JJM -WSS TO VALLAPUZHA-ADDITIONAL WORKS-PIPE LINE EXTENSION TO UNCOVERED AREAS AND LSGD ROAD RESTORATION WORKSPipeline Work

Project JJM -WSS TO VALLAPUZHA-ADDITIONAL WORKS-PIPE LINE EXTENSION TO UNCOVERED AREAS AND LSGD ROAD RESTORATION WORKSPipeline Work
Project Code PKDJJM102315807P1
Type Package
Main Project JJM -WSS TO VALLAPUZHA-ADDITIONAL WORKS-PIPE LINE EXTENSION TO UNCOVERED AREAS AND LSGD ROAD RESTORATION WORKSPipeline Work
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM -WSS TO VALLAPUZHA-ADDITIONAL WORKS-PIPE LINE EXTENSION TO UNCOVERED AREAS AND LSGD ROAD RESTORATION WORKS Pipeline Work
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 24800000
TS Number WRD/KWA-CE(NR)/EST_TS/25906/2023_26_1_1
Technical specification JJM -WSS TO VALLAPUZHA-ADDITIONAL WORKS-PIPE LINE EXTENSION TO UNCOVERED AREAS AND LSGD ROAD RESTORATION WORKS Pipeline Work

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 20/12/2023
Scheduled date of Completion as per agreement 19 Jun 2024
Expected date of Completion 19/06/2024

Processing Dates

TS Date 08 Nov 2023
Estimate Approval 08 Nov 2023
Tender Closing 08 Dec 2023
Price bid opening 08 Dec 2023

Approval Dates

Workorder Date 20 Dec 2023
NA 03 Jan 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Palakkad Project Dn AEE3
Date: 27/06/2024

Work in progress | 4% Completed

90mm pvc pipe supply 10002m completed.Laying not started..

Palakkad Project Dn AEE3
Date: 26/06/2024

Work in progress | 4% Completed

90mm pvc pipe supply 10002m completed.Laying not started..