- Home
- Jal Jeevan Mission (JJM)- JJM - 2022- 20...
Jal Jeevan Mission (JJM)- JJM - 2022- 2023 - Pavaratty Regional water supply scheme to Thrithala Panchayath-Providing distribution network and FHTC in Thrithala Panchayath
Project |
Jal Jeevan Mission (JJM)- JJM - 2022- 2023 - Pavaratty Regional water supply scheme to Thrithala Panchayath-Providing distribution network and FHTC in Thrithala Panchayath |
Project Code |
TCRJJM022214364 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission (JJM)- JJM - 2022- 2023 - Pavaratty Regional water supply scheme to Thrithala Panchayath-Providing distribution network and FHTC in Thrithala Panchayath |
Status |
On-going |
District |
Thrissur |
Executing Office |
Thrissur PH Dn |
AS Amount (Rs) |
156398000
|
AS Number |
G.O.(Rt)No.134/2022/WRD |
TS Amount (Rs) |
78300000 |
TS Number |
WRD/KWA-CEP/EST_TS/335/2022_5_1_1 Dated: 28-10-2022 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
27796 |
Capacity in MLD |
33.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Thrithala Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)- JJM - 2022- 2023 - Pavaratty Regional water supply scheme to Thrithala Panchayath-Providing distribution network and FHTC in Thrithala Panchayath |
Thrithala Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
26 Jun 2024 |
PVC work at panchayat road almost completed . DI work is pending due to PWD sanction pending. Pipe supplied. Demand notice issued by PWD . 95 Nos connection given. |
Thrissur PH Dn EE |
|
22 Jun 2024 |
PVC work at panchayat road almost completed . DI work is pending due to PWD sanction pending. Pipe supplied. Demand notice issued by PWD . 95 Nos connection given. |
Thrissur PH Dn EE |
|
21 Jun 2024 |
PVC work at panchayat road almost completed . DI work is pending due to PWD sanction pending. Pipe supplied. Demand notice issued by PWD . 72 Nos connection given. |
Thrissur PH Dn EE |
|
20 Jun 2024 |
PVC work at panchayat road almost completed . DI work is pending due to PWD sanction pending. Pipe supplied. Demand notice issued by PWD . 72 Nos connection given. |
Thrissur PH Dn EE |
|
19 Jun 2024 |
PVC work at panchayat road almost completed . DI work is pending due to PWD sanction pending. Pipe supplied. Demand notice issued by PWD . 72 Nos connection given. |
Thrissur PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
02/05/2023 |
Scheduled date of Completion of the Project |
01 Nov 2024 |
Expected date of Completion |
01/11/2024 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
28 Oct 2022 |