KIIFB special Investment package - WRD010-05-04-WSS to Tanur Municipality and adjoining 4 panchayaths- package 3 - Electro Mechanical Works.

Project KIIFB special Investment package - WRD010-05-04-WSS to Tanur Municipality and adjoining 4 panchayaths- package 3 - Electro Mechanical Works.
Project Code MLPKIIFB0117518P3
Type Package
Main Project KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Supply ,erection and commissioning of RW pumps ( 500 HP VT X3 nos),CW pumps CF 71 HP X 2 nos and construction of substation building, supply and erection of transformers (1250 KVA& 100KVA) in well site and WTP site(315KVA) Package cost - 39800000/ Over run by - 7 months
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 45600000
TS Number TS/2018/2019/2018/12166 dtd 2/2/2019
Technical specification Supply ,erection and commissioning of RW pumps ( 500 HP VT X3 nos),CW pumps CF 71 HP X 2 nos and construction of substation building, supply and erection of transformers (1250 KVA& 100KVA) in well site and WTP site(315KVA)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
01 Nov 2021 Pending Pending Risks From Other Projects The Project production components have been completed. Laying KSEB dedicated feeder line to RWP is arranged as deposit to KSEB. They have started work by 01-10-21 however the work is halted due to non availability of KSEB department supplied items like A-pole, ABC Cable etc. No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 21/06/2019
Scheduled date of Completion as per agreement 31 Mar 2023
Expected date of Completion 31/12/2021

Processing Dates

TS Date 02 Feb 2019
Estimate Approval 02 Feb 2019
NIT Approval 25 Mar 2019
Tender Closing 23 Apr 2019
Technichal Pre-Qualification 23 May 2019
Price bid opening 23 May 2019

Approval Dates

Workorder Date 30 May 2019
NA 21 Jun 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE5
Date: 04/05/2024

Work in progress | 98% Completed

Construction of transformer substation, 71 HP clear water pump erection, 500 HP 3 Nos raw water pump erection and installation of transformers (1250 KVA, 315 KVA and 100 KVA) got completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid RS. 1,31,747/- and RS. 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. For WTP, it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. Recently on 11/01/2023 the KSEB informed that the powerline extension work in completed. And ready to give power connection. now we start the procedure for obtaining power connection at Pump house and WTP. Which includes Re validation & permission of electrical inspecterate. .

Malappuram Project Dn AE5
Date: 03/05/2024

Work in progress | 98% Completed

Construction of transformer substation, 71 HP clear water pump erection, 500 HP 3 Nos raw water pump erection and installation of transformers (1250 KVA, 315 KVA and 100 KVA) got completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid RS. 1,31,747/- and RS. 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. For WTP, it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. Recently on 11/01/2023 the KSEB informed that the powerline extension work in completed. And ready to give power connection. now we start the procedure for obtaining power connection at Pump house and WTP. Which includes Re validation & permission of electrical inspecterate. .