Oachira AE
Date: 02/05/2023

Work has been completed | 100% Completed

work completed on 28/04/2023

Oachira AE
Date: 27/04/2023

Work in progress | 90% Completed

pipe line completed , balance work interconnection only

Oachira AE
Date: 24/04/2023

Work in progress | 52% Completed

work in progress

Oachira AE
Date: 17/04/2023

Work in progress | 52% Completed

work in progress

Oachira AE
Date: 12/04/2023

Work in progress | 52% Completed

work in progress

Oachira AE
Date: 10/04/2023

Work in progress | 51% Completed

work in progress

Oachira AE
Date: 05/04/2023

Work in progress | 51% Completed

work in progress

Oachira AE
Date: 01/04/2023

Work in progress | 51% Completed

work in progress

Oachira AE
Date: 31/03/2023

Work in progress | 51% Completed

work in progress

Oachira AE
Date: 29/03/2023

Work in progress | 51% Completed

work in progress

Oachira AE
Date: 27/03/2023

Work in progress | 51% Completed

work in progress

Oachira AE
Date: 24/03/2023

Work in progress | 50% Completed

work in progress

Oachira AE
Date: 22/03/2023

Work in progress | 50% Completed

work in progress

Oachira AE
Date: 20/03/2023

Work in progress | 18% Completed

work in progress

Oachira AE
Date: 17/03/2023

Work in progress | 17% Completed

work in progress

Oachira AE
Date: 15/03/2023

Work in progress | 17% Completed

work in progress

Oachira AE
Date: 13/03/2023

Work in progress | 17% Completed

work in progress

Oachira AE
Date: 10/03/2023

Work in progress | 17% Completed

work in progress

Oachira AE
Date: 08/03/2023

Work in progress | 17% Completed

work in progress

Oachira AE
Date: 06/03/2023

Work in progress | 16% Completed

work in progress

Oachira AE
Date: 03/03/2023

Work in progress | 16% Completed

work in progress

Oachira AE
Date: 01/03/2023

Work in progress | 16% Completed

work in progress

Oachira AE
Date: 27/02/2023

Work in progress | 16% Completed

work in progress

Oachira AE
Date: 24/02/2023

Work in progress | 16% Completed

work in progress

Oachira AE
Date: 22/02/2023

Work in progress | 16% Completed

work in progress

Oachira AE
Date: 20/02/2023

Work in progress | 15% Completed

work in progress

Oachira AE
Date: 16/02/2023

Work in progress | 15% Completed

Work in progress

Oachira AE
Date: 14/02/2023

Work in progress | 14% Completed

Supply order issued for pipes,75 mm PVC pipe laying started

Oachira AE
Date: 10/02/2023

Work in progress | 14% Completed

Supply order issued for pipes,75 mm PVC pipe laying started

Oachira AE
Date: 08/02/2023

Work in progress | 13% Completed

Supply order issued for pipes,75 mm PVC pipe laying started

Oachira AE
Date: 06/02/2023

Work in progress | 13% Completed

Supply order issued for pipes,75 mm PVC pipe laying started

Oachira AE
Date: 04/02/2023

Work in progress | 13% Completed

Supply order issued for pipes, 75 mm PVC pipe laying started

Oachira AE
Date: 01/02/2023

Work in progress | 13% Completed

Supply order issued for pipes, 75 mm PVC pipe laying started

Oachira AE
Date: 30/01/2023

Work in progress | 12% Completed

Work started

Oachira AE
Date: 27/01/2023

Work in progress | 11% Completed

Work started

Oachira AE
Date: 25/01/2023

Work in progress | 10% Completed

Work started

Oachira AE
Date: 23/01/2023

Work in progress | 8% Completed

Work started

Oachira AE
Date: 20/01/2023

Work in progress | 7% Completed

Work started

Oachira AE
Date: 18/01/2023

Work in progress | 5% Completed

Work in progress

Oachira AE
Date: 16/01/2023

Work in progress | 3% Completed

work started

Oachira AE
Date: 12/01/2023

Work in progress | 3% Completed

Work started

Oachira AE
Date: 10/01/2023

Work in progress | 1% Completed

waiting for pipe testing

Oachira AE
Date: 07/01/2023

Work in progress | 1% Completed

waiting for pipe testing

Oachira AE
Date: 05/01/2023

Work in progress | 1% Completed

waiting for pipe testing

Oachira AE
Date: 03/01/2023

Work in progress | 1% Completed

waiting for pipe testing

Oachira AE
Date: 28/12/2022

Work in progress | 1% Completed

waiting for pipe testing

Oachira AE
Date: 26/12/2022

Work in progress | 1% Completed

waiting for pipe testing

Oachira AE
Date: 22/12/2022

Work in progress | 1% Completed

waiting for pipe testing

Oachira AE
Date: 20/12/2022

Work in progress | 1% Completed

waiting for pipe testing

Oachira AE
Date: 17/12/2022

Work in progress | 1% Completed

waiting for pipe testing

Oachira AE
Date: 16/12/2022

Work in progress | 1% Completed

waiting for pipe testing

Oachira AE
Date: 13/12/2022

Work in progress | 1% Completed

waiting for pipe testing

Oachira AE
Date: 12/12/2022

Work in progress | 1% Completed

waiting for pipe testing

Oachira AE
Date: 08/12/2022

Work in progress | 1% Completed

waiting for pipe testing

Oachira AE
Date: 30/11/2022

Work in progress | 1% Completed

Waiting for pipe testing.

Kollam PH Dn EE
Date: 26/11/2022

Work in progress | 1% Completed

waiting for pipe testing