Project | Jal Jeevan Mission- 2020-21- Phase I - Vadanappally Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) - 3150 FHTCs |
---|---|
Project Code | TCRJJM08205239P1 |
Type | Package |
Main Project | Jal Jeevan Mission- 2020-21- Phase I - Vadanappally Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission- 2020-21- Phase I - Vadanappally Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) - 3150 FHTCs |
Status | On-going |
District | Thrissur |
Executing Office | Vadanappalli Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 123740000 |
TS Number | TS/2020-2021/2020/21873 |
Technical specification | 3150 nos of FHTC |
Contractor | THADATHIL MOHAMMED ALI (Mob: 9447733327) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
10 Jun 2022 | Pending | Pending | Road Cut Related Risk | Application submitted to NH section for road cutting request. due to corrections they returned the applicatin with adequate directions. | No comments available. | Pending |
14 May 2021 | Pending | Pending | Road Cut Related Risk | 1) ROW/107049/10164 - Vadanappally centre to Beach road Jn. 2) ROW/107049/10165 - crossing at Vadanappally beach road Jn. 3) ROW/107049/10166 - GSM Beach road Jn. to Ganeswamangalam. 4) ROW/107049/10167 - Crossing at GSM Beach Road Jn. 5) ROW/107049/10168 - Eangels Nagar Road Jn. to Kottayi Temple Road Jn. 6) ROW/107049/10169 - Crossing at Eangels Nagar Road Jn. | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 22/10/2020 |
---|---|
Scheduled date of Completion as per agreement | 31 Mar 2021 |
Expected date of Completion | 31/03/2024 |
TS Date | 22 Oct 2020 |
---|---|
Estimate Approval | 22 Oct 2020 |
NIT Approval | 30 Oct 2020 |
Tender Closing | 23 Nov 2020 |
Technichal Pre-Qualification | 23 Nov 2020 |
Price bid opening | 23 Nov 2020 |
Workorder Date | 30 Dec 2020 |
---|---|
NA | 23 Mar 2021 |
Vadanappilly AE |
Date: 27/04/2024 |
Work has been completed | 100% Completed
1775 connections completed out of 3150 (FHTC -1360 and 415htc), 14th and Part bill submitted. 7274m DI pipe laying completed..
Vadanappilly AE |
Date: 18/04/2024 |
Work has been completed | 100% Completed
1775 connections completed out of 3150 (FHTC -1360 and 415htc), 14th and Part bill submitted. 7274m DI pipe laying completed..