Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission (JJM)-Providing FHTCs in Mulankunnathukavu Pt. in Thrissur District-Phase 3-Supply, erection, Testing and commissioning of Floating Pontoon with Submerged type Pump sets and Pressure filter.-5th SLSSC- Package-VII-General Civil Work

Project Jal Jeevan Mission (JJM)-Providing FHTCs in Mulankunnathukavu Pt. in Thrissur District-Phase 3-Supply, erection, Testing and commissioning of Floating Pontoon with Submerged type Pump sets and Pressure filter.-5th SLSSC- Package-VII-General Civil Work
Project Code TCRJJM022213936P7
Type Package
Main Project Jal Jeevan Mission (JJM)-5th SLSSC -Water Supply Scheme to Mulamkunnathukavu Grama Panchayath in Thrissur District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Providing FHTCs in Mulankunnathukavu Pt. in Thrissur District-Phase 3-Supply, erection, Testing and commissioning of Floating Pontoon with Submerged type Pump sets and Pressure filter.-5th SLSSC- Package-VII-General Civil Work
Status On-going
District Thrissur
Executing Office Thrissur WW Sn 1
Agreement Number
Agreement Date
TS Amount (Rs) 21180000
TS Number WRD/KWA-CE(CR)/EST_TS/17102/2022_5_1_1 Dated: 26-07-2023
Technical specification Supply, erection, Testing and commissioning of Floating Pontoon with Submerged type Pump sets and Pressure filter.-5th SLSSC- Package-VII-General Civil Work

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 12/10/2023
Scheduled date of Completion as per agreement 27 Apr 2024
Expected date of Completion 31/07/2024

Processing Dates

TS Date 26 Jul 2023
Estimate Approval 26 Jul 2023
NIT Approval 26 Jul 2023
Tender Closing 15 Sep 2023
Technichal Pre-Qualification 15 Sep 2023
Price bid opening 16 Sep 2023

Approval Dates

Workorder Date 12 Oct 2023
NA 28 Oct 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thrissur WW Sn - AE 1
Date: 28/06/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design..

Thrissur WW Sn - AE 1
Date: 25/06/2024

Work in progress | 3% Completed

Soil test work completed informed contractor to submit the floating and 75 kl GLSR design..