pipe - 39.58 KM( 110 MM PVC -39084 M, 100 MM GI-500 M) Pipe laid-30.27 Km,Balance to be laid 9.31km.Pipe laying ,Interconnection, Road reformation and pipe line charging work under progress. Quoted PAC- 4.22 cr Bill submitted-2.36cr

Kozhikode Project Dn AE2
Date: 10/11/2020

Work in progress | 76% Completed

Total length of pipe - 39.58 KM( 110 MM PVC -39084 M, 100 MM GI-500 M) Pipe laid-28 KM,Balance to be laid 11.58km.Pipe laying ,Interconnection, Road reformation and pipe line charging work under progress.

Attached images

img img img img img img img img

Kozhikode Project Dn AE2
Date: 12/10/2020

Work in progress | 74% Completed

Total length of pipe - 39.58 KM( 110 MM PVC -39084 M, 100 MM GI-500 M) Pipe laid-27.52 KM,Balance to be laid 12.06 KM.Pipe laying ,Interconnection, Road reformation and pipe line charging work under progress.

Kozhikode Project Dn AE2
Date: 17/09/2020

Work in progress | 73% Completed

Total length of pipe - 39.58 KM( 110 MM PVC -39084 M, 100 MM GI-500 M) Pipe already laid-27.52 KM,Balance to be laid 12.06 KM. Distribution pipe lines were already laid by PH division under various heads like SME, DRW,Deposit and MLA asset woks in the proposed locations under AMRUTH work.To avoid duplication ,this was informed in the AMRUT Core Committee meeting held on 19/5/20 and decided to arrange balance pipe line in other zones in the corporation area.Also due to heavy monsoon and Covid-19 out break ,the laying work couldnt be completed.Now road reformation and interconnction &charging work under progress

Kozhikode Project Dn AE2
Date: 19/08/2020

Work in progress | 72% Completed

Total length of pipe - 39.58 KM( 110 MM PVC -39084 M, 100 MM GI-500 M) Pipe already laid-27.52 KM,Balance to be laid 12.06 KM. Distribution pipe lines were already laid by PH division under various heads like SME, DRW,Deposit and MLA asset woks in the proposed locations under AMRUTH work.To avoid duplication ,this was informed in the AMRUT Core Committee meeting held on 19/5/20 and decided to arrange balance pipe line in other zones in the corporation area.Also due to heavy monsoon and Covid-19 out break ,the laying work couldnt be completed.

Kozhikode Project Dn AE2
Date: 18/08/2020

Work in progress | 71% Completed

Total length of pipe - 40.70 KM( 160 MM PVC-130 m, 110 MM PVC -40071 M, 100 MM GI-500 M) Pipe already laid-26.78 KM,Balance to be laid 13.92 KM. Distribution pipe lines were already laid by PH division under various heads like SME, DRW,Deposit and MLA asset woks in the proposed locations under AMRUTH work.To avoid duplication ,this was informed in the AMRUT Core Committee meeting held on 19/5/20 and decided to arrange balance pipe line in other zones in the corporation area.Also due to heavy monsoon and Covid-19 out break ,the laying work couldnt be completed.

Kozhikode Project Dn AE2
Date: 14/08/2020

Work in progress | 70% Completed

Supplying Laying and Testing of 110mm PVC pipe for a length of 27520m out of 39084m & 100mm GI Pipe for a length of 30m out of 500m.

Kozhikode Project Dn AE2
Date: 01/07/2020

Work in progress | 65% Completed

Supplying Laying and Testing of 110mm PVC pipe for a length of 25710m out of 39084m & 100mm GI Pipe for a length of 30m out of 500m.