Thaliparamba WS Dn EE
Date: 26/06/2024

Work in progress | 31% Completed

115.046 km pipe Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 22/06/2024

Work in progress | 31% Completed

114.26 km pipe Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 18/06/2024

Work in progress | 31% Completed

114.26 km pipe Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 14/06/2024

Work in progress | 30% Completed

113.5 km pipe Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 10/06/2024

Work in progress | 30% Completed

112.57kmPVC /DI pipe Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 04/06/2024

Work in progress | 30% Completed

112.57kmPVC /DI pipe Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 31/05/2024

Work in progress | 30% Completed

112.57kmPVC /DI pipe Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 28/05/2024

Work in progress | 30% Completed

112.48km PVC/DI Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 25/05/2024

Work in progress | 30% Completed

112.48km PVC/DI Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 23/05/2024

Work in progress | 30% Completed

112.48km PVC/DI Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 20/05/2024

Work in progress | 30% Completed

112.48km PVC/DI Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 18/05/2024

Work in progress | 30% Completed

112.48km PVC/DI Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 15/05/2024

Work in progress | 30% Completed

112.48km PVC/DI Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 13/05/2024

Work in progress | 30% Completed

112.48km PVC Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 10/05/2024

Work in progress | 30% Completed

112.48km PVC Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 06/05/2024

Work in progress | 30% Completed

112.48km PVC Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 02/05/2024

Work in progress | 30% Completed

112.48km PVC Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 29/04/2024

Work in progress | 30% Completed

112.48km PVC Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 25/04/2024

Work in progress | 30% Completed

112.48km PVC Layed, 159 number HTC provided.

