Jal Jeevan Mission-Kasaragod District-Enmakaje Grama Panchayath-ARWSS to Enmakaje and Adjoining Villages Phase-III Reach-I Laying Distribution and Providing FHTCs
Project |
Jal Jeevan Mission-Kasaragod District-Enmakaje Grama Panchayath-ARWSS to Enmakaje and Adjoining Villages Phase-III Reach-I Laying Distribution and Providing FHTCs |
Project Code |
KGDJJM092112023 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission-Kasaragod District-Enmakaje Grama Panchayath-ARWSS to Enmakaje and Adjoining Villages Phase-III Reach-I Laying Distribution and Providing FHTCs |
Status |
On-going |
District |
Kasaragod |
Executing Office |
Kasargod PH Dn |
AS Amount (Rs) |
89100000
|
AS Number |
GO(Rt)489/2021/WRD |
TS Amount (Rs) |
71200000 |
TS Number |
16015/2021-22 |
Total Bill Submitted (Rs) |
8842480 |
Total Bill Paid (Rs) |
|
Population Benefitted |
5000 |
Capacity in MLD |
4.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
partially covered |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission-Kasaragod District-Enmakaje Grama Panchayath-ARWSS to Enmakaje and Adjoining Villages Phase-III Reach-I Laying Distribution and Providing FHTCs |
Bovikkanam WSP Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Jun 2024 |
Remaining portion of the pipe line is along the PWD road, for which applied for permission. |
Bovikkanam WSP Sn AE |
|
20 Jun 2024 |
Remaining portion of the pipe line is along the PWD road, for which applied for permission. |
Bovikkanam WSP Sn AE |
|
13 Jun 2024 |
Remaining portion of the pipe line is along the PWD road, for which applied for permission. |
Bovikkanam WSP Sn AE |
|
10 Jun 2024 |
Remaining portion of the pipe line is along the PWD road, for which applied for permission. |
Bovikkanam WSP Sn AE |
|
06 Jun 2024 |
Remaining portion of the pipe line is along the PWD road, for which applied for permission. |
Bovikkanam WSP Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
26/03/2022 |
Scheduled date of Completion of the Project |
25 Sep 2022 |
Expected date of Completion |
30/05/2024 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
23 Dec 2021 |