Project | AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION - ELAYAVOOR ZONE- Pipeline work |
---|---|
Project Code | KNRAMRUT 2032314163P1 |
Type | Package |
Main Project | AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION - ELAYAVOOR ZONE- Pipeline work |
Funding Agency | AMRUT 2 |
Category | AMRUT 2 |
Type of scheme | Water Supply |
Scheme | |
Description | AMRUT-AMRUT 2.0 - SWAP-2- PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION - ELAYAVOOR ZONE- Pipeline work |
Status | On-going |
District | Kannur |
Executing Office | Kannur WS Sn 2 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 93300000 |
TS Number | WRD/KWA-CE(NA)/EST-TS/3303/2022-26-2-1 |
Technical specification | PIPE LINE EXTENSION , PROVIDING WATER CONNECTIONS IN VARIOUS ZONES OF KANNUR CORPORATION - ELAYAVOOR ZONE- Pipeline work |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 19/08/2023 |
---|---|
Scheduled date of Completion as per agreement | 18 Aug 2024 |
Expected date of Completion | 18/08/2024 |
TS Date | 10 Apr 2023 |
---|---|
Estimate Approval | 10 Apr 2023 |
NIT Approval | 10 Apr 2023 |
Tender Closing | 10 May 2023 |
Technichal Pre-Qualification | 29 May 2023 |
Price bid opening | 03 Jun 2023 |
Workorder Date | 12 Jul 2023 |
---|---|
NA | 09 Aug 2023 |
Kannur WS Sn AE 2 |
Date: 23/06/2024 |
Work in progress | 70% Completed
pipe Laid 13350m out of 19200m and FHTC 795 Nos out of 2500 Nos completed..
Kannur WS Sn AE 2 |
Date: 20/06/2024 |
Work in progress | 70% Completed
pipe Laid 13350m out of 19200m and FHTC 795 Nos out of 2500 Nos completed..