| Project | Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District Package 1 |
|---|---|
| Project Code | MLPKIIFB1118510P2 |
| Type | Package |
| Main Project | Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District |
| Funding Agency | KIIFB |
| Category | KIIFB |
| Type of scheme | Water Supply |
| Scheme | KIIFB |
| Description | Construction and commissioning of intake well cum pump house 10 m dia, 3 raw water pumps 140 HP 2 clear water pumps 24 HP each Pumping main 2750 m 600 mm dia DI K9 pipes 23 MLD plant 12 LL OHSR Clear water transmission 450mm DI K9 pipe of length 8600m 35.77 crore rupees package cost labour:material - 2:5 Executing officer: EE,Proj. div ,Malappuram |
| Status | On-going |
| District | Malappuram |
| Executing Office | Malappuram Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 357700000 |
| TS Number | TS/2019-2020/2019/20223 Dated: 12-12-2019 |
| Technical specification | Construction and commissioning of intake well cum pump house 10 m dia, 3 raw water pumps 140 HP 2 clear water pumps 24 HP each Pumping main 2750 m 600 mm dia DI K9 pipes 23 MLD plant 12 LL OHSR Clear water transmission 450mm DI K9 pipe of length 8600m |
| Contractor | SHAHUL HAMEED V (Mob: 9544144836) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 17/03/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 29 Feb 2024 |
| Expected date of Completion | 29/02/2024 |
| TS Date | 12 Dec 2019 |
|---|---|
| Estimate Approval | 12 Dec 2019 |
| NIT Approval | 21 Dec 2019 |
| Tender Closing | 13 Jan 2020 |
| Technichal Pre-Qualification | 28 Jan 2020 |
| Price bid opening | 29 Jan 2020 |
| Workorder Date | 07 Mar 2020 |
|---|---|
| NA | 16 Mar 2020 |
| Malappuram Project Dn EE |
| Date: 16/01/2026 |
Work has been completed | 100% Completed
Work Completed. Final bill Submitted.
| Malappuram Project Dn AE3 |
| Date: 22/12/2025 |
Work has been completed | 100% Completed
Work Completed. Final bill Submitted.