Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB-WSS to Perinadu and Athikkayam Villages-Phase II-Package III

Project KIIFB-WSS to Perinadu and Athikkayam Villages-Phase II-Package III
Project Code PTAKIIFB0117573P3
Type Package
Main Project KIIFB_WSS to Perinadu and Athikkayam Villages-Phase II
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Construction of tranformer building,Supply and Erection of transformer and Pump sets
Status On-going
District Pathanamthitta
Executing Office Adoor Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 11533000
TS Number TS/2021-2022/2021/5443
Technical specification Construction of tranformer building,Supply and Erection of transformer and Pump sets
Contractor Electric Project Consultants (Mob: 9446383723)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 11/08/2021
Scheduled date of Completion as per agreement 30 Aug 2022
Expected date of Completion 31/05/2023

Processing Dates

TS Date 02 Jun 2021
Estimate Approval 08 Jun 2021
NIT Approval 10 Jun 2021
Tender Closing 02 Jul 2021
Technichal Pre-Qualification 02 Jul 2021
Price bid opening 05 Jul 2021

Approval Dates

Workorder Date 09 Aug 2021
NA 11 Aug 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Adoor Project Dn AE 4
Date: 23/04/2024

Work in progress | 69% Completed

waiting for KSEB electrical HT connection.

Adoor Project Dn AE 4
Date: 17/01/2024

Work in progress | 69% Completed

work ongoing at WTP perunad.