Jal Jeevan Mission 2021-22- Providing FHTC's (230nos), laying distribution lines, Construction of 8 LL OHSR, Supply, erection and commissioning of motor pump sets in Nellaya Grama Panchayath-- Phase III
Project |
Jal Jeevan Mission 2021-22- Providing FHTC's (230nos), laying distribution lines, Construction of 8 LL OHSR, Supply, erection and commissioning of motor pump sets in Nellaya Grama Panchayath-- Phase III |
Project Code |
PKDJJM022212212P1 |
Type |
Package |
Main Project |
Jal Jeevan Mission 2021-22- Providing FHTC's (230nos), laying distribution lines, Construction of 8 LL OHSR, Supply, erection and commissioning of motor pump sets in Nellaya Grama Panchayath-- Phase III
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission 2021-22- Providing FHTC's (230nos), laying distribution lines, Construction of 8 LL OHSR, Supply, erection and commissioning of motor pump sets in Nellaya Grama Panchayath-- Phase III
|
Status |
On-going |
District |
Palakkad |
Executing Office |
Pattambi PH Sn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
71400000 |
TS Number |
TS/2022-2023/2021/26557 |
Technical specification |
Providing FHTC's (230nos), laying distribution lines, Construction of 8 LL OHSR, Supply, erection and commissioning of motor pump sets in Nellaya Grama Panchayath-- Phase III |
Contractor |
Anuraag Engineers Pvt Ltd (Mob: 9447847913) |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
24/08/2022 |
Scheduled date of Completion as per agreement |
23 Feb 2023 |
Expected date of Completion |
31/03/2024 |
Processing Dates
TS Date |
02 Jun 2022 |
Estimate Approval |
02 Jun 2022 |
Tender Closing |
14 Jun 2022 |
Price bid opening |
17 Jun 2022 |
NA |
29 Sep 2022 |
Approval Dates
Workorder Date |
24 Aug 2022 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Pattambi PH Sn AE |
Date: 01/07/2024 |
Work in progress | 64% Completed
15804 meter 90mm HDPE pipe laid, 80mm GI pipe 5540 m laid, 121 connections provided.8LL Tank work started. 19 nos of footing concreting completed. back wash chamber work completed. Tank work third floor brace beam work on going, GI work ongoing (8300m ).
Pattambi PH Sn AE |
Date: 26/06/2024 |
Work in progress | 64% Completed
15804 meter 90mm HDPE pipe laid, 80mm GI pipe 5540 m laid, 121 connections provided.8LL Tank work started. 19 nos of footing concreting completed. back wash chamber work completed. Tank work third floor brace beam work on going, GI work ongoing (8300m )
.