Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Jun 2024 |
166.08/287.136 km completed. The remaining HDPE, DI, GI pipe & CWPM laying work is progressing. Balance pipes are to be supplied by the contractor. Plamaram11 LL GLSR -Haunch and side wall works in progress, floor slab RCC Completed. Munimala 6 LL GLSR- The floor slab, Haunch, and the sidewall concrete (first lift) completed ,2nd lift work ongoing. 6 LL GLSR cum BPT at Thachamala Plantation - Soil Test completed and earthwork is ongoing. PWD roads (Kakkupadi - Anakkatty Road, Jellipara - Paravalav, Kallamala - Jellipara, Agali - Jellipara, Goolikadav - karara - Mundanpara Road, Pakkulam - kandiyur - jellipara road ) work ongoing, Pmgsy road work progressing, panchayath road restoration ongoing. |
Palakkad Proj AE 3 |
|
26 Jun 2024 |
166.083275/287.136 km completed. The remaining HDPE, DI, GI pipe & CWPM laying work is progressing. Balance pipes are to be supplied by the contractor. Plamaram11 LL GLSR -Haunch and side wall works in progress, floor slab RCC Completed. Munimala 6 LL GLSR- The floor slab, Haunch, and the sidewall concrete (first lift) completed ,2nd lift work ongoing. 6 LL GLSR cum BPT at Thachamala Plantation - Soil Test completed and earthwork is ongoing. PWD roads (Kakkupadi - Anakkatty Road, Jellipara - Paravalav, Kallamala - Jellipara, Agali - Jellipara, Goolikadav - karara - Mundanpara Road, Pakkulam - kandiyur - jellipara road ) work ongoing, Pmgsy road work progressing, panchayath road restoration ongoing. |
Palakkad Proj AE 3 |
|
25 Jun 2024 |
166.083275/287.136 km completed. The remaining HDPE, DI, GI pipe & CWPM laying work is progressing. Balance pipes are to be supplied by the contractor. Plamaram11 LL GLSR -Haunch and side wall works in progress, floor slab RCC Completed. Munimala 6 LL GLSR- The floor slab, Haunch, and the sidewall concrete (first lift) completed ,2nd lift work ongoing. 6 LL GLSR cum BPT at Thachamala Plantation - Soil Test completed and earthwork is ongoing. PWD roads (Kakkupadi - Anakkatty Road, Jellipara - Paravalav, Kallamala - Jellipara, Agali - Jellipara, Goolikadav - karara - Mundanpara Road, Pakkulam - kandiyur - jellipara road ) work ongoing, Pmgsy road work progressing, panchayath road restoration ongoing. |
Palakkad Proj AE 3 |
|
24 Jun 2024 |
166.08/287.136 km completed. The remaining HDPE, DI, GI pipe & CWPM laying work is progressing. Balance pipes are to be supplied by the contractor. Plamaram11 LL GLSR -Haunch and side wall works in progress, floor slab RCC Completed. Munimala 6 LL GLSR- The floor slab, Haunch, and the sidewall concrete (first lift) completed ,2nd lift work ongoing. 6 LL GLSR cum BPT at Thachamala Plantation - Soil Test completed and earthwork is ongoing. PWD roads (Kakkupadi - Anakkatty Road, Jellipara - Paravalav, Kallamala - Jellipara, Agali - Jellipara, Goolikadav - karara - Mundanpara Road, Pakkulam - kandiyur - jellipara road ) work ongoing, Pmgsy road work progressing, panchayath road restoration ongoing. |
Palakkad Proj AE 3 |
|
22 Jun 2024 |
166.08/287.136 km completed. The remaining HDPE, DI, GI pipe & CWPM laying work is progressing. Balance pipes are to be supplied by the contractor. Plamaram11 LL GLSR - floor slab RCC Completed. Munimala 6 LL GLSR- The floor slab, Haunch, and the sidewall concrete (first lift) completed ,2nd lift work ongoing. 6 LL GLSR cum BPT at Thachamala Plantation - Soil Test completed and earthwork is ongoing. PWD roads (Kakkupadi - Anakkatty Road, Jellipara - Paravalav, Kallamala - Jellipara, Agali - Jellipara, Goolikadav - karara - Mundanpara Road, Pakkulam - kandiyur - jellipara road ) work ongoing, Pmgsy road work progressing, panchayath road restoration ongoing. |
Palakkad Proj AE 3 |
|