Jal Jeevan Mission (JJM)-JJM Phase I - CWSS to Elappully, Nalleppilly, Perumatty & Pattanchery Pts- -Pipe line extension to Meppallam SC colony and other areas in Nalleppilly panchayath incluing household tap connections to these areas .-Pipeline Work

Project Jal Jeevan Mission (JJM)-JJM Phase I - CWSS to Elappully, Nalleppilly, Perumatty & Pattanchery Pts- -Pipe line extension to Meppallam SC colony and other areas in Nalleppilly panchayath incluing household tap connections to these areas .-Pipeline Work
Project Code PKDJJM082015634P1
Type Package
Main Project Jal Jeevan Mission (JJM)-JJM Phase I - CWSS to Elappully, Nalleppilly, Perumatty & Pattanchery Pts- -Pipe line extension to Meppallam SC colony and other areas in Nalleppilly panchayath incluing household tap connections to these areas .-Pipeline Work
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-JJM Phase I - CWSS to Elappully, Nalleppilly, Perumatty & Pattanchery Pts- -Pipe line extension to Meppallam SC colony and other areas in Nalleppilly panchayath incluing household tap connections to these areas .-Pipeline Work
Status On-going
District Palakkad
Executing Office Kozhinjampara PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 6299881
TS Number 18860/2023-24
Technical specification Pipe line extension to Meppallam SC colony and other areas in Nalleppilly panchayath incluing household tap connections to these areas .-Pipeline Work
Contractor UDAYAKUMAR P (Mob: 9961887377)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/01/2024
Scheduled date of Completion as per agreement 18 Apr 2023
Expected date of Completion 18/04/2024

Processing Dates

TS Date 13 Nov 2023
Estimate Approval 13 Nov 2023
NIT Approval 13 Nov 2023
Tender Closing 20 Nov 2023
Technichal Pre-Qualification 20 Nov 2023
Price bid opening 20 Nov 2023

Approval Dates

Workorder Date 05 Dec 2023
NA 18 Dec 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kozhinjampara PH Sn AE
Date: 22/06/2024

Work in progress | 99% Completed

Pipe laying completed, 160 Nos FHTCSs provided & 140 Nos of FHTCs Geo tagged .

Kozhinjampara PH Sn AE
Date: 16/04/2024

Work in progress | 80% Completed

90Nos of FHTC s are provided at Meppallam & 60 nos of FHTCs are JJM Geo Tagged.