Jal Jeevan Mission 2021-22- Providing FHTC's (230nos), laying distribution lines, Construction of 8 LL OHSR, Supply, erection and commissioning of motor pump sets in Nellaya Grama Panchayath-- Phase III

Project Jal Jeevan Mission 2021-22- Providing FHTC's (230nos), laying distribution lines, Construction of 8 LL OHSR, Supply, erection and commissioning of motor pump sets in Nellaya Grama Panchayath-- Phase III
Project Code PKDJJM022212212
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission 2021-22- Providing FHTC's (230nos), laying distribution lines, Construction of 8 LL OHSR, Supply, erection and commissioning of motor pump sets in Nellaya Grama Panchayath-- Phase III
Status On-going
District Palakkad
Executing Office Shornur PH Dn
AS Amount (Rs) 76000000
AS Number G.O.(Rt)No.134/2022/WRD
TS Amount (Rs) 71400000
TS Number TS/2022-2023/2021/26557
Total Bill Submitted (Rs) 7286724
Total Bill Paid (Rs) 7286724
Population Benefitted 36146
Capacity in MLD 6.00
Actual Project Completion Date Date is not specified
Coverage 230nos

Packages

No. Project Name Location View
1 Jal Jeevan Mission 2021-22- Providing FHTC's (230nos), laying distribution lines, Construction of 8 LL OHSR, Supply, erection and commissioning of motor pump sets in Nellaya Grama Panchayath-- Phase III Pattambi PH Sn
2 Jal Jeevan Mission (JJM)-Nellaya-Mavundirikkadavu PWD road Restoration -Nellaya JJM Phase 3 PWD road restoration at Nellaya panchayath-Pipeline Work Pattambi PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Feb 2024 15804 meter 90mm HDPE pipe laid, 80mm GI pipe 5540 m laid, 121 connections provided.8LL Tank work started. 19 no.s of footing concreting completed. back wash chamber work completed.Tank work third floor brace beam work on going Shornur PH Dn EE
27 Dec 2022 1300 meter 90mm HDPE pipe laid & the laying work in progress , 30m concrete cutting, inter linking - 3 nos. Shornur PH Dn EE
11 Oct 2022 Work order issued Shoranur PH Sub Dn AEE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 24/08/2022
Scheduled date of Completion of the Project 23 Feb 2023
Expected date of Completion 31/03/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 02 Jun 2022