Jal Jeevan Mission - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 20LL OHSR at Valayakkad in Pudhupariyarum panchayath - Zone 5

Project Jal Jeevan Mission - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 20LL OHSR at Valayakkad in Pudhupariyarum panchayath - Zone 5
Project Code PKDJJM12206105
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 20LL OHSR at Valayakkad in Pudhupariyarum panchayath - Zone 5
Status On-going
District Palakkad
Executing Office Chittur Project Dn
AS Amount (Rs) 327000000
AS Number GO(Rt) No. 777/2020/WRD
TS Amount (Rs) 299700000
TS Number TS/2020-2021/2020/582
Total Bill Submitted (Rs) 182534580
Total Bill Paid (Rs) 182534580
Population Benefitted 51307
Capacity in MLD 0.00
Actual Project Completion Date 31 Dec 2024
Coverage Valayakkad in Pudhupariyarum panchayath

Packages

No. Project Name Location View
1 Jal Jeevan Mission - CWSS to Resolve the Scarcity of drinking water in various panchayaths in Malampuzha Constituency -Phase II - Laying Distribution System and Providing FHTCs from 20LL OHSR at Valayakkad in Pudhupariyarum panchayath - Zone 5 Project Division Chittur

Overall Project Status

Status Date Overall Project Status Project Officer Contact
20 Jun 2024 Work in progress | 91% Completed | 20/06/2024 total pipe supplied, Total-160.391 KM laid,/ out of 182 km, FHTC-2761 Nos/4295nos 1).90mm pvc pipe 6 kg pvc pipe- 48.797 KM 2).90mm pvc pipe 8 kg pvc pipe- 78.176km 3).110mm pvc pipe 6 kg pvc pipe- 4.521 km 4).110mm pvc pipe 8 kg pvc pipe- 5.209km, 5) 250mm DI-2.640km, 6).200mm DI- 3.279km, 7).rider main-90mm -6kg- 1.00km 8)140mm 8kg- 3.032km 9).140mm6kg- 5.104km 10)160mm 6kg-2.644km 11)160mm 8 kg-0.900 km 12)150mm GI -53.75M 13)100mm GI-200m 14).80mm GI- 0. 822km , 15) 125 mm GI pipe-74.00m 16)500 mm DI pipe-1321.80 m 17)600 mm DI-459M 18)350 mm DI pipe-266.70m 19) 400 mm D I pipe-46055m 20)300 mm di pipe-222m 21)450mm DI -26M 21) FHTC-2604Nos ( 6th bill FHTC-500, 7th bill-1200,8TH bill-660, total billed FHTC-2360 Chittur Project Dn - AE 2
12 Jun 2024 Work in progress | 91% Completed | 12/06/2024 total pipe supplied, Total-160.391 KM laid,/ out of 182 km, FHTC-2761 Nos/4295nos 1).90mm pvc pipe 6 kg pvc pipe- 48.797 KM 2).90mm pvc pipe 8 kg pvc pipe- 78.176km 3).110mm pvc pipe 6 kg pvc pipe- 4.521 km 4).110mm pvc pipe 8 kg pvc pipe- 5.209km, 5) 250mm DI-2.640km, 6).200mm DI- 3.279km, 7).rider main-90mm -6kg- 1.00km 8)140mm 8kg- 3.032km 9).140mm6kg- 5.104km 10)160mm 6kg-2.644km 11)160mm 8 kg-0.900 km 12)150mm GI -53.75M 13)100mm GI-200m 14).80mm GI- 0. 822km , 15) 125 mm GI pipe-74.00m 16)500 mm DI pipe-1321.80 m 17)600 mm DI-459M 18)350 mm DI pipe-266.70m 19) 400 mm D I pipe-46055m 20)300 mm di pipe-222m 21)450mm DI -26M 21) FHTC-2604Nos ( 6th bill FHTC-500, 7th bill-1200,8TH bill-660, total billed FHTC-2360 Chittur Project Dn - AE 2
