Jal Jeevan Mission- 2020-21- Phase I - Vadanappally Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS)

Project Jal Jeevan Mission- 2020-21- Phase I - Vadanappally Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS)
Project Code TCRJJM08205239
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission- 2020-21- Phase I - Vadanappally Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS)
Status On-going
District Thrissur
Executing Office Vadanappalli Sn
AS Amount (Rs) 149100000
AS Number GO(Rt) No 541/2020/WRD
TS Amount (Rs) 123740000
TS Number TS/2020-2021/2020/21873
Total Bill Submitted (Rs) 30616199
Total Bill Paid (Rs) 30616199
Population Benefitted 16750
Capacity in MLD 1.00
Actual Project Completion Date Date is not specified
Coverage Vatanappilly Pt.
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission- 2020-21- Phase I - Vadanappally Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) - 3150 FHTCs Vadanappalli Sn
2 Jal Jeevan Mission (JJM) - CWSS to Nattika Firka- Additional works-Vadanappally Panchayath Phase I- Shifting house connection-Shifting house connection-General Civil Work Vadanappalli Sn
3 Jal Jeevan Mission (JJM)-CWSS to Nattika Firka-Vadanappally Panchayath-Phase 1- Additional WorkReplacement Of Inlet Pipe, M.S fabrication work at Angles Nagar. Vadanappalli Sn
4 Jal Jeevan Mission (JJM)-Jal Jeevan Mission-Vadanappally Panchayath Phase I-Additional work at Chilanka Beach Road & Atmavu Junction-Supplying and Laying 90mm PVC Pipe line Work Vadanappalli Sn
5 Jal Jeevan Mission Phase I - Vadanappally Grama Panchayath- CWSS to Nattika Firka- Providing FHTC to Rural house holds PH.Division Irinjalakkuda
6 JJM - 2020-21 - Vadanappally PANCHAYATH- Providing public tap based FHTC to Rural house holds.-PART 1 (20 Nos) Vadanappalli Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Jun 2024 1775 connections completed out of 3150 (FHTC -1360 and 415htc), 14th and Part bill submitted. 7274m DI pipe laying completed. Vadanappilly AE
12 Jun 2024 1775 connections completed out of 3150 (FHTC -1360 and 415htc), 14th and Part bill submitted. 7274m DI pipe laying completed. Vadanappilly AE
27 Apr 2024 1775 connections completed out of 3150 (FHTC -1360 and 415htc), 14th and Part bill submitted. 7274m DI pipe laying completed. Vadanappilly AE
18 Apr 2024 1775 connections completed out of 3150 (FHTC -1360 and 415htc), 14th and Part bill submitted. 7274m DI pipe laying completed. Vadanappilly AE
08 Apr 2024 1775 connections completed out of 3150 (FHTC -1360 and 415htc), 14th and Part bill submitted. 7274m DI pipe laying completed. Vadanappilly AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 21/08/2020
Scheduled date of Completion of the Project 21 Apr 2021
Expected date of Completion 31/03/2024

Processing Dates

AS Date 21 Aug 2020
TS Date 22 Oct 2020

Other details

Project Officers View