Thrissur WW Sn - AE 1
Date: 28/06/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design.

Thrissur WW Sn - AE 1
Date: 25/06/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design.

Thrissur WW Sn - AE 1
Date: 24/06/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design.

Thrissur WW Sn - AE 1
Date: 21/06/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design.

Thrissur WW Sn - AE 1
Date: 18/06/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design.

Thrissur WW Sn - AE 1
Date: 13/06/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design.

Thrissur WW Sn - AE 1
Date: 10/06/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design.

Thrissur WW Sn - AE 1
Date: 05/06/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design.

Thrissur WW Sn - AE 1
Date: 03/06/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design.

Thrissur PH Dn EE
Date: 30/05/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design.

Thrissur WW Sn - AE 1
Date: 27/05/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design.

Thrissur WW Sn - AE 1
Date: 23/05/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design.

Thrissur WW Sn - AE 1
Date: 18/05/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design.

Thrissur WW Sn - AE 1
Date: 14/05/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design.

Thrissur WW Sn - AE 1
Date: 10/05/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design

Thrissur WW Sn - AE 1
Date: 06/05/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design

Thrissur WW Sn - AE 1
Date: 04/05/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design

Thrissur WW Sn - AE 1
Date: 02/05/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design

Thrissur WW Sn - AE 1
Date: 30/04/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design

Thrissur WW Sn - AE 1
Date: 27/04/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design

Thrissur PH Dn EE
Date: 25/04/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design

Thrissur WW Sn - AE 1
Date: 23/04/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design

Thrissur PH Dn EE
Date: 19/04/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design

Thrissur WW Sn - AE 1
Date: 16/04/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design

Thrissur WW Sn - AE 1
Date: 15/04/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design

Thrissur PH Dn EE
Date: 12/04/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design.

Thrissur WW Sn - AE 1
Date: 08/04/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design.

Thrissur WW Sn - AE 1
Date: 03/04/2024

Work in progress | 2% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design.

Thrissur WW Sn - AE 1
Date: 30/03/2024

Work in progress | 2% Completed

Soil test completed. Soil test report not submitted by the contractor.

Thrissur WW Sn - AE 1
Date: 26/03/2024

Work in progress | 2% Completed

Soil test completed. Soil test report not submitted by the contractor.

Thrissur PH Dn EE
Date: 23/03/2024

Work in progress | 2% Completed

Soil test completed. Soil test report not submitted by the contractor.

Thrissur WW Sn - AE 1
Date: 19/03/2024

Work in progress | 2% Completed

Soil test completed. Soil test report not submitted by the contractor.

Thrissur WW Sn - AE 1
Date: 15/03/2024

Work in progress | 2% Completed

Soil test completed. Soil test report not submitted by the contractor.

Thrissur PH Dn EE
Date: 14/03/2024

Work in progress | 1% Completed

Soil test completed

Thrissur WW Sn - AE 1
Date: 11/03/2024

Work in progress | 1% Completed

Soil test completed

Thrissur WW Sn - AE 1
Date: 05/03/2024

Work in progress | 1% Completed

Soil test completed

Thrissur WW Sn - AE 1
Date: 29/02/2024

Work in progress | 1% Completed

Soil test work in progress

Thrissur WW Sn - AE 1
Date: 26/02/2024

Work in progress | 1% Completed

Site hand over.Informed contractor for submitting design.

Thrissur WW Sn - AE 1
Date: 23/02/2024

Work in progress | 1% Completed

Site hand over.Informed contractor for submitting design.

Thrissur WW Sn - AE 1
Date: 19/02/2024

Work has started | 0% Completed

Agreement execution completed.

Thrissur WW Sn - AE 1
Date: 15/02/2024

Work has started | 0% Completed

Permission for construction 75 KL GLSR pressure filter and floating structure from the irrigation department. Awaiting for agreement execution

Thrissur WW Sn - AE 1
Date: 12/02/2024

Work has started | 0% Completed

Permission for construction 75 KL GLSR pressure filter and floating structure from the irrigation department. Awaiting for agreement execution

Thrissur WW Sn - AE 1
Date: 08/02/2024

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur WW Sn - AE 1
Date: 06/02/2024

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur WW Sn - AE 1
Date: 02/02/2024

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur WW Sn - AE 1
Date: 29/01/2024

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur WW Sn - AE 1
Date: 25/01/2024

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur WW Sn - AE 1
Date: 22/01/2024

Work in progress | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur WW Sn - AE 1
Date: 18/01/2024

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur WW Sn - AE 1
Date: 16/01/2024

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur WW Sn - AE 1
Date: 11/01/2024

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur WW Sn - AE 1
Date: 08/01/2024

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur WW Sn - AE 1
Date: 04/01/2024

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur WW Sn - AE 1
Date: 01/01/2024

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur WW Sn - AE 1
Date: 30/12/2023

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur WW Sn - AE 1
Date: 26/12/2023

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur WW Sn - AE 1
Date: 21/12/2023

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur WW Sn - AE 1
Date: 18/12/2023

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur WW Sn - AE 1
Date: 14/12/2023

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur WW Sn - AE 1
Date: 11/12/2023

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur PH Dn EE
Date: 08/12/2023

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023

Thrissur PH Dn EE
Date: 05/12/2023

Work has started | 0% Completed

Work order issued on 12/10/2023. Agreement executed on 28/10/2023