06 Jun 2024 Work in progress | 91% Completed | 06/06/2024 Total pipe supplied, Total-160.391 KM laid,/ out of 182 km, FHTC-2761 Nos/4295nos 1).90mm pvc pipe 6 kg pvc pipe- 48.797 KM 2).90mm pvc pipe 8 kg pvc pipe- 78.176km 3).110mm pvc pipe 6 kg pvc pipe- 4.521 km 4).110mm pvc pipe 8 kg pvc pipe- 5.209km, 5) 250mm DI-2.640km, 6).200mm DI- 3.279km, 7).rider main-90mm -6kg- 1.00km 8)140mm 8kg- 3.032km 9).140mm6kg- 5.104km 10)160mm 6kg-2.644km 11)160mm 8 kg-0.900 km 12)150mm GI -53.75M 13)100mm GI-200m 14).80mm GI- 0. 822km , 15) 125 mm GI pipe-74.00m 16)500 mm DI pipe-1321.80 m 17)600 mm DI-459M 18)350 mm DI pipe-266.70m 19) 400 mm D I pipe-46055m 20)300 mm di pipe-222m 21)450mm DI -26M 21) FHTC-2604Nos ( 6th bill FHTC-500, 7th bill-1200,8TH bill-660, total billed FHTC-2360 Chittur Project Dn - AE 2
30 May 2024 Work in progress | 91% Completed | 30/05/2024 Total pipe supplied, Total-160.391 KM laid,/ out of 182 km, FHTC-2761 Nos/4295nos 1).90mm pvc pipe 6 kg pvc pipe- 48.797 KM 2).90mm pvc pipe 8 kg pvc pipe- 78.176km 3).110mm pvc pipe 6 kg pvc pipe- 4.521 km 4).110mm pvc pipe 8 kg pvc pipe- 5.209km, 5) 250mm DI-2.640km, 6).200mm DI- 3.279km, 7).rider main-90mm -6kg- 1.00km 8)140mm 8kg- 3.032km 9).140mm6kg- 5.104km 10)160mm 6kg-2.644km 11)160mm 8 kg-0.900 km 12)150mm GI -53.75M 13)100mm GI-200m 14).80mm GI- 0. 822km , 15) 125 mm GI pipe-74.00m 16)500 mm DI pipe-1321.80 m 17)600 mm DI-459M 18)350 mm DI pipe-266.70m 19) 400 mm D I pipe-46055m 20)300 mm di pipe-222m 21)450mm DI -26M 21) FHTC-2604Nos ( 6th bill FHTC-500, 7th bill-1200,8TH bill-660, total billed FHTC-2360 Chittur Project Dn - AE 2
23 May 2024 Work in progress | 91% Completed | 23/05/2024 Total pipe supplied, Total-160.391 KM laid,/ out of 182 km, FHTC-2761 Nos/4295nos 1).90mm pvc pipe 6 kg pvc pipe- 48.797 KM 2).90mm pvc pipe 8 kg pvc pipe- 78.176km 3).110mm pvc pipe 6 kg pvc pipe- 4.521 km 4).110mm pvc pipe 8 kg pvc pipe- 5.209km, 5) 250mm DI-2.640km, 6).200mm DI- 3.279km, 7).rider main-90mm -6kg- 1.00km 8)140mm 8kg- 3.032km 9).140mm6kg- 5.104km 10)160mm 6kg-2.644km 11)160mm 8 kg-0.900 km 12)150mm GI -53.75M 13)100mm GI-200m 14).80mm GI- 0. 822km , 15) 125 mm GI pipe-74.00m 16)500 mm DI pipe-1321.80 m 17)600 mm DI-459M 18)350 mm DI pipe-266.70m 19) 400 mm D I pipe-46055m 20)300 mm di pipe-222m 21)450mm DI -26M 21) FHTC-2604Nos ( 6th bill FHTC-500, 7th bill-1200,8TH bill-660, total billed FHTC-2360 Chittur Project Dn - AE 2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 03/05/2021
Scheduled date of Completion of the Project 02 Nov 2021
Expected date of Completion 31/12/2023

Processing Dates

AS Date 24 Dec 2020
TS Date 29 Dec 2020

Other details

Project Officers View