Thaliparamba WS Dn EE |
Date: 26/06/2024 |
Work in progress | 31% Completed
115.046 km pipe Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 22/06/2024 |
Work in progress | 31% Completed
114.26 km pipe Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 18/06/2024 |
Work in progress | 31% Completed
114.26 km pipe Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 14/06/2024 |
Work in progress | 30% Completed
113.5 km pipe Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 10/06/2024 |
Work in progress | 30% Completed
112.57kmPVC /DI pipe Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 04/06/2024 |
Work in progress | 30% Completed
112.57kmPVC /DI pipe Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 31/05/2024 |
Work in progress | 30% Completed
112.57kmPVC /DI pipe Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 28/05/2024 |
Work in progress | 30% Completed
112.48km PVC/DI Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 25/05/2024 |
Work in progress | 30% Completed
112.48km PVC/DI Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 23/05/2024 |
Work in progress | 30% Completed
112.48km PVC/DI Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 20/05/2024 |
Work in progress | 30% Completed
112.48km PVC/DI Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 18/05/2024 |
Work in progress | 30% Completed
112.48km PVC/DI Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 15/05/2024 |
Work in progress | 30% Completed
112.48km PVC/DI Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 13/05/2024 |
Work in progress | 30% Completed
112.48km PVC Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 10/05/2024 |
Work in progress | 30% Completed
112.48km PVC Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 06/05/2024 |
Work in progress | 30% Completed
112.48km PVC Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 02/05/2024 |
Work in progress | 30% Completed
112.48km PVC Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 29/04/2024 |
Work in progress | 30% Completed
112.48km PVC Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 25/04/2024 |
Work in progress | 30% Completed
112.48km PVC Layed, 159 number HTC provided.
Thaliparamba WS Dn EE |
Date: 22/04/2024 |
Work in progress | 30% Completed
112.48km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 19/04/2024 |
Work in progress | 30% Completed
112.48km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 17/04/2024 |
Work in progress | 30% Completed
112.38km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 15/04/2024 |
Work in progress | 30% Completed
112.27km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 11/04/2024 |
Work in progress | 30% Completed
112.21km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 08/04/2024 |
Work in progress | 30% Completed
112.15km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 05/04/2024 |
Work in progress | 30% Completed
112.11 km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 02/04/2024 |
Work in progress | 30% Completed
112.11 km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 30/03/2024 |
Work in progress | 30% Completed
112.11 km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 27/03/2024 |
Work in progress | 30% Completed
112.11 km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 25/03/2024 |
Work in progress | 30% Completed
112.11 km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 22/03/2024 |
Work in progress | 30% Completed
111.79 km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 20/03/2024 |
Work in progress | 30% Completed
111.56 km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 18/03/2024 |
Work in progress | 30% Completed
111.43 km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 15/03/2024 |
Work in progress | 30% Completed
111.36 km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 13/03/2024 |
Work in progress | 30% Completed
111.21 km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 11/03/2024 |
Work in progress | 30% Completed
111.11 km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 06/03/2024 |
Work in progress | 30% Completed
110.86km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 04/03/2024 |
Work in progress | 30% Completed
