Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM-2020-21-Providing FHTC's in Agali Grama panchayath, Palakkad District- Phase-II

Project JJM-2020-21-Providing FHTC's in Agali Grama panchayath, Palakkad District- Phase-II
Project Code PKDJJM10204492
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Providing 3000 nos. FHTC's in in Ward nos. 8,9,10,11,12,13 Agali Grama panchayath, Palakkad District- Phase-II
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
AS Amount (Rs) 850019000
AS Number G.o(Rt) No.489/2021/WRD
TS Amount (Rs) 769000000
TS Number TS/2020-2021/2021/51
Total Bill Submitted (Rs) 258685361
Total Bill Paid (Rs) 162257780
Population Benefitted 10849
Capacity in MLD 1.43
Actual Project Completion Date 10 Nov 2024
Coverage Ward nos. 8,9,10,11,12,13 of Agali Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM-2020-21-Providing FHTC's in Agali Grama panchayath, Palakkad District- Phase-II Project Division Palakkad

Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Jun 2024 166.08/287.136 km completed. The remaining HDPE, DI, GI pipe & CWPM laying work is progressing. Balance pipes are to be supplied by the contractor. Plamaram11 LL GLSR -Haunch and side wall works in progress, floor slab RCC Completed. Munimala 6 LL GLSR- The floor slab, Haunch, and the sidewall concrete (first lift) completed ,2nd lift work ongoing. 6 LL GLSR cum BPT at Thachamala Plantation - Soil Test completed and earthwork is ongoing. PWD roads (Kakkupadi - Anakkatty Road, Jellipara - Paravalav, Kallamala - Jellipara, Agali - Jellipara, Goolikadav - karara - Mundanpara Road, Pakkulam - kandiyur - jellipara road ) work ongoing, Pmgsy road work progressing, panchayath road restoration ongoing. Palakkad Proj AE 3
26 Jun 2024 166.083275/287.136 km completed. The remaining HDPE, DI, GI pipe & CWPM laying work is progressing. Balance pipes are to be supplied by the contractor. Plamaram11 LL GLSR -Haunch and side wall works in progress, floor slab RCC Completed. Munimala 6 LL GLSR- The floor slab, Haunch, and the sidewall concrete (first lift) completed ,2nd lift work ongoing. 6 LL GLSR cum BPT at Thachamala Plantation - Soil Test completed and earthwork is ongoing. PWD roads (Kakkupadi - Anakkatty Road, Jellipara - Paravalav, Kallamala - Jellipara, Agali - Jellipara, Goolikadav - karara - Mundanpara Road, Pakkulam - kandiyur - jellipara road ) work ongoing, Pmgsy road work progressing, panchayath road restoration ongoing. Palakkad Proj AE 3
25 Jun 2024 166.083275/287.136 km completed. The remaining HDPE, DI, GI pipe & CWPM laying work is progressing. Balance pipes are to be supplied by the contractor. Plamaram11 LL GLSR -Haunch and side wall works in progress, floor slab RCC Completed. Munimala 6 LL GLSR- The floor slab, Haunch, and the sidewall concrete (first lift) completed ,2nd lift work ongoing. 6 LL GLSR cum BPT at Thachamala Plantation - Soil Test completed and earthwork is ongoing. PWD roads (Kakkupadi - Anakkatty Road, Jellipara - Paravalav, Kallamala - Jellipara, Agali - Jellipara, Goolikadav - karara - Mundanpara Road, Pakkulam - kandiyur - jellipara road ) work ongoing, Pmgsy road work progressing, panchayath road restoration ongoing. Palakkad Proj AE 3
24 Jun 2024 166.08/287.136 km completed. The remaining HDPE, DI, GI pipe & CWPM laying work is progressing. Balance pipes are to be supplied by the contractor. Plamaram11 LL GLSR -Haunch and side wall works in progress, floor slab RCC Completed. Munimala 6 LL GLSR- The floor slab, Haunch, and the sidewall concrete (first lift) completed ,2nd lift work ongoing. 6 LL GLSR cum BPT at Thachamala Plantation - Soil Test completed and earthwork is ongoing. PWD roads (Kakkupadi - Anakkatty Road, Jellipara - Paravalav, Kallamala - Jellipara, Agali - Jellipara, Goolikadav - karara - Mundanpara Road, Pakkulam - kandiyur - jellipara road ) work ongoing, Pmgsy road work progressing, panchayath road restoration ongoing. Palakkad Proj AE 3
22 Jun 2024 166.08/287.136 km completed. The remaining HDPE, DI, GI pipe & CWPM laying work is progressing. Balance pipes are to be supplied by the contractor. Plamaram11 LL GLSR - floor slab RCC Completed. Munimala 6 LL GLSR- The floor slab, Haunch, and the sidewall concrete (first lift) completed ,2nd lift work ongoing. 6 LL GLSR cum BPT at Thachamala Plantation - Soil Test completed and earthwork is ongoing. PWD roads (Kakkupadi - Anakkatty Road, Jellipara - Paravalav, Kallamala - Jellipara, Agali - Jellipara, Goolikadav - karara - Mundanpara Road, Pakkulam - kandiyur - jellipara road ) work ongoing, Pmgsy road work progressing, panchayath road restoration ongoing. Palakkad Proj AE 3

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 17/05/2023
Scheduled date of Completion of the Project 29 Mar 2024
Expected date of Completion 10/11/2024

Processing Dates

AS Date 27 Oct 2020
TS Date 05 Jan 2021

Other details

Project Officers View