- Home
- Jaljeevan Mission(JJM)-JJM 2022-23 -RWSS...
Jaljeevan Mission(JJM)-JJM 2022-23 -RWSS to Thazhava-Construction of newly drilled tube well,Pump house,Supply and erection of submersible pumpset and interconnection work at Anganawadi compound no:106, Vettuvila Temple Ward No:20 in Thazhava Panchayath
Project |
Jaljeevan Mission(JJM)-JJM 2022-23 -RWSS to Thazhava-Construction of newly drilled tube well,Pump house,Supply and erection of submersible pumpset and interconnection work at Anganawadi compound no:106, Vettuvila Temple Ward No:20 in Thazhava Panchayath |
Project Code |
KLMJJM082014888 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jaljeevan Mission(JJM)-JJM 2022-23 -RWSS to Thazhava-Construction of newly drilled tube well,Pump house,Supply and erection of submersible pumpset and interconnection work at Anganawadi compound no:106, Vettuvila Temple Ward No:20 in Thazhava Panchayath |
Status |
On-going |
District |
Kollam |
Executing Office |
Kollam PH Dn |
AS Amount (Rs) |
58800000
|
AS Number |
541/2020/WRD |
TS Amount (Rs) |
2147000 |
TS Number |
WRD/KWA-CE(SR)/EST_TS/15812/2022_5_1_1 |
Total Bill Submitted (Rs) |
58800000 |
Total Bill Paid (Rs) |
1 |
Population Benefitted |
4000 |
Capacity in MLD |
2.70 |
Actual Project Completion Date |
31 Mar 2024 |
Coverage |
Ward 18,19 and 20 |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jaljeevan Mission(JJM)-JJM 2022-23 -RWSS to Thazhava-Construction of newly drilled tube well,Pump house,Supply and erection of submersible pumpset and interconnection work at Anganawadi compound no:106, Vettuvila Temple Ward No:20 in Thazhava Panchayath |
Chavara PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
29 Jun 2024 |
Work not started yet due to local issues |
Chavara AE |
|
27 Jun 2024 |
Work not started yet due to local issues |
Chavara AE |
|
26 Jun 2024 |
Work not started yet due to local issues |
Chavara AE |
|
23 Jun 2024 |
Work not started yet due to local issues |
Chavara AE |
|
20 Jun 2024 |
Work not started yet due to local issues |
Chavara AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
18/03/2023 |
Scheduled date of Completion of the Project |
31 Mar 2024 |
Expected date of Completion |
31/07/2024 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
17 Mar 2023 |