Thaliparamba WS Dn EE
Date: 22/04/2024

Work in progress | 30% Completed

112.48km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 19/04/2024

Work in progress | 30% Completed

112.48km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 17/04/2024

Work in progress | 30% Completed

112.38km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 15/04/2024

Work in progress | 30% Completed

112.27km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 11/04/2024

Work in progress | 30% Completed

112.21km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 08/04/2024

Work in progress | 30% Completed

112.15km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 05/04/2024

Work in progress | 30% Completed

112.11 km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 02/04/2024

Work in progress | 30% Completed

112.11 km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 30/03/2024

Work in progress | 30% Completed

112.11 km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 27/03/2024

Work in progress | 30% Completed

112.11 km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 25/03/2024

Work in progress | 30% Completed

112.11 km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 22/03/2024

Work in progress | 30% Completed

111.79 km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 20/03/2024

Work in progress | 30% Completed

111.56 km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 18/03/2024

Work in progress | 30% Completed

111.43 km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 15/03/2024

Work in progress | 30% Completed

111.36 km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 13/03/2024

Work in progress | 30% Completed

111.21 km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 11/03/2024

Work in progress | 30% Completed

111.11 km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 06/03/2024

Work in progress | 30% Completed

110.86km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 04/03/2024

Work in progress | 30% Completed

110.68km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 01/03/2024

Work in progress | 30% Completed

110.36km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 28/02/2024

Work in progress | 30% Completed

110.36km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 26/02/2024

Work in progress | 30% Completed

109.90km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 24/02/2024

Work in progress | 30% Completed

109.90km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 22/02/2024

Work in progress | 30% Completed

109.90km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 20/02/2024

Work in progress | 30% Completed

109.90km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 17/02/2024

Work in progress | 30% Completed

109.90km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 14/02/2024

Work in progress | 30% Completed

109.76km PVC Layed, 159 number FHTC provided

Thaliparamba WS Dn EE
Date: 12/02/2024

Work in progress | 30% Completed

108.78km PVC Layed,141 number FHTC provided

Thaliparamba WS Dn EE
Date: 08/02/2024

Work in progress | 30% Completed

108.78km PVC Layed,141 number FHTC provided

Thaliparamba WS Dn EE
Date: 05/02/2024

Work in progress | 30% Completed

108.78km PVC Layed,141 number FHTC provided

Thaliparamba WS Dn EE
Date: 02/02/2024

Work in progress | 30% Completed

108.78km PVC Layed,141 number FHTC provided

Thaliparamba WS Dn EE
Date: 31/01/2024

Work in progress | 30% Completed

108.66km PVC Layed,141 number FHTC provided

Thaliparamba WS Dn EE
Date: 29/01/2024

Work in progress | 30% Completed

108.10km PVC Layed,118 number FHTC provided

Thaliparamba WS Dn EE
Date: 27/01/2024

Work in progress | 30% Completed

108.04km PVC Layed,118 number FHTC provided

Thaliparamba WS Dn EE
Date: 24/01/2024

Work in progress | 29% Completed

107.77km PVC Layed,118 number FHTC provided

Thaliparamba WS Dn EE
Date: 22/01/2024

Work in progress | 29% Completed

107.77km PVC Layed,118 number FHTC provided

Thaliparamba WS Dn EE
Date: 19/01/2024

Work in progress | 29% Completed

107.25 km PVC Layed,115 number FHTC provided

Thaliparamba WS Dn EE
Date: 17/01/2024

Work in progress | 29% Completed

106.81 km PVC Layed,115 number FHTC provided

Thaliparamba WS Dn EE
Date: 15/01/2024

Work in progress | 29% Completed

105.55 km PVC Layed,115 number FHTC provided

Thaliparamba WS Dn EE
Date: 11/01/2024

Work in progress | 29% Completed

104.42 km PVC Layed,75 number FHTC provided

Thaliparamba WS Dn EE
Date: 08/01/2024

Work in progress | 10% Completed

103.06 km PVC Layed,75 number FHTC provided

Thaliparamba WS Dn EE
Date: 05/01/2024

Work in progress | 10% Completed

100.96 km PVC Layed,56 number FHTC provided

Thaliparamba WS Dn EE
Date: 03/01/2024

Work in progress | 10% Completed

100.52 km PVC Layed,56 number FHTC provided

Thaliparamba WS Dn EE
Date: 01/01/2024

Work in progress | 10% Completed

95.74 km PVC Layed,35 number FHTC provided

Thaliparamba WS Dn EE
Date: 28/12/2023

Work in progress | 10% Completed

95.74 km PVC Layed,35 number FHTC provided

Thaliparamba WS Dn EE
Date: 26/12/2023

Work in progress | 10% Completed

95.74 km PVC Layed,35 number FHTC provided

Thaliparamba WS Dn EE
Date: 22/12/2023

Work in progress | 10% Completed

90 km PVC Layed,35 number FHTC provided

Thaliparamba WS Dn EE
Date: 20/12/2023

Work in progress | 10% Completed

86.99km PVC Layed

Thaliparamba WS Dn EE
Date: 18/12/2023

Work in progress | 10% Completed

67 km PVC Layed

Thaliparamba WS Dn EE
Date: 15/12/2023

Work in progress | 10% Completed

67 km PVC Layed

Thaliparamba WS Dn EE
Date: 13/12/2023

Work in progress | 10% Completed

57 km PVC Layed

Thaliparamba WS Dn EE
Date: 11/12/2023

Work in progress | 9% Completed

pipe laying 48 km completed

Thaliparamba WS Dn EE
Date: 08/12/2023

Work in progress | 9% Completed

pipe laying 48 km completed

Thaliparamba WS Dn EE
Date: 06/12/2023

Work in progress | 9% Completed

pipe laying 40 km completed

Thaliparamba WS Dn EE
Date: 04/12/2023

Work in progress | 9% Completed

pipe laying 35 km completed

Thaliparamba WS Dn EE
Date: 02/12/2023

Work in progress | 9% Completed

pipe laying 35 km completed

Thaliparamba WS Dn EE
Date: 30/11/2023

Work in progress | 9% Completed

pipe laying 35 km completed