Jal Jeevan Mission (JJM)- JJM - 2022- 2023 - Pavaratty Regional water supply scheme to Thrithala Panchayath-Providing distribution network and FHTC in Thrithala Panchayath

Project Jal Jeevan Mission (JJM)- JJM - 2022- 2023 - Pavaratty Regional water supply scheme to Thrithala Panchayath-Providing distribution network and FHTC in Thrithala Panchayath
Project Code TCRJJM022214364P1
Type Package
Main Project Jal Jeevan Mission (JJM)- JJM - 2022- 2023 - Pavaratty Regional water supply scheme to Thrithala Panchayath-Providing distribution network and FHTC in Thrithala Panchayath
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)- JJM - 2022- 2023 - Pavaratty Regional water supply scheme to Thrithala Panchayath-Providing distribution network and FHTC in Thrithala Panchayath
Status On-going
District Thrissur
Executing Office Thrithala Sn
Agreement Number
Agreement Date
TS Amount (Rs) 78300000
TS Number WRD/KWA-CEP/EST_TS/335/2022_5_1_1 Dated: 28-10-2022
Technical specification Providing distribution network and FHTC in Thrithala Panchayath
Contractor COCHIN MARINE INDUSTRIES (Mob: 9388961464)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 02/05/2023
Scheduled date of Completion as per agreement 01 Nov 2024
Expected date of Completion 01/11/2024

Processing Dates

TS Date 28 Oct 2022
Estimate Approval 28 Oct 2022
NIT Approval 28 Oct 2022
Tender Closing 10 Apr 2023
Technichal Pre-Qualification 10 Apr 2023
Price bid opening 20 Apr 2023

Approval Dates

Workorder Date 02 May 2023
NA 10 May 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thrissur PH Dn EE
Date: 26/06/2024

Work in progress | 20% Completed

PVC work at panchayat road almost completed . DI work is pending due to PWD sanction pending. Pipe supplied. Demand notice issued by PWD . 95 Nos connection given..

Thrithala PH Sn - AE
Date: 25/06/2024

Work in progress | 20% Completed

PVC work at panchayat road almost completed . DI work is pending due to PWD sanction pending. Pipe supplied. Demand notice issued by PWD . 95 Nos connection given..