Project | JJM-2020-21-Providing FHTC's in Agali Grama panchayath, Palakkad District- Phase-II |
---|---|
Project Code | PKDJJM10204492P1 |
Type | Package |
Main Project | JJM-2020-21-Providing FHTC's in Agali Grama panchayath, Palakkad District- Phase-II |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Providing 3000 nos. FHTC's in Ward nos. 8,9,10,11,12,13 of Agali Grama panchayath, Palakkad District- Phase-II |
Status | On-going |
District | Palakkad |
Executing Office | Palakkad Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 769000000 |
TS Number | TS/2020-2021/2021/51 |
Technical specification | The proposed project is for retrofitting of the existing water supply scheme under the control of the Grama Panchayath after commissioning of ongoing phase I project under the NABARD with a pipe line extension / replacement of 50 kms and providing 3000 nos. FHTCs to cover a population of 10849 nos. in ward nos. 8,9,10,12,13 in full and ward no. 11 in part of Agali Panchayath. It is proposed to lay 47.38 kms of pipe for line extention / Augmentation of existing water supply network after survey and design. 47.8 kms – 200m DI K9 – 2 km, 160 mm PVC – 9.18 km, 140mm PVC-9.38 km 110 mm PVC -9.69 km, 90 mm PVC -13.26 km and G.I pipes – 150 mm GI – 1 km, 125 mm GI - 0.8 km, 100 mm GI – 0.5 km, 80 mm GI – 2 km This project is to provide Functional Household Tap Connections in in ward nos. 8,9,10,12,13 Agali panchayath in Palakkad District on EPCM basis from the existing E1.50 LL reservoir at Kottamedu and existing Reservoir of capacity 5.70 LL Agali Rest house compound |
Contractor | M/S HILL TRACK CONSTRUCTIONS PVT.LTD (Mob: 9447666114) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
31 Aug 2022 | Pending | Pending | Land Related Risk | 20 cents of land to be otained in Thachamala plantation | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 18/05/2023 |
---|---|
Scheduled date of Completion as per agreement | 29 Mar 2024 |
Expected date of Completion | 10/11/2024 |
TS Date | 05 Jan 2021 |
---|---|
Estimate Approval | 05 Jan 2021 |
NIT Approval | 06 Jan 2021 |
Tender Closing | 09 Feb 2021 |
Technichal Pre-Qualification | 15 Feb 2023 |
Price bid opening | 01 Mar 2023 |
Workorder Date | 17 Mar 2023 |
---|---|
NA | 28 Mar 2023 |
Palakkad Proj AE 3 |
Date: 27/06/2024 |
Work in progress | 27% Completed
166.083275/287.136 km completed. The remaining HDPE, DI, GI pipe & CWPM laying work is progressing. Balance pipes are to be supplied by the contractor. Plamaram11 LL GLSR -Haunch and side wall works in progress, floor slab RCC Completed. Munimala 6 LL GLSR- The floor slab, Haunch, and the sidewall concrete (first lift) completed ,2nd lift work ongoing. 6 LL GLSR cum BPT at Thachamala Plantation - Soil Test completed and earthwork is ongoing. PWD roads (Kakkupadi - Anakkatty Road, Jellipara - Paravalav, Kallamala - Jellipara, Agali - Jellipara, Goolikadav - karara - Mundanpara Road, Pakkulam - kandiyur - jellipara road ) work ongoing, Pmgsy road work progressing, panchayath road restoration ongoing. .
Palakkad Proj AE 3 |
Date: 26/06/2024 |
Work in progress | 27% Completed
166.083275/287.136 km completed. The remaining HDPE, DI, GI pipe & CWPM laying work is progressing. Balance pipes are to be supplied by the contractor. Plamaram11 LL GLSR -Haunch and side wall works in progress, floor slab RCC Completed. Munimala 6 LL GLSR- The floor slab, Haunch, and the sidewall concrete (first lift) completed ,2nd lift work ongoing. 6 LL GLSR cum BPT at Thachamala Plantation - Soil Test completed and earthwork is ongoing. PWD roads (Kakkupadi - Anakkatty Road, Jellipara - Paravalav, Kallamala - Jellipara, Agali - Jellipara, Goolikadav - karara - Mundanpara Road, Pakkulam - kandiyur - jellipara road ) work ongoing, Pmgsy road work progressing, panchayath road restoration ongoing. .