DEPOSIT-Deposit work Karunagappally Municipality-- CWSS to Oachira, Alappad, Clappana and Karunagappally - Water supply connection to Gas Crematorium, in Division-19 of Karunagappally Municipality.-General Civil Work

Project DEPOSIT-Deposit work Karunagappally Municipality-- CWSS to Oachira, Alappad, Clappana and Karunagappally - Water supply connection to Gas Crematorium, in Division-19 of Karunagappally Municipality.-General Civil Work
Project Code KLMDEPO112213604P1
Type Package
Main Project DEPOSIT-Deposit work Karunagappally Municipality-- CWSS to Oachira, Alappad, Clappana and Karunagappally - Water supply connection to Gas Crematorium, in Division-19 of Karunagappally Municipality.-General Civil Work
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Deposit work Karunagappally Municipality-- CWSS to Oachira, Alappad, Clappana and Karunagappally - Water supply connection to Gas Crematorium, in Division-19 of Karunagappally Municipality.-General Civil Work
Status Completed
District Kollam
Executing Office Oachira PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 40000
TS Number WRD/KWA-CEP/EST-TS/101/2022-5-7-6
Technical specification nil

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 23/01/2023
Scheduled date of Completion as per agreement 21 Mar 2023
Expected date of Completion 20/02/2024

Processing Dates

TS Date 20 Jan 2023
Estimate Approval 20 Jan 2023
NIT Approval 20 Jan 2023
Tender Closing 21 Jan 2023
Technichal Pre-Qualification 21 Jan 2023
Price bid opening 21 Jan 2023

Approval Dates

Workorder Date 23 Jan 2023
NA 23 Jan 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Oachira AE
Date: 15/02/2024

Work has been completed | 100% Completed

Work completed.

Chavara AEE
Date: 14/02/2024

Work in progress | 75% Completed

75% completed. Pipe laying completed. meter could n't be placed as ownership certificate was pending from municipality. Now ownership received. application entered in etapp . amount to be remitted by contractor..