Project | JJM - 2021-22 - Meloor Grama panchayath (Phase ll) - Providing FHTCs to Rural house holds by Augmentation of existing WSS |
---|---|
Project Code | TCRJJM022212397P1 |
Type | Package |
Main Project | JJM - WSS to Meloor Grama panchayath (Phase ll) |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM - 2021-22 - Meloor Grama panchayath (Phase ll) - Providing FHTCs to Rural house holds by Augmentation of existing WSS |
Status | On-going |
District | Thrissur |
Executing Office | Chalakkudy PH Sn II |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 212900000 |
TS Number | TS/2022-2023/2021/5931 |
Technical specification | JJM - 2021-22 - Meloor Grama panchayath (Phase ll) - Providing FHTCs to Rural house holds by Augmentation of existing WSS |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 10/11/2022 |
---|---|
Scheduled date of Completion as per agreement | 09 Nov 2023 |
Expected date of Completion | 09/11/2023 |
TS Date | 16 Jun 2022 |
---|---|
Estimate Approval | 16 Jun 2022 |
NIT Approval | 16 Jun 2022 |
Tender Closing | 12 Sep 2022 |
Technichal Pre-Qualification | 12 Sep 2022 |
Price bid opening | 14 Sep 2022 |
Workorder Date | 10 Nov 2022 |
---|---|
NA | 23 Nov 2022 |
Chalakudy AE 2 |
Date: 29/06/2024 |
Work in progress | 60% Completed
Work in progress. 1119 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed..
Chalakudy AE 2 |
Date: 28/06/2024 |
Work in progress | 60% Completed
Work in progress. 1095 connection tagged. pipe supplied 98.93%.laying = 79.12% completed. Connection=29.74%completed. .