Jal Jeevan Mission 2021-22- Providing FHTC's (230nos), laying distribution lines, Construction of 8 LL OHSR, Supply, erection and commissioning of motor pump sets in Nellaya Grama Panchayath-- Phase III

Project Jal Jeevan Mission 2021-22- Providing FHTC's (230nos), laying distribution lines, Construction of 8 LL OHSR, Supply, erection and commissioning of motor pump sets in Nellaya Grama Panchayath-- Phase III
Project Code PKDJJM022212212P1
Type Package
Main Project Jal Jeevan Mission 2021-22- Providing FHTC's (230nos), laying distribution lines, Construction of 8 LL OHSR, Supply, erection and commissioning of motor pump sets in Nellaya Grama Panchayath-- Phase III
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission 2021-22- Providing FHTC's (230nos), laying distribution lines, Construction of 8 LL OHSR, Supply, erection and commissioning of motor pump sets in Nellaya Grama Panchayath-- Phase III
Status On-going
District Palakkad
Executing Office Pattambi PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 71400000
TS Number TS/2022-2023/2021/26557
Technical specification Providing FHTC's (230nos), laying distribution lines, Construction of 8 LL OHSR, Supply, erection and commissioning of motor pump sets in Nellaya Grama Panchayath-- Phase III
Contractor Anuraag Engineers Pvt Ltd (Mob: 9447847913)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 24/08/2022
Scheduled date of Completion as per agreement 23 Feb 2023
Expected date of Completion 31/03/2024

Processing Dates

TS Date 02 Jun 2022
Estimate Approval 02 Jun 2022
Tender Closing 14 Jun 2022
Price bid opening 17 Jun 2022
NA 29 Sep 2022

Approval Dates

Workorder Date 24 Aug 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Pattambi PH Sn AE
Date: 01/07/2024

Work in progress | 64% Completed

15804 meter 90mm HDPE pipe laid, 80mm GI pipe 5540 m laid, 121 connections provided.8LL Tank work started. 19 nos of footing concreting completed. back wash chamber work completed. Tank work third floor brace beam work on going, GI work ongoing (8300m ).

Pattambi PH Sn AE
Date: 26/06/2024

Work in progress | 64% Completed

15804 meter 90mm HDPE pipe laid, 80mm GI pipe 5540 m laid, 121 connections provided.8LL Tank work started. 19 nos of footing concreting completed. back wash chamber work completed. Tank work third floor brace beam work on going, GI work ongoing (8300m ) .