Kozhinjampara PH Sn AE |
Date: 03/07/2024 |
Work in progress | 99% Completed
Pipe laying completed, 160 Nos FHTCSs provided & 140 Nos of FHTCs Geo tagged
Kozhinjampara PH Sn AE |
Date: 22/06/2024 |
Work in progress | 99% Completed
Pipe laying completed, 160 Nos FHTCSs provided & 140 Nos of FHTCs Geo tagged
Kozhinjampara PH Sn AE |
Date: 16/04/2024 |
Work in progress | 80% Completed
90Nos of FHTC s are provided at Meppallam & 60 nos of FHTCs are JJM Geo Tagged
Kozhinjampara PH Sn AE |
Date: 20/03/2024 |
Work in progress | 70% Completed
80mm GI pipe laying work
Kozhinjampara PH Sn AE |
Date: 16/03/2024 |
Work in progress | 50% Completed
Laying of 80mm GI work progress
Kozhinjampara PH Sn AE |
Date: 05/03/2024 |
Work in progress | 47% Completed
Supply and Laying of 80mm GI work progress
Kozhinjampara PH Sn AE |
Date: 02/03/2024 |
Work in progress | 45% Completed
Supply and Fixing of 100mm GI pipe 1002m and Supply & Fixing 80mm GI pipe 213.9m