Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM 2020-21 WSS TO MATHUR AND PIRAYIRI PANCHAYATS

Project JJM 2020-21 WSS TO MATHUR AND PIRAYIRI PANCHAYATS
Project Code PKDJJM12206491
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM 2020-21 WSS TO MATHUR AND PIRAYIRI PANCHAYATS
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
AS Amount (Rs) 806700000
AS Number G.O.(Rt)No.777/2020/WRD
TS Amount (Rs) 801900000
TS Number TS/2020-2021/2020/30327
Total Bill Submitted (Rs) 432172988
Total Bill Paid (Rs) 355809164
Population Benefitted 88158
Capacity in MLD 12.00
Actual Project Completion Date 28 Jan 2024
Coverage Mathur, Pirayiri panchayats
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM 2020-21 WSS TO MATHUR AND PIRAYIRI PANCHAYATS Project Division Palakkad

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Jun 2024 179.3574/239.14 km (Mathur -72.758/130.72 km, Pirayiri- 106.7396/201.42 km) completed. Remaining PVC & GI pipe laying work progressing. 22 LL OHSR TANK - Haunch concreting & Column RCC concrete started, Bottom floor slab concrete completed. WTP -. CLARIFLOCCULATOR : Walkway plastering, bridge fabrication work completed. CHEMICAL HOUSE - Neutralization pit plastering completed, Plastering work completed. Filter house- plastering (external & internal) work 95% Completed. PUMP HOUSE - Plastering completed. AREATOR - plastering progress. Intake well (6 m dia) - Access ramp footing work finish and approach bridge 75% completed, wall plastering completed. 14 LL OHSR - Plastering 95% completed, Store room brick work completed. Sump plastering work on going . Pirayiri : FHTC -10 & HTC-3490, 3500/7969 , 2991 tagged & Mathur ; FHTC -0 , 2601 House connections and 2362 geo-tagged. Palakkad Project Dn AEE3
25 Jun 2024 179.3574/239.14 km (Mathur -72.758/130.72 km, Pirayiri- 106.7396/201.42 km) completed. Remaining PVC & GI pipe laying work progressing. 22 LL OHSR TANK - Haunch concreting & Column RCC concrete started, Bottom floor slab concrete completed. WTP -. CLARIFLOCCULATOR : Walkway plastering, bridge fabrication work completed. CHEMICAL HOUSE - Neutralization pit plastering completed, Plastering work completed. Filter house- plastering (external & internal) work 95% Completed. PUMP HOUSE - Plastering completed. AREATOR - plastering progress. Intake well (6 m dia) - Access ramp footing work finish and approach bridge 75% completed, wall plastering completed. 14 LL OHSR - Plastering 95% completed, Store room brick work completed. Sump plastering work on going . Pirayiri : FHTC -10 & HTC-3482, 3492/7969 , 2991 tagged & Mathur ; FHTC -0 , 2601 House connections and 2362 geo-tagged. Palakkad Project Dn AEE3
24 Jun 2024 179.3574/239.14 km (Mathur -72.758/130.72 km, Pirayiri- 106.7396/201.42 km) completed. Remaining PVC & GI pipe laying work progressing. 22 LL OHSR TANK - Haunch concreting & Column RCC concrete started, Bottom floor slab concrete completed. WTP -. CLARIFLOCCULATOR : Walkway plastering, bridge fabrication work completed. CHEMICAL HOUSE - Neutralization pit plastering completed, Plastering work completed. Filter house- plastering (external & internal) work 95% Completed. PUMP HOUSE - Plastering completed. AREATOR - plastering progress. Intake well (6 m dia) - Access ramp footing work finish and approach bridge 75% completed, wall plastering completed. 14 LL OHSR - Plastering 95% completed, Store room brick work completed. Sump plastering work on going . Pirayiri : FHTC -10 & HTC-3482, 3492/7969 , 2991 tagged & Mathur ; FHTC -0 , 2601 House connections and 2362 geo-tagged. Palakkad Project Dn AEE3
22 Jun 2024 179.3574/239.14 km (Mathur -72.758/130.72 km, Pirayiri- 106.7396/201.42 km) completed. Remaining PVC & GI pipe laying work progressing. 22 LL OHSR TANK - Column RCC concrete started, Bottom floor slab concrete completed. WTP -Neutralization pit plastering completed. CLARIFLOCCULATOR : Walkway plastering, bridge fabrication work completed. CHEMICAL HOUSE - Plastering work completed. Filter house- plastering (external & internal) work 95% Completed ,Neutralization pit side wall shuttering. PUMP HOUSE - plastering completed. AREATOR - plastering progress. Intake well (6 m dia) - access ramp footing work finish and approach bridge 75% completed, wall plastering completed. 14 LL OHSR - Plastering 95% completed, Store room brick work completed. Sump plastering work on going . Pirayiri : FHTC -10 & HTC-3482, 3492/7969 , 2991 tagged & Mathur ; FHTC -0 , 2601 House connections and 2337 geo-tagged. Palakkad Project Dn AEE3
20 Jun 2024 179.3574/239.14 km (Mathur -72.758/130.72 km, Pirayiri- 106.7396/201.42 km) completed. Remaining PVC & GI pipe laying work progressing. 22 LL OHSR TANK - Column RCC concrete started, Bottom floor slab concrete completed. WTP -Neutralization pit plastering completed. CLARIFLOCCULATOR : Walkway plastering, bridge fabrication work completed. CHEMICAL HOUSE - Plastering work completed. Filter house- plastering (external & internal) work 95% Completed ,Neutralization pit side wall shuttering. PUMP HOUSE - plastering completed. AREATOR - plastering progress. Intake well (6 m dia) - access ramp footing work finish and approach bridge 75% completed, wall plastering completed. 14 LL OHSR - Plastering 95% completed, Store room brick work completed. Sump plastering work on going . Pirayiri : FHTC -10 & HTC-3482, 3492/7969 , 2991 tagged & Mathur ; FHTC -0 , 2601 House connections and 2321 geo-tagged. Palakkad Project Dn AEE3

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 07/12/2021
Scheduled date of Completion of the Project 06 Jun 2023
Expected date of Completion 31/05/2024

Processing Dates

AS Date 24 Dec 2020
TS Date 28 Jan 2021

Other details

Project Officers View