Project | Jal Jeevan Mission - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 20LL OHSR at Valayakkad in Pudhupariyarum panchayath - Zone 5 |
---|---|
Project Code | PKDJJM12206105P1 |
Type | Package |
Main Project | Jal Jeevan Mission - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 20LL OHSR at Valayakkad in Pudhupariyarum panchayath - Zone 5 |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 20LL OHSR at Valayakkad in Pudhupariyarum panchayath - Zone 5 |
Status | On-going |
District | Palakkad |
Executing Office | Chittur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 299700000 |
TS Number | TS/2020-2021/2020/582 |
Technical specification | Jal Jeevan Mission - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 20LL OHSR at Valayakkad in Pudhupariyarum panchayath - Zone 5 |
Contractor | Ravi Construction company (Mob: 8490866160) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 03/05/2021 |
---|---|
Scheduled date of Completion as per agreement | 02 Nov 2021 |
Expected date of Completion | 31/12/2024 |
TS Date | 29 Dec 2020 |
---|---|
Estimate Approval | 29 Dec 2020 |
NIT Approval | 30 Dec 2020 |
Tender Closing | 25 Mar 2021 |
Technichal Pre-Qualification | 22 Apr 2021 |
Price bid opening | 22 Apr 2021 |
Workorder Date | 03 May 2021 |
---|---|
NA | 24 Jun 2021 |
Chittur Project Dn - AE 2 |
Date: 27/06/2024 |
Work in progress | 91% Completed
total pipe supplied, Total-160.391 KM laid,/ out of 182 km, FHTC-2761 Nos/4295nos 1).90mm pvc pipe 6 kg pvc pipe- 48.797 KM 2).90mm pvc pipe 8 kg pvc pipe- 78.176km 3).110mm pvc pipe 6 kg pvc pipe- 4.521 km 4).110mm pvc pipe 8 kg pvc pipe- 5.209km, 5) 250mm DI-2.640km, 6).200mm DI- 3.279km, 7).rider main-90mm -6kg- 1.00km 8)140mm 8kg- 3.032km 9).140mm6kg- 5.104km 10)160mm 6kg-2.644km 11)160mm 8 kg-0.900 km 12)150mm GI -53.75M 13)100mm GI-200m 14).80mm GI- 0. 822km , 15) 125 mm GI pipe-74.00m 16)500 mm DI pipe-1321.80 m 17)600 mm DI-459M 18)350 mm DI pipe-266.70m 19) 400 mm D I pipe-46055m 20)300 mm di pipe-222m 21)450mm DI -26M 21) FHTC-2604Nos ( 6th bill FHTC-500, 7th bill-1200,8TH bill-660, total billed FHTC-2360.
Chittur Project Dn - AE 2 |
Date: 20/06/2024 |
Work in progress | 91% Completed
total pipe supplied, Total-160.391 KM laid,/ out of 182 km, FHTC-2761 Nos/4295nos 1).90mm pvc pipe 6 kg pvc pipe- 48.797 KM 2).90mm pvc pipe 8 kg pvc pipe- 78.176km 3).110mm pvc pipe 6 kg pvc pipe- 4.521 km 4).110mm pvc pipe 8 kg pvc pipe- 5.209km, 5) 250mm DI-2.640km, 6).200mm DI- 3.279km, 7).rider main-90mm -6kg- 1.00km 8)140mm 8kg- 3.032km 9).140mm6kg- 5.104km 10)160mm 6kg-2.644km 11)160mm 8 kg-0.900 km 12)150mm GI -53.75M 13)100mm GI-200m 14).80mm GI- 0. 822km , 15) 125 mm GI pipe-74.00m 16)500 mm DI pipe-1321.80 m 17)600 mm DI-459M 18)350 mm DI pipe-266.70m 19) 400 mm D I pipe-46055m 20)300 mm di pipe-222m 21)450mm DI -26M 21) FHTC-2604Nos ( 6th bill FHTC-500, 7th bill-1200,8TH bill-660, total billed FHTC-2360.