JJM - 2021-22 - Meloor Grama panchayath (Phase ll) - Providing FHTCs to Rural house holds by Augmentation of existing WSS

Project JJM - 2021-22 - Meloor Grama panchayath (Phase ll) - Providing FHTCs to Rural house holds by Augmentation of existing WSS
Project Code TCRJJM022212397P1
Type Package
Main Project JJM - WSS to Meloor Grama panchayath (Phase ll)
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM - 2021-22 - Meloor Grama panchayath (Phase ll) - Providing FHTCs to Rural house holds by Augmentation of existing WSS
Status On-going
District Thrissur
Executing Office Chalakkudy PH Sn II
Agreement Number
Agreement Date
TS Amount (Rs) 212900000
TS Number TS/2022-2023/2021/5931
Technical specification JJM - 2021-22 - Meloor Grama panchayath (Phase ll) - Providing FHTCs to Rural house holds by Augmentation of existing WSS

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 10/11/2022
Scheduled date of Completion as per agreement 09 Nov 2023
Expected date of Completion 09/11/2023

Processing Dates

TS Date 16 Jun 2022
Estimate Approval 16 Jun 2022
NIT Approval 16 Jun 2022
Tender Closing 12 Sep 2022
Technichal Pre-Qualification 12 Sep 2022
Price bid opening 14 Sep 2022

Approval Dates

Workorder Date 10 Nov 2022
NA 23 Nov 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chalakudy AE 2
Date: 29/06/2024

Work in progress | 60% Completed

Work in progress. 1119 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed..

Chalakudy AE 2
Date: 28/06/2024

Work in progress | 60% Completed

Work in progress. 1095 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. .