Jal Jeevan Mission - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 20LL OHSR at Valayakkad in Pudhupariyarum panchayath - Zone 5

Project Jal Jeevan Mission - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 20LL OHSR at Valayakkad in Pudhupariyarum panchayath - Zone 5
Project Code PKDJJM12206105P1
Type Package
Main Project Jal Jeevan Mission - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 20LL OHSR at Valayakkad in Pudhupariyarum panchayath - Zone 5
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 20LL OHSR at Valayakkad in Pudhupariyarum panchayath - Zone 5
Status On-going
District Palakkad
Executing Office Chittur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 299700000
TS Number TS/2020-2021/2020/582
Technical specification Jal Jeevan Mission - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 20LL OHSR at Valayakkad in Pudhupariyarum panchayath - Zone 5
Contractor Ravi Construction company (Mob: 8490866160)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 03/05/2021
Scheduled date of Completion as per agreement 02 Nov 2021
Expected date of Completion 31/12/2024

Processing Dates

TS Date 29 Dec 2020
Estimate Approval 29 Dec 2020
NIT Approval 30 Dec 2020
Tender Closing 25 Mar 2021
Technichal Pre-Qualification 22 Apr 2021
Price bid opening 22 Apr 2021

Approval Dates

Workorder Date 03 May 2021
NA 24 Jun 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Chittur Project Dn - AE 2
Date: 27/06/2024

Work in progress | 91% Completed

total pipe supplied, Total-160.391 KM laid,/ out of 182 km, FHTC-2761 Nos/4295nos 1).90mm pvc pipe 6 kg pvc pipe- 48.797 KM 2).90mm pvc pipe 8 kg pvc pipe- 78.176km 3).110mm pvc pipe 6 kg pvc pipe- 4.521 km 4).110mm pvc pipe 8 kg pvc pipe- 5.209km, 5) 250mm DI-2.640km, 6).200mm DI- 3.279km, 7).rider main-90mm -6kg- 1.00km 8)140mm 8kg- 3.032km 9).140mm6kg- 5.104km 10)160mm 6kg-2.644km 11)160mm 8 kg-0.900 km 12)150mm GI -53.75M 13)100mm GI-200m 14).80mm GI- 0. 822km , 15) 125 mm GI pipe-74.00m 16)500 mm DI pipe-1321.80 m 17)600 mm DI-459M 18)350 mm DI pipe-266.70m 19) 400 mm D I pipe-46055m 20)300 mm di pipe-222m 21)450mm DI -26M 21) FHTC-2604Nos ( 6th bill FHTC-500, 7th bill-1200,8TH bill-660, total billed FHTC-2360.

Chittur Project Dn - AE 2
Date: 20/06/2024

Work in progress | 91% Completed

total pipe supplied, Total-160.391 KM laid,/ out of 182 km, FHTC-2761 Nos/4295nos 1).90mm pvc pipe 6 kg pvc pipe- 48.797 KM 2).90mm pvc pipe 8 kg pvc pipe- 78.176km 3).110mm pvc pipe 6 kg pvc pipe- 4.521 km 4).110mm pvc pipe 8 kg pvc pipe- 5.209km, 5) 250mm DI-2.640km, 6).200mm DI- 3.279km, 7).rider main-90mm -6kg- 1.00km 8)140mm 8kg- 3.032km 9).140mm6kg- 5.104km 10)160mm 6kg-2.644km 11)160mm 8 kg-0.900 km 12)150mm GI -53.75M 13)100mm GI-200m 14).80mm GI- 0. 822km , 15) 125 mm GI pipe-74.00m 16)500 mm DI pipe-1321.80 m 17)600 mm DI-459M 18)350 mm DI pipe-266.70m 19) 400 mm D I pipe-46055m 20)300 mm di pipe-222m 21)450mm DI -26M 21) FHTC-2604Nos ( 6th bill FHTC-500, 7th bill-1200,8TH bill-660, total billed FHTC-2360.