Project | KIIFB special Investment package - WRD010-05-04-WSS to Tanur Municipality and adjoining 4 panchayaths- package 3 - Electro Mechanical Works. |
---|---|
Project Code | MLPKIIFB0117518P3 |
Type | Package |
Main Project | KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Supply ,erection and commissioning of RW pumps ( 500 HP VT X3 nos),CW pumps CF 71 HP X 2 nos and construction of substation building, supply and erection of transformers (1250 KVA& 100KVA) in well site and WTP site(315KVA) Package cost - 39800000/ Over run by - 7 months |
Status | On-going |
District | Malappuram |
Executing Office | Malappuram Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 45600000 |
TS Number | TS/2018/2019/2018/12166 dtd 2/2/2019 |
Technical specification | Supply ,erection and commissioning of RW pumps ( 500 HP VT X3 nos),CW pumps CF 71 HP X 2 nos and construction of substation building, supply and erection of transformers (1250 KVA& 100KVA) in well site and WTP site(315KVA) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
01 Nov 2021 | Pending | Pending | Risks From Other Projects | The Project production components have been completed. Laying KSEB dedicated feeder line to RWP is arranged as deposit to KSEB. They have started work by 01-10-21 however the work is halted due to non availability of KSEB department supplied items like A-pole, ABC Cable etc. | No comments available. | Pending |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 21/06/2019 |
---|---|
Scheduled date of Completion as per agreement | 31 Mar 2023 |
Expected date of Completion | 31/12/2021 |
TS Date | 02 Feb 2019 |
---|---|
Estimate Approval | 02 Feb 2019 |
NIT Approval | 25 Mar 2019 |
Tender Closing | 23 Apr 2019 |
Technichal Pre-Qualification | 23 May 2019 |
Price bid opening | 23 May 2019 |
Workorder Date | 30 May 2019 |
---|---|
NA | 21 Jun 2019 |
Malappuram Project Dn AE5 |
Date: 04/05/2024 |
Work in progress | 98% Completed
Construction of transformer substation, 71 HP clear water pump erection, 500 HP 3 Nos raw water pump erection and installation of transformers (1250 KVA, 315 KVA and 100 KVA) got completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid RS. 1,31,747/- and RS. 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. For WTP, it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. Recently on 11/01/2023 the KSEB informed that the powerline extension work in completed. And ready to give power connection. now we start the procedure for obtaining power connection at Pump house and WTP. Which includes Re validation & permission of electrical inspecterate. .
Malappuram Project Dn AE5 |
Date: 03/05/2024 |
Work in progress | 98% Completed
Construction of transformer substation, 71 HP clear water pump erection, 500 HP 3 Nos raw water pump erection and installation of transformers (1250 KVA, 315 KVA and 100 KVA) got completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid RS. 1,31,747/- and RS. 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. For WTP, it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. Recently on 11/01/2023 the KSEB informed that the powerline extension work in completed. And ready to give power connection. now we start the procedure for obtaining power connection at Pump house and WTP. Which includes Re validation & permission of electrical inspecterate. .