110.68km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 01/03/2024 |
Work in progress | 30% Completed
110.36km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 28/02/2024 |
Work in progress | 30% Completed
110.36km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 26/02/2024 |
Work in progress | 30% Completed
109.90km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 24/02/2024 |
Work in progress | 30% Completed
109.90km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 22/02/2024 |
Work in progress | 30% Completed
109.90km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 20/02/2024 |
Work in progress | 30% Completed
109.90km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 17/02/2024 |
Work in progress | 30% Completed
109.90km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 14/02/2024 |
Work in progress | 30% Completed
109.76km PVC Layed, 159 number FHTC provided
Thaliparamba WS Dn EE |
Date: 12/02/2024 |
Work in progress | 30% Completed
108.78km PVC Layed,141 number FHTC provided
Thaliparamba WS Dn EE |
Date: 08/02/2024 |
Work in progress | 30% Completed
108.78km PVC Layed,141 number FHTC provided
Thaliparamba WS Dn EE |
Date: 05/02/2024 |
Work in progress | 30% Completed
108.78km PVC Layed,141 number FHTC provided
Thaliparamba WS Dn EE |
Date: 02/02/2024 |
Work in progress | 30% Completed
108.78km PVC Layed,141 number FHTC provided
Thaliparamba WS Dn EE |
Date: 31/01/2024 |
Work in progress | 30% Completed
108.66km PVC Layed,141 number FHTC provided
Thaliparamba WS Dn EE |
Date: 29/01/2024 |
Work in progress | 30% Completed
108.10km PVC Layed,118 number FHTC provided
Thaliparamba WS Dn EE |
Date: 27/01/2024 |
Work in progress | 30% Completed
108.04km PVC Layed,118 number FHTC provided
Thaliparamba WS Dn EE |
Date: 24/01/2024 |
Work in progress | 29% Completed
107.77km PVC Layed,118 number FHTC provided
Thaliparamba WS Dn EE |
Date: 22/01/2024 |
Work in progress | 29% Completed
107.77km PVC Layed,118 number FHTC provided
Thaliparamba WS Dn EE |
Date: 19/01/2024 |
Work in progress | 29% Completed
107.25 km PVC Layed,115 number FHTC provided
Thaliparamba WS Dn EE |
Date: 17/01/2024 |
Work in progress | 29% Completed
106.81 km PVC Layed,115 number FHTC provided
Thaliparamba WS Dn EE |
Date: 15/01/2024 |
Work in progress | 29% Completed
105.55 km PVC Layed,115 number FHTC provided
Thaliparamba WS Dn EE |
Date: 11/01/2024 |
Work in progress | 29% Completed
104.42 km PVC Layed,75 number FHTC provided
Thaliparamba WS Dn EE |
Date: 08/01/2024 |
Work in progress | 10% Completed
103.06 km PVC Layed,75 number FHTC provided
Thaliparamba WS Dn EE |
Date: 05/01/2024 |
Work in progress | 10% Completed
100.96 km PVC Layed,56 number FHTC provided
Thaliparamba WS Dn EE |
Date: 03/01/2024 |
Work in progress | 10% Completed
100.52 km PVC Layed,56 number FHTC provided
Thaliparamba WS Dn EE |
Date: 01/01/2024 |
Work in progress | 10% Completed
95.74 km PVC Layed,35 number FHTC provided
Thaliparamba WS Dn EE |
Date: 28/12/2023 |
Work in progress | 10% Completed
95.74 km PVC Layed,35 number FHTC provided
Thaliparamba WS Dn EE |
Date: 26/12/2023 |
Work in progress | 10% Completed
95.74 km PVC Layed,35 number FHTC provided
Thaliparamba WS Dn EE |
Date: 22/12/2023 |
Work in progress | 10% Completed
90 km PVC Layed,35 number FHTC provided
Thaliparamba WS Dn EE |
Date: 20/12/2023 |
Work in progress | 10% Completed
86.99km PVC Layed
Thaliparamba WS Dn EE |
Date: 18/12/2023 |
Work in progress | 10% Completed
67 km PVC Layed
Thaliparamba WS Dn EE |
Date: 15/12/2023 |
Work in progress | 10% Completed
67 km PVC Layed
Thaliparamba WS Dn EE |
Date: 13/12/2023 |
Work in progress | 10% Completed
57 km PVC Layed
Thaliparamba WS Dn EE |
Date: 11/12/2023 |
Work in progress | 9% Completed
pipe laying 48 km completed
Thaliparamba WS Dn EE |
Date: 08/12/2023 |
Work in progress | 9% Completed
pipe laying 48 km completed
Thaliparamba WS Dn EE |
Date: 06/12/2023 |
Work in progress | 9% Completed
pipe laying 40 km completed
Thaliparamba WS Dn EE |
Date: 04/12/2023 |
Work in progress | 9% Completed
pipe laying 35 km completed
Thaliparamba WS Dn EE |
Date: 02/12/2023 |
Work in progress | 9% Completed
pipe laying 35 km completed
Thaliparamba WS Dn EE |
Date: 30/11/2023 |
Work in progress | 9% Completed
pipe laying 35 km completed