Jaljeevan Mission(JJM)-JJM 2022-23 -RWSS to Thazhava-Construction of newly drilled tube well,Pump house,Supply and erection of submersible pumpset and interconnection work at Anganawadi compound no:106, Vettuvila Temple Ward No:20 in Thazhava Panchayath
Project |
Jaljeevan Mission(JJM)-JJM 2022-23 -RWSS to Thazhava-Construction of newly drilled tube well,Pump house,Supply and erection of submersible pumpset and interconnection work at Anganawadi compound no:106, Vettuvila Temple Ward No:20 in Thazhava Panchayath |
Project Code |
KLMJJM082014888P1 |
Type |
Package |
Main Project |
Jaljeevan Mission(JJM)-JJM 2022-23 -RWSS to Thazhava-Construction of newly drilled tube well,Pump house,Supply and erection of submersible pumpset and interconnection work at Anganawadi compound no:106, Vettuvila Temple Ward No:20 in Thazhava Panchayath
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jaljeevan Mission(JJM)-JJM 2022-23 -RWSS to Thazhava-Construction of newly drilled tube well,Pump house,Supply and erection of submersible pumpset and interconnection work at Anganawadi compound no:106, Vettuvila Temple Ward No:20 in Thazhava Panchayath |
Status |
On-going |
District |
Kollam |
Executing Office |
Chavara PH Sn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
2147000 |
TS Number |
WRD/KWA-CE(SR)/EST_TS/15812/2022_5_1_1 |
Technical specification |
Jaljeevan Mission(JJM)-JJM 2022-23 -RWSS to Thazhava-Construction of newly drilled tube well,Pump house,Supply and erection of submersible pumpset and interconnection work at Anganawadi compound no:106, Vettuvila Temple Ward No:20 in Thazhava Panchayath |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
18/03/2023 |
Scheduled date of Completion as per agreement |
31 Mar 2024 |
Expected date of Completion |
31/03/2024 |
Processing Dates
TS Date |
17 Mar 2023 |
Estimate Approval |
15 Mar 2023 |
NIT Approval |
15 Mar 2024 |
Tender Closing |
03 Apr 2023 |
Technichal Pre-Qualification |
03 Apr 2023 |
Price bid opening |
05 Apr 2023 |
Approval Dates
Workorder Date |
21 Aug 2020 |
NA |
18 Mar 2023 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Chavara AE |
Date: 02/07/2024 |
Work in progress | 2% Completed
Work not started yet due to local issues.
Chavara AE |
Date: 29/06/2024 |
Work in progress | 2% Completed
Work not started yet due to local issues .