Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission 2020-21 ( Phase III) -PRWSS . Providing Distribution network and FHTCs in Chalissery Panchayath Panchayath -General civil work

Project Jal Jeevan Mission 2020-21 ( Phase III) -PRWSS . Providing Distribution network and FHTCs in Chalissery Panchayath Panchayath -General civil work
Project Code TCRJJM022213948
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission 2020-21 ( Phase III) -PRWSS . Providing Distribution network and FHTCs in Chalissery Panchayath Panchayath -General civil work
Status On-going
District Thrissur
Executing Office Thrissur PH Dn
AS Amount (Rs) 239992000
AS Number G.O.(Rt)No.134/2022/WRD
TS Amount (Rs) 160300000
TS Number WRD/KWA-CEP/EST_TS/334/2022_5_1_1 Dated: 23-09-2022
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 38339
Capacity in MLD 33.00
Actual Project Completion Date 25 Dec 2023
Coverage In Chalissery Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission 2020-21 ( Phase III) -PRWSS . Providing Distribution network and FHTCs in Chalissery Panchayath Panchayath -General civil work Thrithala Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Jun 2024 Work is ongoing. 95% laying work completed. Road work is pending 384 FHTCs given. Thrissur PH Dn EE
22 Jun 2024 Work is ongoing. 95% laying work completed. Road work is pending 384 FHTCs given. Thrissur PH Dn EE
21 Jun 2024 Work is ongoing. 95% laying work completed. Road work is pending 384 FHTCs given. Thrissur PH Dn EE
20 Jun 2024 Work is ongoing. 95% laying work completed. Road work is pending 384 FHTCs given. Thrissur PH Dn EE
19 Jun 2024 Work is ongoing. 95% laying work completed. Road work is pending 384 FHTCs given. Thrissur PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 26/12/2022
Scheduled date of Completion of the Project 25 Dec 2023
Expected date of Completion 30/06/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 23 Sep 2022

Other details

Project Officers View