Jal Jeevan Mission- 2020-21- Phase I - Vadanappally Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS)
Project |
Jal Jeevan Mission- 2020-21- Phase I - Vadanappally Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) |
Project Code |
TCRJJM08205239 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission- 2020-21- Phase I - Vadanappally Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) |
Status |
On-going |
District |
Thrissur |
Executing Office |
Vadanappalli Sn |
AS Amount (Rs) |
149100000
|
AS Number |
GO(Rt) No 541/2020/WRD |
TS Amount (Rs) |
123740000 |
TS Number |
TS/2020-2021/2020/21873 |
Total Bill Submitted (Rs) |
30616199 |
Total Bill Paid (Rs) |
30616199 |
Population Benefitted |
16750 |
Capacity in MLD |
1.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Vatanappilly Pt. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission- 2020-21- Phase I - Vadanappally Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) - 3150 FHTCs |
Vadanappalli Sn |
|
2 |
Jal Jeevan Mission (JJM) - CWSS to Nattika Firka- Additional works-Vadanappally Panchayath Phase I- Shifting house connection-Shifting house connection-General Civil Work |
Vadanappalli Sn |
|
3 |
Jal Jeevan Mission (JJM)-CWSS to Nattika Firka-Vadanappally Panchayath-Phase 1- Additional WorkReplacement Of Inlet Pipe, M.S fabrication work at Angles Nagar. |
Vadanappalli Sn |
|
4 |
Jal Jeevan Mission (JJM)-Jal Jeevan Mission-Vadanappally Panchayath Phase I-Additional work at Chilanka Beach Road & Atmavu Junction-Supplying and Laying 90mm PVC Pipe line Work |
Vadanappalli Sn |
|
5 |
Jal Jeevan Mission Phase I - Vadanappally Grama Panchayath- CWSS to Nattika Firka- Providing FHTC to Rural house holds |
PH.Division Irinjalakkuda |
|
6 |
JJM - 2020-21 - Vadanappally PANCHAYATH- Providing public tap based FHTC to Rural house holds.-PART 1 (20 Nos) |
Vadanappalli Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Jun 2024 |
1775 connections completed out of 3150 (FHTC -1360 and 415htc), 14th and Part bill submitted. 7274m DI pipe laying completed. |
Vadanappilly AE |
|
12 Jun 2024 |
1775 connections completed out of 3150 (FHTC -1360 and 415htc), 14th and Part bill submitted. 7274m DI pipe laying completed. |
Vadanappilly AE |
|
27 Apr 2024 |
1775 connections completed out of 3150 (FHTC -1360 and 415htc), 14th and Part bill submitted. 7274m DI pipe laying completed. |
Vadanappilly AE |
|
18 Apr 2024 |
1775 connections completed out of 3150 (FHTC -1360 and 415htc), 14th and Part bill submitted. 7274m DI pipe laying completed. |
Vadanappilly AE |
|
08 Apr 2024 |
1775 connections completed out of 3150 (FHTC -1360 and 415htc), 14th and Part bill submitted. 7274m DI pipe laying completed. |
Vadanappilly AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
21/08/2020 |
Scheduled date of Completion of the Project |
21 Apr 2021 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
22 Oct 2020 |