Deposit work - Alappad Grama panchayat - Project No. 100/22 - CWSS to Oachira, Karunagappally, Alappad and Clappana - Extension and interconnection of distribution pipe line with 75 mm PVC pipe CL3 & 90 mm PE Pipe, PE100, PN8 in various wards of Alappad Grama panchayat. - .
| Project |
Deposit work - Alappad Grama panchayat - Project No. 100/22 - CWSS to Oachira, Karunagappally, Alappad and Clappana - Extension and interconnection of distribution pipe line with 75 mm PVC pipe CL3 & 90 mm PE Pipe, PE100, PN8 in various wards of Alappad Grama panchayat. - . |
| Project Code |
KLMDEPO022212676P1 |
| Type |
Package |
| Main Project |
Deposit work - Alappad Gra100/22 - Cma panchayat - Project No. WSS to Oachira, Karunagappally, Alappad and Clappana - Extension and interconnection of distribution pipe line with 75 mm PVC pipe CL3 & 90 mm PE Pipe, PE100, PN8 in various wards of Alappad Grama panchayat. -
|
| Funding Agency |
DEPO |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
DEPO |
| Description |
Deposit work - Alappad Grama panchayat - Project No. 100/22 - CWSS to Oachira, Karunagappally, Alappad and Clappana - Extension and interconnection of distribution pipe line with 75 mm PVC pipe CL3 & 90 mm PE Pipe, PE100, PN8 in various wards of Alappad Grama panchayat. |
| Status |
On-going |
| District |
Kollam |
| Executing Office |
Oachira PH Sn |
| Agreement Number |
|
| Agreement Date |
|
| TS Amount (Rs) |
1432000 |
| TS Number |
6682/2022-2023 |
| Technical specification |
Extension and interconnection of distribution pipe line with 75 mm PVC pipe CL3 & 90 mm PE Pipe, PE100, PN8 in various wards of Alappad Grama panchayat. |
No project review have been added to this project
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
29/10/2022 |
| Scheduled date of Completion as per agreement |
28 Dec 2022 |
| Expected date of Completion |
28/12/2022 |
Processing Dates
| TS Date |
02 Apr 2022 |
| Estimate Approval |
02 Apr 2022 |
| NIT Approval |
26 Jul 2022 |
| Tender Closing |
06 Aug 2022 |
| Technichal Pre-Qualification |
06 Aug 2022 |
| Price bid opening |
06 Aug 2022 |
Approval Dates
| Workorder Date |
10 Oct 2022 |
| NA |
29 Oct 2022 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| Oachira AE |
| Date: 02/05/2023 |
Work has been completed | 100% Completed
work completed on 28/04/2023.
| Oachira AE |
| Date: 27/04/2023 |
Work in progress | 90% Completed
pipe line completed , balance work interconnection only.