Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Oachira AE
Date: 15/02/2024

Work has been completed | 100% Completed

Work completed

Chavara AEE
Date: 14/02/2024

Work in progress | 75% Completed

75% completed. Pipe laying completed. meter could n't be placed as ownership certificate was pending from municipality. Now ownership received. application entered in etapp . amount to be remitted by contractor.

Oachira AE
Date: 13/02/2024

Work in progress | 75% Completed

Connection process ongoing.

Oachira AE
Date: 12/02/2024

Work in progress | 75% Completed

Connection process ongoing.

Oachira AE
Date: 07/02/2024

Work in progress | 70% Completed

Connection process ongoing.

Oachira AE
Date: 04/02/2024

Work in progress | 70% Completed

Connection process ongoing.

Oachira AE
Date: 01/02/2024

Work in progress | 70% Completed

Connection process ongoing.

Oachira AE
Date: 29/01/2024

Work in progress | 20% Completed

Letter sent to the Municipal Secretary for getting documents

Oachira AE
Date: 25/01/2024

Work in progress | 20% Completed

Letter sent to the Municipal Secretary for getting documents

Oachira AE
Date: 22/01/2024

Work in progress | 20% Completed

Letter sent to the Municipal Secretary for getting documents

Oachira AE
Date: 18/01/2024

Work in progress | 20% Completed

Letter sent to the Municipal Secretary for getting documents

Oachira AE
Date: 16/01/2024

Work in progress | 20% Completed

Letter sent to the Municipal Secretary for getting documents

Oachira AE
Date: 11/01/2024

Work in progress | 20% Completed

Letter sent to the Municipal Secretary for getting documents

Oachira AE
Date: 08/01/2024

Work in progress | 20% Completed

Letter sent to the Municipal Secretary for getting documents

Oachira AE
Date: 03/01/2024

Work in progress | 20% Completed

Letter sent to the Municipal Secretary for getting documents

Chavara AEE
Date: 01/01/2024

Work in progress | 20% Completed

pipe supplied .Work could not be started as consent for pipe laying not obtained

Oachira AE
Date: 30/12/2023

Work in progress | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 27/12/2023

Work in progress | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 18/12/2023

Work in progress | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 11/12/2023

Work in progress | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 06/12/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 30/11/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 28/11/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 25/11/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 23/11/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 20/11/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 16/11/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 13/11/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 10/11/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 06/11/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 02/11/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 30/10/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 25/10/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 18/10/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 16/10/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 13/10/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 09/10/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 06/10/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 03/10/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 29/09/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 25/09/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 23/09/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 19/09/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 16/09/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 14/09/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 11/09/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 08/09/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 07/09/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 05/09/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 01/09/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 22/08/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 19/08/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 16/08/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 14/08/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 11/08/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 07/08/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 05/08/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 02/08/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 31/07/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 29/07/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 26/07/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 24/07/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 22/07/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 19/07/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 18/07/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 14/07/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 12/07/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 10/07/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 04/07/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 01/07/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 27/06/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 24/06/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 20/06/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 16/06/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 12/06/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 06/06/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 02/06/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 30/05/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 27/05/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 23/05/2023

Work has started | 0% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 20/05/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 17/05/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 15/05/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 12/05/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 10/05/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 08/05/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 04/05/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 02/05/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 27/04/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 24/04/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 17/04/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 12/04/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 10/04/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 05/04/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 01/04/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 31/03/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 29/03/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 27/03/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 24/03/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 22/03/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 20/03/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 17/03/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 15/03/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 13/03/2023

Work in progress | 1% Completed

agreement executed on 23/01/2023

Oachira AE
Date: 10/03/2023

Work in progress | 1% Completed

Agreement executive on 23/1/2023

Oachira AE
Date: 08/03/2023

Work in progress | 1% Completed

Agreement executive on 23/1/2023

Oachira AE
Date: 06/03/2023

Work in progress | 1% Completed

Agreement executive on 23/1/2023

Oachira AE
Date: 03/03/2023

Work in progress | 1% Completed

Agreement executive on 23/1/2023

Oachira AE
Date: 01/03/2023

Work in progress | 1% Completed

Agreement executive on 23/1/2023

Chavara AEE
Date: 27/02/2023

Work in progress | 1% Completed

Agreement executive on 23/1/2023