Kollam QC AE
Date: 17/05/2023

Work in progress | 95% Completed

Sensors traced back from courier provider and collected it is installed and now the IOT system is completely set up. Tracing the data to main servor is in progress now

Kollam QC AE
Date: 16/05/2023

Work in progress | 92% Completed

As informed the sensors are returned from the wtp site and it is traced back and waiting for return

Kollam QC AE
Date: 13/05/2023

Work in progress | 91% Completed

Sensors rest of the analyzers are despatched waiting for arrival at site

Kollam QC AE
Date: 09/05/2023

Work in progress | 91% Completed

Sensors yet to arrive

Kollam QC AE
Date: 04/05/2023

Work in progress | 90% Completed

Pending Bills HomeState Plan 2022-23-Supply Installation & The analyzer and sensors arrived from abroad(Austria) and it should reach the site. Expecting to complete the work this week sensors yet to arrive at the site.

Kollam QC AE
Date: 27/04/2023

Work in progress | 90% Completed

The analyzer and sensors arrived from abroad(Austria) and it should reach the site. Expecting to complete the work in next week.

Kollam QC AE
Date: 18/04/2023

Work in progress | 90% Completed

Plumping work, sensor point installation panel board compressor installations completed. Analyzer and sensors have not arrived to be installed to complete the work

Attached images

img

Kollam QC AE
Date: 13/04/2023

Work in progress | 77% Completed

Electrical installation wiring work completed

Attached images

img

Kollam QC AE
Date: 01/04/2023

Work in progress | 50% Completed

Plumping electrical work planned next week analysor and sensor to arrive

Kollam QC AE
Date: 23/03/2023

Work in progress | 38% Completed

Installation fixed next week delayed due to unavailability of sub contractor to do the plumbing work as informed by the firm . Told that sensor installation is planned in the coming week as the sub contractor has agreed the same time

Kollam QC AE
Date: 15/03/2023

Work in progress | 30% Completed

Equipments to arrive few sensors recieved installation planned in next week

Kollam QC AE
Date: 02/03/2023

Work in progress | 2% Completed

Endpoint selected and sensors to arrive installation points fixed sub contractor to be selected for installation of sensors. Old chemical lab selected

Kollam QC AE
Date: 20/02/2023

Work in progress | 1% Completed

Engineer visited the plant sensors installation site fixed

Kollam QC AE
Date: 08/02/2023

Work in progress | 0% Completed

Sensors yet to arrive

Kollam QC AE
Date: 30/01/2023

Work has started | 0% Completed

Agreement Executed Work not started

Kollam QC AE
Date: 17/01/2023

Work has started | 0% Completed

Agreement executed work to be started

Kollam QC AE
Date: 09/01/2023

Work has started | 0% Completed

Agreement to be executed

Kollam QC AE
Date: 04/01/2023

Work has started | 0% Completed

Work Order Issued

Kollam QC AE
Date: 29/12/2022

Work has started | 0% Completed

Work order to be issued

Kollam QC AE
Date: 23/12/2022

Work has started | 0% Completed

Tender opening on 28-12-2022

Kollam QC AE
Date: 09/12/2022

Work has started | 0% Completed

Tender extended

Kollam QC AE
Date: 19/11/2022

Work has started | 0% Completed

Tender opening 25/11/22

Kollam QC AE
Date: 12/11/2022

Work has started | 0% Completed

Tender extended

Kollam QC AE
Date: 29/10/2022

Work has started | 0% Completed

Tender extended opening 11/11/2022

Kollam QC AE
Date: 20/10/2022

Work has started | 0% Completed

Tender opening on 25/10/2022

Kollam QC AE
Date: 13/10/2022

Work has started | 0% Completed

Work called for tender

Kollam QC AE
Date: 30/09/2022

Work has started | 0% Completed

TS approved and reverted to Sub Division for tendering

Kollam QC AE
Date: 26/09/2022

Work has started | 0% Completed

OD items approved by CE estimate send to EE for TS approval after corrections

Kollam QC AE
Date: 13/09/2022

Work has started | 0% Completed

Estimate with CE central region for checking and awaiting for TS approval

Kollam QC AE
Date: 09/09/2022

Work has started | 0% Completed

ESTIMATE AWAITING FOR TS APPROVAL

Kollam QC AE
Date: 06/09/2022

Work has started | 0% Completed

Estimate is with CE central region for TS Approval

Kollam QC AE
Date: 02/09/2022

Work has started | 0% Completed

Estimate Awaiting approval WIth CE Central region