Jal Jeevan Mission 2020-21 -providing functional house hold Tap connections in Angadipuram grama Panchayath -Phase-2

Project Jal Jeevan Mission 2020-21 -providing functional house hold Tap connections in Angadipuram grama Panchayath -Phase-2
Project Code MLPJJM12208972P1
Type Package
Main Project Jal Jeevan Mission 2020-21 -providing functional house hold Tap connections in Angadipuram grama Panchayath -Phase-2
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Laying distribution line, OHSR- 2.25LL, Demolishing abandoned- 1.28LL, design and survey- using total station / DGPS
Status On-going
District Malappuram
Executing Office Perinthalmanna PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 271000000
TS Number Reg .No. 14187/2021-2022
Technical specification Laying distribution line, OHSR- 2.25LL, Demolishing abandoned- 1.28LL, design and survey- using total station / DGPS

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 06/09/2022
Scheduled date of Completion as per agreement 05 Sep 2023
Expected date of Completion 05/09/2023

Processing Dates

TS Date 30 Nov 2021
Estimate Approval 30 Nov 2021
NIT Approval 30 Nov 2021
Tender Closing 15 Jul 2022
Technichal Pre-Qualification 18 Jul 2022
Price bid opening 18 Jul 2022

Approval Dates

Workorder Date 26 Aug 2022
NA 06 Sep 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Perinthalmanna AE
Date: 28/06/2024

Work in progress | 52% Completed

22000m 90mm HDPE Laid. 1800m 80mm GI Laid. 2300m 50mm GI laid. 4300m 110mm HDPE laid.1750m 65mm GI laid,160mm HDPE 700m,250mm DI 850m .100mm GI 200m laid,2431 FHTC and 796 HTC provided. Demolition of old tank and site clearing completed. Foundation concrete completed. Pedestal column completed. PCC for plinth beam completed. Plinth beam concrete completed.12 Nos Column concrete completed. First flight of stair concrete completed. plinth Beam bottom concrete completed. Earth filling completed. Tank stair 2nd flight completed. 1st brace beam concreting completed.First floor colomn completed. first floor landing 3-landing 4 stair concreting completed. second brace beam concrete completed.second level colomn 12 numbers of colomn concreting completed.water tank base slab concreting completed.reinforcement of side wall and colomn completed ,haunch completed,side wall concreting completed . Tank cover slab concreting completed.Plastering 50mm sqm completed . .

Perinthalmanna AE
Date: 24/06/2024

Work in progress | 52% Completed

22000m 90mm HDPE Laid. 1800m 80mm GI Laid. 2300m 50mm GI laid. 4300m 110mm HDPE laid.1750m 65mm GI laid,160mm HDPE 700m,250mm DI 850m .100mm GI 200m laid,2431 FHTC and 796 HTC provided. Demolition of old tank and site clearing completed. Foundation concrete completed. Pedestal column completed. PCC for plinth beam completed. Plinth beam concrete completed.12 Nos Column concrete completed. First flight of stair concrete completed. plinth Beam bottom concrete completed. Earth filling completed. Tank stair 2nd flight completed. 1st brace beam concreting completed.First floor colomn completed. first floor landing 3-landing 4 stair concreting completed. second brace beam concrete completed.second level colomn 12 numbers of colomn concreting completed.water tank base slab concreting completed.reinforcement of side wall and colomn completed ,haunch completed,side wall concreting completed . Tank cover slab concreting completed.Plastering 50mm sqm completed . .