Status Date |
Overall Project Status |
Project Officer |
Contact |
26 Jun 2024 |
179.3574/239.14 km (Mathur -72.758/130.72 km, Pirayiri- 106.7396/201.42 km) completed. Remaining PVC & GI pipe laying work progressing. 22 LL OHSR TANK - Haunch concreting & Column RCC concrete started, Bottom floor slab concrete completed. WTP -. CLARIFLOCCULATOR : Walkway plastering, bridge fabrication work completed. CHEMICAL HOUSE - Neutralization pit plastering completed, Plastering work completed. Filter house- plastering (external & internal) work 95% Completed. PUMP HOUSE - Plastering completed. AREATOR - plastering progress. Intake well (6 m dia) - Access ramp footing work finish and approach bridge 75% completed, wall plastering completed. 14 LL OHSR - Plastering 95% completed, Store room brick work completed. Sump plastering work on going . Pirayiri : FHTC -10 & HTC-3490, 3500/7969 , 2991 tagged & Mathur ; FHTC -0 , 2601 House connections and 2362 geo-tagged. |
Palakkad Project Dn AEE3 |
|
25 Jun 2024 |
179.3574/239.14 km (Mathur -72.758/130.72 km, Pirayiri- 106.7396/201.42 km) completed. Remaining PVC & GI pipe laying work progressing. 22 LL OHSR TANK - Haunch concreting & Column RCC concrete started, Bottom floor slab concrete completed. WTP -. CLARIFLOCCULATOR : Walkway plastering, bridge fabrication work completed. CHEMICAL HOUSE - Neutralization pit plastering completed, Plastering work completed. Filter house- plastering (external & internal) work 95% Completed. PUMP HOUSE - Plastering completed. AREATOR - plastering progress. Intake well (6 m dia) - Access ramp footing work finish and approach bridge 75% completed, wall plastering completed. 14 LL OHSR - Plastering 95% completed, Store room brick work completed. Sump plastering work on going . Pirayiri : FHTC -10 & HTC-3482, 3492/7969 , 2991 tagged & Mathur ; FHTC -0 , 2601 House connections and 2362 geo-tagged. |
Palakkad Project Dn AEE3 |
|
24 Jun 2024 |
179.3574/239.14 km (Mathur -72.758/130.72 km, Pirayiri- 106.7396/201.42 km) completed. Remaining PVC & GI pipe laying work progressing. 22 LL OHSR TANK - Haunch concreting & Column RCC concrete started, Bottom floor slab concrete completed. WTP -. CLARIFLOCCULATOR : Walkway plastering, bridge fabrication work completed. CHEMICAL HOUSE - Neutralization pit plastering completed, Plastering work completed. Filter house- plastering (external & internal) work 95% Completed. PUMP HOUSE - Plastering completed. AREATOR - plastering progress. Intake well (6 m dia) - Access ramp footing work finish and approach bridge 75% completed, wall plastering completed. 14 LL OHSR - Plastering 95% completed, Store room brick work completed. Sump plastering work on going . Pirayiri : FHTC -10 & HTC-3482, 3492/7969 , 2991 tagged & Mathur ; FHTC -0 , 2601 House connections and 2362 geo-tagged. |
Palakkad Project Dn AEE3 |
|
22 Jun 2024 |
179.3574/239.14 km (Mathur -72.758/130.72 km, Pirayiri- 106.7396/201.42 km) completed. Remaining PVC & GI pipe laying work progressing. 22 LL OHSR TANK - Column RCC concrete started, Bottom floor slab concrete completed. WTP -Neutralization pit plastering completed. CLARIFLOCCULATOR : Walkway plastering, bridge fabrication work completed. CHEMICAL HOUSE - Plastering work completed. Filter house- plastering (external & internal) work 95% Completed ,Neutralization pit side wall shuttering. PUMP HOUSE - plastering completed. AREATOR - plastering progress. Intake well (6 m dia) - access ramp footing work finish and approach bridge 75% completed, wall plastering completed. 14 LL OHSR - Plastering 95% completed, Store room brick work completed. Sump plastering work on going . Pirayiri : FHTC -10 & HTC-3482, 3492/7969 , 2991 tagged & Mathur ; FHTC -0 , 2601 House connections and 2337 geo-tagged. |
Palakkad Project Dn AEE3 |
|
20 Jun 2024 |
179.3574/239.14 km (Mathur -72.758/130.72 km, Pirayiri- 106.7396/201.42 km) completed. Remaining PVC & GI pipe laying work progressing. 22 LL OHSR TANK - Column RCC concrete started, Bottom floor slab concrete completed. WTP -Neutralization pit plastering completed. CLARIFLOCCULATOR : Walkway plastering, bridge fabrication work completed. CHEMICAL HOUSE - Plastering work completed. Filter house- plastering (external & internal) work 95% Completed ,Neutralization pit side wall shuttering. PUMP HOUSE - plastering completed. AREATOR - plastering progress. Intake well (6 m dia) - access ramp footing work finish and approach bridge 75% completed, wall plastering completed. 14 LL OHSR - Plastering 95% completed, Store room brick work completed. Sump plastering work on going . Pirayiri : FHTC -10 & HTC-3482, 3492/7969 , 2991 tagged & Mathur ; FHTC -0 , 2601 House connections and 2321 geo-tagged. |
Palakkad Project Dn AEE3 |
|