| Nedumkandam Sn AE |
| Date: 01/01/2023 |
Work has been completed | 100% Completed
Pipe laying completed
| Nedumkandam Sn AE |
| Date: 13/12/2022 |
Work in progress | 97% Completed
Pipe laying completed
| Nedumkandam Sn AE |
| Date: 19/11/2022 |
Work in progress | 84% Completed
Marykulam - Old match box road pipe laying done (Alternate option for pipe laying instead of Kattappana - Kuttikanam road)
| Nedumkandam Sn AE |
| Date: 13/09/2022 |
Work in progress | 77% Completed
Pipe laying towards Chenninaykankudy route completed. Pipe laying towards Parappu from Marykulam town pending at PWD road cutting sanction. Part bill submitted.
| Nedumkandam Sn AE |
| Date: 29/08/2022 |
Work in progress | 77% Completed
Pipe laying towards Chenninaykankudy route completed. Pipe laying towards Parappu from Marykulam town pending at PWD road cutting sanction. Part bill submitted.
| Thodupuzha PH Dn EE |
| Date: 24/08/2022 |
Work in progress | 77% Completed
on going
| Nedumkandam Sn AE |
| Date: 12/08/2022 |
Work in progress | 75% Completed
Pipe laying towards Chenninaykankudy route completed. Pipe laying towards Parappu from Marykulam town pending at PWD road cutting sanction. Part bill submitted.
| Nedumkandam Sn AE |
| Date: 01/08/2022 |
Work in progress | 75% Completed
Pipe laying towards Chenninaykankudy route completed. Pipe laying towards Parappu from Marykulam town pending at PWD road cutting sanction. Part bill created
| Nedumkandam Sn AE |
| Date: 26/07/2022 |
Work in progress | 75% Completed
Pipe laying towards Chenninaykankudy route completed. Pipe laying towards Parappu from Marykulam town pending at PWD road cutting sanction.
| Nedumkandam Sn AE |
| Date: 20/07/2022 |
Work in progress | 75% Completed
Pipe laying towards Chenninaykankudy route completed. Pipe laying towards Parappu from Marykulam town pending at PWD road cutting sanction. Joint inspection with PWD officials and KWA conducted on 24/06/2022.
| Thodupuzha PH Dn EE |
| Date: 13/07/2022 |
Work in progress | 75% Completed
On going
| Nedumkandam Sn AE |
| Date: 11/07/2022 |
Work in progress | 70% Completed
Pipe laying towards Chenninaykankudy route completed. Pipe laying towards Parappu from Marykulam town pending at PWD road cutting sanction. Joint inspection with PWD officials and KWA conducted on 24/06/2022. Waiting for estimation.
| Nedumkandam Sn AE |
| Date: 01/07/2022 |
Work in progress | 70% Completed
Pipe laying towards Chenninaykankudy route completed. Pipe laying towards Parappu from Marykulam town pending at PWD road cutting sanction. Joint inspection with PWD officials and KWA conducted on 24/06/2022. Waiting for estimation.
| Nedumkandam Sn AE |
| Date: 24/06/2022 |
Work in progress | 70% Completed
Pipe laying towards Chenninaykankudy route completed. Pipe laying towards Parappu from Marykulam town pending at PWD road cutting sanction. Joint inspection with PWD officials and KWA conducted on 24/06/2022. Waiting for estimation.
| Nedumkandam Sn AE |
| Date: 20/06/2022 |
Work in progress | 70% Completed
Pipe laying towards Chenninaykankudy route completed
| Thodupuzha PH Dn EE |
| Date: 17/06/2022 |
Work has started | 0% Completed
Agreement Executed on 18.03.2022
| Nedumkandam Sn AE |
| Date: 31/05/2022 |
Work in progress | 62% Completed
Ongoing
| Nedumkandam Sn AE |
| Date: 12/05/2022 |
Work in progress | 57% Completed
63 mm PVC pipe laid from Chenninaykankudy - 235 m (1215 m upto date) 50 mm GI pipes laid -30m -264 m ( upto date)
| Nedumkandam Sn AE |
| Date: 09/05/2022 |
Work in progress | 46% Completed
63 mm PVC pipe laid from Chenninaykankudy - 200 m (1015 m upto date) 50 mm GI pipes laid -66m -168 m ( upto date)
| Nedumkandam Sn AE |
| Date: 04/05/2022 |
| Nedumkandam Sn AE |
| Date: 02/05/2022 |
Work in progress | 29% Completed
63 mm PVC pipe laid from Chenninaykankudy - 60 m (Total = 760 m)
| Nedumkandam Sn AE |
| Date: 30/04/2022 |
| Nedumkandam Sn AE |
| Date: 29/04/2022 |
Work in progress | 16% Completed
63 mm PVC pipe laid from Chenninaykankudy (225 m + 200 m = 425 m pipe)
| Nedumkandam Sn AE |
| Date: 28/04/2022 |
Work in progress | 8% Completed
63 mm PVC pipe laid from Chenninaykankudy
| Nedumkandam Sn AE |
| Date: 27/04/2022 |
Work in progress | 4% Completed
Work started in the stretch from Chenninaykankudy
| Nedumkandam Sn AE |
| Date: 18/04/2022 |
Work has started | 0% Completed
Pipe testing completed
| Nedumkandam Sn AE |
| Date: 12/04/2022 |
Work has started | 0% Completed
Pipe testing completed
| Nedumkandam Sn AE |
| Date: 05/04/2022 |
Work has started | 0% Completed
Agreement Executed
| Nedumkandam Sn AE |
