Project | Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District Package 1 |
---|---|
Project Code | MLPKIIFB1118510P2 |
Type | Package |
Main Project | Budget -2017-2018-KIIFB project-TRAN10:WRD 025-13-WSS to Ramanchadi- Aligarh in Malappuram District |
Funding Agency | KIIFB |
Category | KIIFB |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Construction and commissioning of intake well cum pump house 10 m dia, 3 raw water pumps 140 HP 2 clear water pumps 24 HP each Pumping main 2750 m 600 mm dia DI K9 pipes 23 MLD plant 12 LL OHSR Clear water transmission 450mm DI K9 pipe of length 8600m 35.77 crore rupees package cost labour:material - 2:5 Executing officer: EE,Proj. div ,Malappuram |
Status | On-going |
District | Malappuram |
Executing Office | Malappuram Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 357700000 |
TS Number | TS/2019-2020/2019/20223 Dated: 12-12-2019 |
Technical specification | Construction and commissioning of intake well cum pump house 10 m dia, 3 raw water pumps 140 HP 2 clear water pumps 24 HP each Pumping main 2750 m 600 mm dia DI K9 pipes 23 MLD plant 12 LL OHSR Clear water transmission 450mm DI K9 pipe of length 8600m |
Contractor | SHAHUL HAMEED V (Mob: 9544144836) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 17/03/2020 |
---|---|
Scheduled date of Completion as per agreement | 29 Feb 2024 |
Expected date of Completion | 29/02/2024 |
TS Date | 12 Dec 2019 |
---|---|
Estimate Approval | 12 Dec 2019 |
NIT Approval | 21 Dec 2019 |
Tender Closing | 13 Jan 2020 |
Technichal Pre-Qualification | 28 Jan 2020 |
Price bid opening | 29 Jan 2020 |
Workorder Date | 07 Mar 2020 |
---|---|
NA | 16 Mar 2020 |
Malappuram Project Dn AE3 |
Date: 03/05/2024 |
Work in progress | 93% Completed
Raw water pumphouse, Raw water pumping main, and Booster station are in Finishing stage. 23 MLD WTP, 12 LL OHSR, All gravity and pumping mains are completed. Leading Channel Work in Progress. .
Malappuram Project Dn AE3 |
Date: 02/05/2024 |
Work in progress | 93% Completed
Raw water pumphouse, Raw water pumping main, and Booster station are in Finishing stage. 23 MLD WTP, 12 LL OHSR, All gravity and pumping mains are completed. Leading Channel Work in Progress. .