Project | Jal Jeevan Mission-Kasaragod District-Enmakaje Grama Panchayath-ARWSS to Enmakaje and Adjoining Villages Phase-III Reach-I Laying Distribution and Providing FHTCs |
---|---|
Project Code | KGDJJM092112023P1 |
Type | Package |
Main Project | Jal Jeevan Mission-Kasaragod District-Enmakaje Grama Panchayath-ARWSS to Enmakaje and Adjoining Villages Phase-III Reach-I Laying Distribution and Providing FHTCs |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission-Kasaragod District-Enmakaje Grama Panchayath-ARWSS to Enmakaje and Adjoining Villages Phase-III Reach-I Laying Distribution and Providing FHTCs |
Status | On-going |
District | Kasaragod |
Executing Office | Bovikkanam WSP Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 71200000 |
TS Number | 16015/2021-22 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 26/03/2022 |
---|---|
Scheduled date of Completion as per agreement | 25 Sep 2022 |
Expected date of Completion | 30/05/2024 |
TS Date | 23 Dec 2021 |
---|---|
Estimate Approval | 23 Dec 2021 |
NIT Approval | 31 Jan 2022 |
Tender Closing | 07 Feb 2022 |
Price bid opening | 09 Feb 2022 |
Workorder Date | 26 Mar 2022 |
---|---|
NA | 18 Apr 2022 |
Bovikkanam WSP Sn AE |
Date: 28/06/2024 |
Work in progress | 75% Completed
Remaining portion of the pipe line is along the PWD road, for which applied for permission..
Bovikkanam WSP Sn AE |
Date: 24/06/2024 |
Work in progress | 75% Completed
Remaining portion of the pipe line is along the PWD road, for which applied for permission..