| Date: 29/03/2022 |
Work has started | 0% Completed
Agreement Executed
| Thodupuzha PH Dn EE |
| Date: 25/03/2022 |
Work in progress | 0% Completed
Agreement Executed
| Nedumkandam Sn AE |
| Date: 24/03/2022 |
Work has started | 0% Completed
work tendered
| Nedumkandam Sn AE |
| Date: 17/03/2022 |
Work has started | 0% Completed
work tendered
| Nedumkandam Sn AE |
| Date: 10/03/2022 |
Work has started | 0% Completed
work tendered
| Nedumkandam Sn AE |
| Date: 03/03/2022 |
Work has started | 0% Completed
work tendered
| Nedumkandam Sn AE |
| Date: 25/02/2022 |
Work has started | 0% Completed
work tendered
| Nedumkandam Sn AE |
| Date: 21/02/2022 |
Work has started | 0% Completed
work tendered
| Nedumkandam Sn AE |
| Date: 15/02/2022 |
Work has started | 0% Completed
work tendered
| Nedumkandam Sn AE |
| Date: 10/02/2022 |
Work has started | 0% Completed
work tendered
| Nedumkandam Sn AE |
| Date: 04/02/2022 |
Work has started | 0% Completed
work tendered
| Nedumkandam Sn AE |
| Date: 31/01/2022 |
Work has started | 0% Completed
work tendered
| Nedumkandam Sn AE |
| Date: 23/01/2022 |
Work has started | 0% Completed
work tendered
| Nedumkandam Sn AE |
| Date: 18/01/2022 |
Work has started | 0% Completed
work tendered
| Thodupuzha PH Dn EE |
| Date: 11/01/2022 |
Work has started | 0% Completed
work tendered
| Nedumkandam Sn AE |
| Date: 04/01/2022 |
Work has started | 0% Completed
Estimate recasted
| Nedumkandam Sn AE |
| Date: 29/12/2021 |
Work has started | 0% Completed
Estimate recasted
| Nedumkandam Sn AE |
| Date: 24/12/2021 |
Work has started | 0% Completed
Estimate recasted
| Nedumkandam Sn AE |
| Date: 20/12/2021 |
Work has started | 0% Completed
Estimate recasted
| Nedumkandam Sn AE |
| Date: 12/12/2021 |
Work has started | 0% Completed
Estimate recasted
| Nedumkandam Sn AE |
| Date: 06/12/2021 |
Work has started | 0% Completed
Estimate to be recasted
| Nedumkandam Sn AE |
| Date: 28/11/2021 |
Work has started | 0% Completed
Estimate to be recasted
| Nedumkandam Sn AE |
| Date: 17/11/2021 |
Work has started | 0% Completed
Estimate recasted
| Thodupuzha PH Dn EE |
| Date: 15/11/2021 |
Work has started | 0% Completed
non starter
| Nedumkandam Sn AE |
| Date: 09/11/2021 |
Work has started | 0% Completed
Recasted with new rates
| Nedumkandam Sn AE |
| Date: 05/11/2021 |
Work has started | 0% Completed
Recasted with new rates
| Nedumkandam Sn AE |
| Date: 01/11/2021 |
Work has started | 0% Completed
Recasted with new rates
| Nedumkandam Sn AE |
| Date: 21/10/2021 |
Work has started | 0% Completed
Recasted with new rates
| Nedumkandam Sn AE |
| Date: 12/10/2021 |
Work has started | 0% Completed
Recasted with new rates
| Thodupuzha PH Dn EE |
| Date: 07/10/2021 |
Work has started | 0% Completed
Recasted with new rates
| Thodupuzha PH Dn EE |
| Date: 30/09/2021 |
Work has started | 0% Completed
Recasted with new rates
| Thodupuzha PH Dn EE |
| Date: 29/09/2021 |
Work has started | 0% Completed
Recasted with new rates
| Thodupuzha PH Dn EE |
| Date: 25/09/2021 |
Work has started | 0% Completed
Recasted with new rates
| Thodupuzha PH Dn EE |
| Date: 20/09/2021 |
Work has started | 0% Completed
Recasted with new rates
| Thodupuzha PH Dn EE |
| Date: 16/09/2021 |
Work has started | 0% Completed
Recasted with new rates
| Thodupuzha PH Dn EE |
| Date: 06/09/2021 |
Work has started | 0% Completed
Recasted with new rates
| Thodupuzha PH Dn EE |
| Date: 31/08/2021 |
Work has started | 0% Completed
Recasted with new rates
| Thodupuzha PH Dn EE |
| Date: 23/08/2021 |
Work has started | 0% Completed
Retendered No offer
| Thodupuzha PH Dn EE |
| Date: 17/08/2021 |
Work has started | 0% Completed
Retendered No offer
| Thodupuzha PH Dn EE |
| Date: 10/08/2021 |
Work has started | 0% Completed
Retendered No offer
| Thodupuzha PH Dn EE |
| Date: 04/08/2021 |
Work has started | 0% Completed
Retendered No offer
| Thodupuzha PH Dn EE |
| Date: 28/07/2021 |
Work has started | 0% Completed
Retendered No offer
| Thodupuzha PH Dn EE |
| Date: 20/07/2021 |
Work in progress | 0% Completed
Retendered No offer
| Thodupuzha PH Dn EE |
| Date: 11/07/2021 |
Work has started | 0% Completed
Retendered No participants
| Thodupuzha PH Dn EE |
| Date: 29/06/2021 |
Work has started | 0% Completed
Retendered
| Thodupuzha PH Dn EE |
| Date: 01/06/2021 |
Work in progress | 0% Completed
work has re tendered
| Thodupuzha PH Dn EE |
| Date: 03/05/2021 |
Work has started | 0% Completed
work Tendered two times but no participation
| Thodupuzha PH Dn EE |
| Date: 29/03/2021 |
Work has started | 0% Completed
work Tendered two times but no participation