JJM -WSS TO VALLAPUZHA-ADDITIONAL WORKS-PIPE LINE EXTENSION TO UNCOVERED AREAS AND LSGD ROAD RESTORATION WORKSPipeline Work
Project |
JJM -WSS TO VALLAPUZHA-ADDITIONAL WORKS-PIPE LINE EXTENSION TO UNCOVERED AREAS AND LSGD ROAD RESTORATION WORKSPipeline Work |
Project Code |
PKDJJM102315807 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission (JJM)-WSS to
VALLAPUZHA-ADDITIONAL WORKS-PIPE
LINE EXTENSION TO UNCOVERED AREAS
AND LSGD ROAD RESTORATION WORKSPipeline Work |
Status |
On-going |
District |
Palakkad |
Executing Office |
Palakkad Project Dn |
AS Amount (Rs) |
101000000
|
AS Number |
GO(Rt)No.897/2023/WRD |
TS Amount (Rs) |
24800000 |
TS Number |
WRD/KWA-CE(NR)/EST_TS/25906/2023_26_1_1 |
Total Bill Submitted (Rs) |
2549300 |
Total Bill Paid (Rs) |
|
Population Benefitted |
25000 |
Capacity in MLD |
5.00 |
Actual Project Completion Date |
19 Jun 2024 |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
JJM -WSS TO VALLAPUZHA-ADDITIONAL WORKS-PIPE LINE EXTENSION TO UNCOVERED AREAS AND LSGD ROAD RESTORATION WORKSPipeline Work |
Project Division Palakkad |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Jun 2024 |
90mm pvc pipe supply 10002m completed.Laying not started. |
Palakkad Project Dn AEE3 |
|
22 Jun 2024 |
90mm pvc pipe supply 10002m completed.Laying not started. |
Palakkad Project Dn AEE3 |
|
18 Jun 2024 |
90mm pvc pipe supply 10002m completed.Laying not started. |
Palakkad Project Dn AEE3 |
|
14 Jun 2024 |
90mm pvc pipe supply 10002m completed.Laying not started. |
Palakkad Project Dn AEE3 |
|
10 Jun 2024 |
90mm pvc pipe supply 10002m completed.Laying not started. |
Palakkad Project Dn AEE3 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
20/12/2023 |
Scheduled date of Completion of the Project |
19 Jun 2024 |
Expected date of Completion |
19/06/2024 |
Processing Dates
AS Date |
26 Oct 2023 |
TS Date |
08 Nov 2023 |