Jal Jeevan Mission 2021-22- Providing FHTC's (230nos), laying distribution lines, Construction of 8 LL OHSR, Supply, erection and commissioning of motor pump sets in Nellaya Grama Panchayath-- Phase III
Project |
Jal Jeevan Mission 2021-22- Providing FHTC's (230nos), laying distribution lines, Construction of 8 LL OHSR, Supply, erection and commissioning of motor pump sets in Nellaya Grama Panchayath-- Phase III |
Project Code |
PKDJJM022212212 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission 2021-22- Providing FHTC's (230nos), laying distribution lines, Construction of 8 LL OHSR, Supply, erection and commissioning of motor pump sets in Nellaya Grama Panchayath-- Phase III |
Status |
On-going |
District |
Palakkad |
Executing Office |
Shornur PH Dn |
AS Amount (Rs) |
76000000
|
AS Number |
G.O.(Rt)No.134/2022/WRD |
TS Amount (Rs) |
71400000 |
TS Number |
TS/2022-2023/2021/26557 |
Total Bill Submitted (Rs) |
7286724 |
Total Bill Paid (Rs) |
7286724 |
Population Benefitted |
36146 |
Capacity in MLD |
6.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
230nos |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission 2021-22- Providing FHTC's (230nos), laying distribution lines, Construction of 8 LL OHSR, Supply, erection and commissioning of motor pump sets in Nellaya Grama Panchayath-- Phase III |
Pattambi PH Sn |
|
2 |
Jal Jeevan Mission (JJM)-Nellaya-Mavundirikkadavu PWD road Restoration -Nellaya JJM Phase 3 PWD road restoration at Nellaya panchayath-Pipeline Work |
Pattambi PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
21 Feb 2024 |
15804 meter 90mm HDPE pipe laid, 80mm GI pipe 5540 m laid, 121 connections provided.8LL Tank work started. 19 no.s of footing concreting completed. back wash chamber work completed.Tank work third floor brace beam work on going |
Shornur PH Dn EE |
|
27 Dec 2022 |
1300 meter 90mm HDPE pipe laid & the laying work in progress , 30m concrete cutting, inter linking - 3 nos.
|
Shornur PH Dn EE |
|
11 Oct 2022 |
Work order issued |
Shoranur PH Sub Dn AEE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
24/08/2022 |
Scheduled date of Completion of the Project |
23 Feb 2023 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
02 Jun 2022 |