Project | JJM-Kannur District-Chengalayi Grama panchayath-WSS to Chengalayi Panchayath- Construction of 2 Nos OHSR ,Supplying and Laying gravity main, Pumping main, Supply and errection of pumpsets and Laying distribution system and Providing FHTCs |
---|---|
Project Code | KNRJJM092114940P1 |
Type | Package |
Main Project | JJM-Kannur District-Chengalayi Grama panchayath-WSS to Chengalayi Panchayath- Construction of 2 Nos OHSR ,Supplying and Laying gravity main, Pumping main, Supply and errection of pumpsets and Laying distribution system and Providing FHTCs |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM-Kannur District-Chengalayi Grama panchayath-WSS to Chengalayi Panchayath- Construction of 2 Nos OHSR ,Supplying and Laying gravity main, Pumping main, Supply and errection of pumpsets and Laying distribution system and Providing FHTCs |
Status | On-going |
District | Kannur |
Executing Office | Irikkur WS Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | |
TS Number | |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | Date is not specified |
Thaliparamba WS Dn EE |
Date: 26/06/2024 |
Work in progress | 31% Completed
115.046 km pipe Layed, 159 number HTC provided..
Thaliparamba WS Dn EE |
Date: 22/06/2024 |
Work in progress | 31% Completed
114.26 km pipe Layed, 159 number HTC provided..