Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District Package 1

Project Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District Package 1
Project Code MLPKIIFB1118510P2
Type Package
Main Project Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Construction and commissioning of intake well cum pump house 10 m dia, 3 raw water pumps 140 HP 2 clear water pumps 24 HP each Pumping main 2750 m 600 mm dia DI K9 pipes 23 MLD plant 12 LL OHSR Clear water transmission 450mm DI K9 pipe of length 8600m 35.77 crore rupees package cost labour:material - 2:5 Executing officer: EE,Proj. div ,Malappuram
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 357700000
TS Number TS/2019-2020/2019/20223 Dated: 12-12-2019
Technical specification Construction and commissioning of intake well cum pump house 10 m dia, 3 raw water pumps 140 HP 2 clear water pumps 24 HP each Pumping main 2750 m 600 mm dia DI K9 pipes 23 MLD plant 12 LL OHSR Clear water transmission 450mm DI K9 pipe of length 8600m
Contractor SHAHUL HAMEED V (Mob: 9544144836)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 17/03/2020
Scheduled date of Completion as per agreement 29 Feb 2024
Expected date of Completion 29/02/2024

Processing Dates

TS Date 12 Dec 2019
Estimate Approval 12 Dec 2019
NIT Approval 21 Dec 2019
Tender Closing 13 Jan 2020
Technichal Pre-Qualification 28 Jan 2020
Price bid opening 29 Jan 2020

Approval Dates

Workorder Date 07 Mar 2020
NA 16 Mar 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE3
Date: 03/05/2024

Work in progress | 93% Completed

Raw water pumphouse, Raw water pumping main, and Booster station are in Finishing stage. 23 MLD WTP, 12 LL OHSR, All gravity and pumping mains are completed. Leading Channel Work in Progress. .

Malappuram Project Dn AE3
Date: 02/05/2024

Work in progress | 93% Completed

Raw water pumphouse, Raw water pumping main, and Booster station are in Finishing stage. 23 MLD WTP, 12 LL OHSR, All gravity and pumping mains are completed. Leading Channel Work in Progress. .