Jal Jeevan Mission 2020-21 ( Phase III) -PRWSS . Providing Distribution network and FHTCs in Chalissery Panchayath Panchayath -General civil work

Project Jal Jeevan Mission 2020-21 ( Phase III) -PRWSS . Providing Distribution network and FHTCs in Chalissery Panchayath Panchayath -General civil work
Project Code TCRJJM022213948P1
Type Package
Main Project Jal Jeevan Mission 2020-21 ( Phase III) -PRWSS . Providing Distribution network and FHTCs in Chalissery Panchayath Panchayath -General civil work
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission 2020-21 ( Phase III) -PRWSS . Providing Distribution network and FHTCs in Chalissery Panchayath Panchayath -General civil work
Status On-going
District Thrissur
Executing Office Thrithala Sn
Agreement Number
Agreement Date
TS Amount (Rs) 160300000
TS Number WRD/KWA-CEP/EST_TS/334/2022_5_1_1 Dated: 23-09-2022
Technical specification Providing Distribution network and FHTCs in Chalissery Panchayath Panchayath -General civil work
Contractor David Mangan (Mob: 9400592878)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 26/12/2022
Scheduled date of Completion as per agreement 25 Dec 2023
Expected date of Completion 31/07/2024

Processing Dates

TS Date 23 Sep 2022
Estimate Approval 25 Oct 2022
NIT Approval 25 Oct 2022
Tender Closing 05 Nov 2022
Technichal Pre-Qualification 05 Nov 2022
Price bid opening 07 Nov 2022

Approval Dates

Workorder Date 26 Dec 2022
NA 10 Jan 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thrissur PH Dn EE
Date: 28/06/2024

Work in progress | 95% Completed

Work is ongoing. 95% laying work completed. Road work is pending 384 FHTCs given..

Thrithala PH Sn - AE
Date: 25/06/2024

Work in progress | 95% Completed

Work is ongoing. 95% laying work completed. Road work is pending 384 FHTCs given..