Project | Jal Jeevan Mission 2020-21 -providing functional house hold Tap connections in Angadipuram grama Panchayath -Phase-2 |
---|---|
Project Code | MLPJJM12208972P1 |
Type | Package |
Main Project | Jal Jeevan Mission 2020-21 -providing functional house hold Tap connections in Angadipuram grama Panchayath -Phase-2 |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Laying distribution line, OHSR- 2.25LL, Demolishing abandoned- 1.28LL, design and survey- using total station / DGPS |
Status | On-going |
District | Malappuram |
Executing Office | Perinthalmanna PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 271000000 |
TS Number | Reg .No. 14187/2021-2022 |
Technical specification | Laying distribution line, OHSR- 2.25LL, Demolishing abandoned- 1.28LL, design and survey- using total station / DGPS |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 06/09/2022 |
---|---|
Scheduled date of Completion as per agreement | 05 Sep 2023 |
Expected date of Completion | 05/09/2023 |
TS Date | 30 Nov 2021 |
---|---|
Estimate Approval | 30 Nov 2021 |
NIT Approval | 30 Nov 2021 |
Tender Closing | 15 Jul 2022 |
Technichal Pre-Qualification | 18 Jul 2022 |
Price bid opening | 18 Jul 2022 |
Workorder Date | 26 Aug 2022 |
---|---|
NA | 06 Sep 2022 |
Perinthalmanna AE |
Date: 28/06/2024 |
Work in progress | 52% Completed
22000m 90mm HDPE Laid. 1800m 80mm GI Laid. 2300m 50mm GI laid. 4300m 110mm HDPE laid.1750m 65mm GI laid,160mm HDPE 700m,250mm DI 850m .100mm GI 200m laid,2431 FHTC and 796 HTC provided. Demolition of old tank and site clearing completed. Foundation concrete completed. Pedestal column completed. PCC for plinth beam completed. Plinth beam concrete completed.12 Nos Column concrete completed. First flight of stair concrete completed. plinth Beam bottom concrete completed. Earth filling completed. Tank stair 2nd flight completed. 1st brace beam concreting completed.First floor colomn completed. first floor landing 3-landing 4 stair concreting completed. second brace beam concrete completed.second level colomn 12 numbers of colomn concreting completed.water tank base slab concreting completed.reinforcement of side wall and colomn completed ,haunch completed,side wall concreting completed . Tank cover slab concreting completed.Plastering 50mm sqm completed . .
Perinthalmanna AE |
Date: 24/06/2024 |
Work in progress | 52% Completed
22000m 90mm HDPE Laid. 1800m 80mm GI Laid. 2300m 50mm GI laid. 4300m 110mm HDPE laid.1750m 65mm GI laid,160mm HDPE 700m,250mm DI 850m .100mm GI 200m laid,2431 FHTC and 796 HTC provided. Demolition of old tank and site clearing completed. Foundation concrete completed. Pedestal column completed. PCC for plinth beam completed. Plinth beam concrete completed.12 Nos Column concrete completed. First flight of stair concrete completed. plinth Beam bottom concrete completed. Earth filling completed. Tank stair 2nd flight completed. 1st brace beam concreting completed.First floor colomn completed. first floor landing 3-landing 4 stair concreting completed. second brace beam concrete completed.second level colomn 12 numbers of colomn concreting completed.water tank base slab concreting completed.reinforcement of side wall and colomn completed ,haunch completed,side wall concreting completed . Tank cover slab concreting completed.Plastering 50mm sqm completed . .