Project | JJM Providing WSS to Areekode Panchayath - Laying distribution network ,Changing of Damaged Clarifier bridge ,Fitting new gear box and out let pipe line for Alum Lime tank at Treatment plant. |
---|---|
Project Code | MLPJJM022212567P1 |
Type | Package |
Main Project | Sub:- JJM Providing WSS to Areekode Panchayath - Laying distribution Network, Changing of Damaged Clarifier bridge ,Fitting new gear box and out let pipe line for Alum Lime tank at treatment plant-reg- |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Laying distribution line : 63 PVC - 2500mtr, 75PVC -2000mtr,90 PVC-2000mtr,110 PVC - 1500mtr,140PVC -500mtr, 50 GI - 1700mtr Changing of damaged clarifire bridge, Centre bush to new thrust bearing set in WTP,Treatment plant - Fitting new gear box and out let pipe line,Providing FHTCs - 200Noss |
Status | On-going |
District | Malappuram |
Executing Office | Areecode PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 16900000 |
TS Number | Reg .No. 10167/2022-2023 |
Technical specification | Changing of damaged clarifire bridge, Centre bush to new thrust bearing set in WTP,Treatment plant - Fitting new gear box and out let pipe line |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 23/10/2022 |
---|---|
Scheduled date of Completion as per agreement | 22 Apr 2023 |
Expected date of Completion | 22/04/2023 |
TS Date | 14 Jul 2022 |
---|---|
Estimate Approval | 14 Jul 2022 |
NIT Approval | 14 Jul 2022 |
Tender Closing | 05 Aug 2022 |
Technichal Pre-Qualification | 26 Jul 2022 |
Price bid opening | 26 Jul 2022 |
Workorder Date | 17 Aug 2022 |
---|---|
NA | 06 Sep 2022 |
Areacode AE |
Date: 29/06/2024 |
Work in progress | 90% Completed
FHTC -88 nos Completed, Pipe line work in progress..
Areacode AE |
Date: 20/06/2024 |
Work in progress | 89% Completed
FHTC -88 nos Completed, Pipe line work in progress..