Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM-2020-21-Providing FHTC's in Agali Grama panchayath, Palakkad District- Phase-II

Project JJM-2020-21-Providing FHTC's in Agali Grama panchayath, Palakkad District- Phase-II
Project Code PKDJJM10204492P1
Type Package
Main Project JJM-2020-21-Providing FHTC's in Agali Grama panchayath, Palakkad District- Phase-II
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Providing 3000 nos. FHTC's in Ward nos. 8,9,10,11,12,13 of Agali Grama panchayath, Palakkad District- Phase-II
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 769000000
TS Number TS/2020-2021/2021/51
Technical specification The proposed project is for retrofitting of the existing water supply scheme under the control of the Grama Panchayath after commissioning of ongoing phase I project under the NABARD with a pipe line extension / replacement of 50 kms and providing 3000 nos. FHTCs to cover a population of 10849 nos. in ward nos. 8,9,10,12,13 in full and ward no. 11 in part of Agali Panchayath. It is proposed to lay 47.38 kms of pipe for line extention / Augmentation of existing water supply network after survey and design. 47.8 kms – 200m DI K9 – 2 km, 160 mm PVC – 9.18 km, 140mm PVC-9.38 km 110 mm PVC -9.69 km, 90 mm PVC -13.26 km and G.I pipes – 150 mm GI – 1 km, 125 mm GI - 0.8 km, 100 mm GI – 0.5 km, 80 mm GI – 2 km This project is to provide Functional Household Tap Connections in in ward nos. 8,9,10,12,13 Agali panchayath in Palakkad District on EPCM basis from the existing E1.50 LL reservoir at Kottamedu and existing Reservoir of capacity 5.70 LL Agali Rest house compound
Contractor M/S HILL TRACK CONSTRUCTIONS PVT.LTD (Mob: 9447666114)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
31 Aug 2022 Pending Pending Land Related Risk 20 cents of land to be otained in Thachamala plantation No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/05/2023
Scheduled date of Completion as per agreement 29 Mar 2024
Expected date of Completion 10/11/2024

Processing Dates

TS Date 05 Jan 2021
Estimate Approval 05 Jan 2021
NIT Approval 06 Jan 2021
Tender Closing 09 Feb 2021
Technichal Pre-Qualification 15 Feb 2023
Price bid opening 01 Mar 2023

Approval Dates

Workorder Date 17 Mar 2023
NA 28 Mar 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Palakkad Proj AE 3
Date: 27/06/2024

Work in progress | 27% Completed

166.083275/287.136 km completed. The remaining HDPE, DI, GI pipe & CWPM laying work is progressing. Balance pipes are to be supplied by the contractor. Plamaram11 LL GLSR -Haunch and side wall works in progress, floor slab RCC Completed. Munimala 6 LL GLSR- The floor slab, Haunch, and the sidewall concrete (first lift) completed ,2nd lift work ongoing. 6 LL GLSR cum BPT at Thachamala Plantation - Soil Test completed and earthwork is ongoing. PWD roads (Kakkupadi - Anakkatty Road, Jellipara - Paravalav, Kallamala - Jellipara, Agali - Jellipara, Goolikadav - karara - Mundanpara Road, Pakkulam - kandiyur - jellipara road ) work ongoing, Pmgsy road work progressing, panchayath road restoration ongoing. .

Palakkad Proj AE 3
Date: 26/06/2024

Work in progress | 27% Completed

166.083275/287.136 km completed. The remaining HDPE, DI, GI pipe & CWPM laying work is progressing. Balance pipes are to be supplied by the contractor. Plamaram11 LL GLSR -Haunch and side wall works in progress, floor slab RCC Completed. Munimala 6 LL GLSR- The floor slab, Haunch, and the sidewall concrete (first lift) completed ,2nd lift work ongoing. 6 LL GLSR cum BPT at Thachamala Plantation - Soil Test completed and earthwork is ongoing. PWD roads (Kakkupadi - Anakkatty Road, Jellipara - Paravalav, Kallamala - Jellipara, Agali - Jellipara, Goolikadav - karara - Mundanpara Road, Pakkulam - kandiyur - jellipara road ) work ongoing, Pmgsy road work progressing, panchayath road restoration ongoing. .