Jal Jeevan Mission 2020-21 -providing functional house hold Tap connections in Angadipuram grama Panchayath -Phase-2
Project |
Jal Jeevan Mission 2020-21 -providing functional house hold Tap connections in Angadipuram grama Panchayath -Phase-2 |
Project Code |
MLPJJM12208972 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Laying distribution line,
OHSR- 2.25LL,
Demolishing abandoned- 1.28LL,
design and survey- using total station / DGPS |
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram PH Dn |
AS Amount (Rs) |
279000000
|
AS Number |
G.O.(Rt)No.777/2020/WRD |
TS Amount (Rs) |
271000000 |
TS Number |
Reg .No. 14187/2021-2022 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
1000 |
Capacity in MLD |
0.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
8900 FHTCs |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission 2020-21 -providing functional house hold Tap connections in Angadipuram grama Panchayath -Phase-2 |
Perinthalmanna PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
26 Jun 2024 |
22000m 90mm HDPE Laid. 1800m 80mm GI Laid. 2300m 50mm GI laid. 4300m 110mm HDPE laid.1750m 65mm GI laid,160mm HDPE 700m,250mm DI 850m .100mm GI 200m laid,2431 FHTC and 796 HTC provided. Demolition of old tank and site clearing completed. Foundation concrete completed. Pedestal column completed. PCC for plinth beam completed. Plinth beam concrete completed.12 Nos Column concrete completed. First flight of stair concrete completed. plinth Beam bottom concrete completed. Earth filling completed. Tank stair 2nd flight completed. 1st brace beam concreting completed.First floor colomn completed. first floor landing 3-landing 4 stair concreting completed. second brace beam concrete completed.second level colomn 12 numbers of colomn concreting completed.water tank base slab concreting completed.reinforcement of side wall and colomn completed ,haunch completed,side wall concreting completed . Tank cover slab concreting completed.Plastering 50mm sqm completed . |
Perinthalmanna AE |
|
24 Jun 2024 |
22000m 90mm HDPE Laid. 1800m 80mm GI Laid. 2300m 50mm GI laid. 4300m 110mm HDPE laid.1750m 65mm GI laid,160mm HDPE 700m,250mm DI 850m .100mm GI 200m laid,2431 FHTC and 796 HTC provided. Demolition of old tank and site clearing completed. Foundation concrete completed. Pedestal column completed. PCC for plinth beam completed. Plinth beam concrete completed.12 Nos Column concrete completed. First flight of stair concrete completed. plinth Beam bottom concrete completed. Earth filling completed. Tank stair 2nd flight completed. 1st brace beam concreting completed.First floor colomn completed. first floor landing 3-landing 4 stair concreting completed. second brace beam concrete completed.second level colomn 12 numbers of colomn concreting completed.water tank base slab concreting completed.reinforcement of side wall and colomn completed ,haunch completed,side wall concreting completed . Tank cover slab concreting completed.Plastering 50mm sqm completed . |
Perinthalmanna AE |
|
15 Jun 2024 |
22000m 90mm HDPE Laid. 1800m 80mm GI Laid. 2300m 50mm GI laid. 4300m 110mm HDPE laid.1750m 65mm GI laid,160mm HDPE 700m,250mm DI 850m .100mm GI 200m laid,2431 FHTC and 796 HTC provided. Demolition of old tank and site clearing completed. Foundation concrete completed. Pedestal column completed. PCC for plinth beam completed. Plinth beam concrete completed.12 Nos Column concrete completed. First flight of stair concrete completed. plinth Beam bottom concrete completed. Earth filling completed. Tank stair 2nd flight completed. 1st brace beam concreting completed.First floor colomn completed. first floor landing 3-landing 4 stair concreting completed. second brace beam concrete completed.second level colomn 12 numbers of colomn concreting completed.water tank base slab concreting completed.reinforcement of side wall and colomn completed ,haunch completed,side wall concreting completed . Tank cover slab concreting completed.Plastering 50mm sqm completed . |
Perinthalmanna AE |
|
10 Jun 2024 |
22000m 90mm HDPE Laid. 1800m 80mm GI Laid. 2300m 50mm GI laid. 4300m 110mm HDPE laid.1750m 65mm GI laid,160mm HDPE 700m,250mm DI 850m .100mm GI 200m laid,2431 FHTC and 796 HTC provided. Demolition of old tank and site clearing completed. Foundation concrete completed. Pedestal column completed. PCC for plinth beam completed. Plinth beam concrete completed.12 Nos Column concrete completed. First flight of stair concrete completed. plinth Beam bottom concrete completed. Earth filling completed. Tank stair 2nd flight completed. 1st brace beam concreting completed.First floor colomn completed. first floor landing 3-landing 4 stair concreting completed. second brace beam concrete completed.second level colomn 12 numbers of colomn concreting completed.water tank base slab concreting completed.reinforcement of side wall and colomn completed ,haunch completed,side wall concreting completed . Tank cover slab concreting completed.Plastering 50mm sqm completed . |
Perinthalmanna AE |
|
06 Jun 2024 |
22000m 90mm HDPE Laid. 1800m 80mm GI Laid. 2300m 50mm GI laid. 4300m 110mm HDPE laid.1750m 65mm GI laid,160mm HDPE 700m,250mm DI 850m .100mm GI 200m laid,2431 FHTC and 796 HTC provided. Demolition of old tank and site clearing completed. Foundation concrete completed. Pedestal column completed. PCC for plinth beam completed. Plinth beam concrete completed.12 Nos Column concrete completed. First flight of stair concrete completed. plinth Beam bottom concrete completed. Earth filling completed. Tank stair 2nd flight completed. 1st brace beam concreting completed.First floor colomn completed. first floor landing 3-landing 4 stair concreting completed. second brace beam concrete completed.second level colomn 12 numbers of colomn concreting completed.water tank base slab concreting completed.reinforcement of side wall and colomn completed ,haunch completed,side wall concreting completed . Tank cover slab concreting completed.Plastering 50mm sqm completed . |
Perinthalmanna AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
06/09/2022 |
Scheduled date of Completion of the Project |
05 Sep 2023 |
Expected date of Completion |
05/09/2023 |
Processing Dates
AS Date |
24 Dec 2020 |
TS Date |
30 Nov 2021 |