| Kollam QC AE |
| Date: 17/05/2023 |
Work in progress | 95% Completed
Sensors traced back from courier provider and collected it is installed and now the IOT system is completely set up. Tracing the data to main servor is in progress now
| Kollam QC AE |
| Date: 16/05/2023 |
Work in progress | 92% Completed
As informed the sensors are returned from the wtp site and it is traced back and waiting for return
| Kollam QC AE |
| Date: 13/05/2023 |
Work in progress | 91% Completed
Sensors rest of the analyzers are despatched waiting for arrival at site
| Kollam QC AE |
| Date: 09/05/2023 |
Work in progress | 91% Completed
Sensors yet to arrive
| Kollam QC AE |
| Date: 04/05/2023 |
Work in progress | 90% Completed
Pending Bills HomeState Plan 2022-23-Supply Installation & The analyzer and sensors arrived from abroad(Austria) and it should reach the site. Expecting to complete the work this week sensors yet to arrive at the site.
| Kollam QC AE |
| Date: 27/04/2023 |
Work in progress | 90% Completed
The analyzer and sensors arrived from abroad(Austria) and it should reach the site. Expecting to complete the work in next week.
| Kollam QC AE |
| Date: 18/04/2023 |
| Kollam QC AE |
| Date: 13/04/2023 |
| Kollam QC AE |
| Date: 01/04/2023 |
Work in progress | 50% Completed
Plumping electrical work planned next week analysor and sensor to arrive
| Kollam QC AE |
| Date: 23/03/2023 |
Work in progress | 38% Completed
Installation fixed next week delayed due to unavailability of sub contractor to do the plumbing work as informed by the firm . Told that sensor installation is planned in the coming week as the sub contractor has agreed the same time
| Kollam QC AE |
| Date: 15/03/2023 |
Work in progress | 30% Completed
Equipments to arrive few sensors recieved installation planned in next week
| Kollam QC AE |
| Date: 02/03/2023 |
Work in progress | 2% Completed
Endpoint selected and sensors to arrive installation points fixed sub contractor to be selected for installation of sensors. Old chemical lab selected
| Kollam QC AE |
| Date: 20/02/2023 |
Work in progress | 1% Completed
Engineer visited the plant sensors installation site fixed
| Kollam QC AE |
| Date: 08/02/2023 |
Work in progress | 0% Completed
Sensors yet to arrive
| Kollam QC AE |
| Date: 30/01/2023 |
Work has started | 0% Completed
Agreement Executed Work not started
| Kollam QC AE |
| Date: 17/01/2023 |
Work has started | 0% Completed
Agreement executed work to be started
| Kollam QC AE |
| Date: 09/01/2023 |
Work has started | 0% Completed
Agreement to be executed
| Kollam QC AE |
| Date: 04/01/2023 |
Work has started | 0% Completed
Work Order Issued
| Kollam QC AE |
| Date: 29/12/2022 |
Work has started | 0% Completed
Work order to be issued
| Kollam QC AE |
| Date: 23/12/2022 |
Work has started | 0% Completed
Tender opening on 28-12-2022
| Kollam QC AE |
| Date: 09/12/2022 |
Work has started | 0% Completed
Tender extended
| Kollam QC AE |
| Date: 19/11/2022 |
Work has started | 0% Completed
Tender opening 25/11/22
| Kollam QC AE |
| Date: 12/11/2022 |
Work has started | 0% Completed
Tender extended
| Kollam QC AE |
| Date: 29/10/2022 |
Work has started | 0% Completed
Tender extended opening 11/11/2022
| Kollam QC AE |
| Date: 20/10/2022 |
Work has started | 0% Completed
Tender opening on 25/10/2022
| Kollam QC AE |
| Date: 13/10/2022 |
Work has started | 0% Completed
Work called for tender
| Kollam QC AE |
| Date: 30/09/2022 |
Work has started | 0% Completed
TS approved and reverted to Sub Division for tendering
| Kollam QC AE |
| Date: 26/09/2022 |
Work has started | 0% Completed
OD items approved by CE estimate send to EE for TS approval after corrections
| Kollam QC AE |
| Date: 13/09/2022 |
Work has started | 0% Completed
Estimate with CE central region for checking and awaiting for TS approval
| Kollam QC AE |
| Date: 09/09/2022 |
Work has started | 0% Completed
ESTIMATE AWAITING FOR TS APPROVAL
| Kollam QC AE |
| Date: 06/09/2022 |
Work has started | 0% Completed
Estimate is with CE central region for TS Approval
| Kollam QC AE |
| Date: 02/09/2022 |
Work has started | 0% Completed
Estimate Awaiting approval WIth CE Central region