| Pathanapuram WS Sn - AE |
| Date: 10/05/2023 |
Work has been completed | 100% Completed
Completed
| Pathanapuram WS Sn - AE |
| Date: 09/05/2023 |
Work in progress | 70% Completed
Work in Progress
| Pathanapuram WS Sn - AE |
| Date: 06/05/2023 |
Work in progress | 70% Completed
Work in Progress
| Pathanapuram WS Sn - AE |
| Date: 03/05/2023 |
Work in progress | 70% Completed
Work in progress
| Pathanapuram WS Sn - AE |
| Date: 29/04/2023 |
Work in progress | 70% Completed
Work in Progress
| Pathanapuram WS Sn - AE |
| Date: 26/04/2023 |
Work in progress | 70% Completed
Work in progress
| Pathanapuram WS Sn - AE |
| Date: 24/04/2023 |
Work in progress | 70% Completed
Work in progress
| Pathanapuram WS Sn - AE |
| Date: 18/04/2023 |
Work in progress | 70% Completed
Work in Progress
| Pathanapuram WS Sn - AE |
| Date: 13/04/2023 |
Work in progress | 70% Completed
Work in progress
| Pathanapuram WS Sn - AE |
| Date: 10/04/2023 |
Work in progress | 70% Completed
Work in Progress
| Pathanapuram WS Sn - AE |
| Date: 03/04/2023 |
Work in progress | 70% Completed
Work in Progress
| Pathanapuram WS Sn - AE |
| Date: 30/03/2023 |
Work in progress | 70% Completed
Work in Progress
| Pathanapuram WS Sn - AE |
| Date: 27/03/2023 |
Work in progress | 70% Completed
Work in progress
| Pathanapuram WS Sn - AE |
| Date: 24/03/2023 |
Work in progress | 70% Completed
Work in progress
| Pathanapuram WS Sn - AE |
| Date: 20/03/2023 |
Work in progress | 70% Completed
Work in progress
| Pathanapuram WS Sn - AE |
| Date: 15/03/2023 |
Work in progress | 70% Completed
Work in progress
| Pathanapuram WS Sn - AE |
| Date: 10/03/2023 |
Work in progress | 70% Completed
Work in progres
| Pathanapuram WS Sn - AE |
| Date: 07/03/2023 |
Work in progress | 70% Completed
Work in progress
| Pathanapuram WS Sn - AE |
| Date: 04/03/2023 |
Work in progress | 70% Completed
Work in progress
| Pathanapuram WS Sn - AE |
| Date: 02/03/2023 |
Work in progress | 70% Completed
Work in progress
| Pathanapuram WS Sn - AE |
| Date: 22/02/2023 |
Work in progress | 70% Completed
Work in progress
| Kottarakkara PH Dn EE |
| Date: 16/02/2023 |
Work in progress | 70% Completed
1916 FHTCs Completed. WTP renovation in progress