| Project | RWSS to Marykulam- Replacing old damaged(DM) 63 mm UPC with 63 mm PVC-2500m, 65 mm GI-750m at Marykulam, Parappau |
|---|---|
| Project Code | IDKGOK06195201P2 |
| Type | Package |
| Main Project | Optimisation of Production and Transmission- pipeline extension 2019-20 - RWSS to Marykulam- Replacing old damaged(DM) 63 mm UPC with 63 mm PVC-2500m, 65 mm GI-750m at Marykulam, Parappau |
| Funding Agency | GOK |
| Category | State plan |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | RWSS to Marykulam- Replacing old damaged(DM) 63 mm UPC with 63 mm PVC-2500m, 65 mm GI-750m at Marykulam, Parappau |
| Status | On-going |
| District | Idukki |
| Executing Office | Peerumedu Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 3091000 |
| TS Number | TS/2021-2022/2019/14694 |
| Technical specification | Pipe line laying work |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 05/03/2022 |
|---|---|
| Scheduled date of Completion as per agreement | 31 Oct 2022 |
| Expected date of Completion | 31/10/2022 |
| TS Date | 09 Feb 2021 |
|---|---|
| Estimate Approval | 09 Feb 2021 |
| NIT Approval | 09 Feb 2021 |
| Tender Closing | 09 Feb 2021 |
| Technichal Pre-Qualification | 09 Feb 2021 |
| Price bid opening | 09 Feb 2021 |
| Workorder Date | 05 Mar 2022 |
|---|---|
| NA | 05 Mar 2022 |
| Nedumkandam Sn AE |
| Date: 01/01/2023 |
Work has been completed | 100% Completed
Pipe laying completed.
| Nedumkandam Sn AE |
| Date: 13/12/2022 |
Work in progress | 97% Completed
Pipe laying completed.