| Project | AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in East Hill Zone |
|---|---|
| Project Code | CLTGOI0118511P7 |
| Type | Package |
| Main Project | AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Distribution Lines in 10 Zone in Kozhikode corporation |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in East Hill Zone |
| Status | Completed |
| District | Kozhikkode |
| Executing Office | Kozhikode Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 50300000 |
| TS Number | TS/3007/2018-2019 |
| Technical specification | Scope of Work- Supplying and Laying- 110mm PVC pipe -39084m 100mm GI Pipe-500m |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 15/03/2019 |
|---|---|
| Scheduled date of Completion as per agreement | 24 Sep 2019 |
| Expected date of Completion | 16/03/2021 |
| TS Date | 22 Nov 2018 |
|---|---|
| Estimate Approval | 22 Nov 2018 |
| NIT Approval | 23 Nov 2018 |
| Tender Closing | 20 Dec 2018 |
| Price bid opening | 24 Dec 2018 |
| Workorder Date | 25 Jan 2019 |
|---|---|
| NA | 15 Mar 2019 |
| Kozhikode Project Dn AE5 |
| Date: 22/09/2021 |
Work has been completed | 100% Completed
Work completed, Total expenditure Rs.36373563/- final Bill paid to contractor on 27.07.2021 including Road restoration charges . .
| Kozhikode Project Dn AE2 |
| Date: 21/04/2021 |
Work has been completed | 100% Completed
work completed.