Jal Jeevan Mission (JJM)-al Jeevan Mission - CWSS to Ottasekharamangalam - Water supply line extension & providing water connections from existing and proposed pipelines to households of Ottasekharamangalam Grama Panchayath. (Phase-2)-Design Supply erection and trail running of booster pumps and design, Construction of 0.25 LL Capacity OHSR at Anakuzhi colony. -General Civil Work
Project |
Jal Jeevan Mission (JJM)-al Jeevan Mission - CWSS to Ottasekharamangalam - Water supply line extension & providing water connections from existing and proposed pipelines to households of Ottasekharamangalam Grama Panchayath. (Phase-2)-Design Supply erection and trail running of booster pumps and design, Construction of 0.25 LL Capacity OHSR at Anakuzhi colony. -General Civil Work |
Project Code |
TVMJJM08204599P4 |
Type |
Package |
Main Project |
JJM-2020-2021 Ottasekharamangalam Grama Panchayath - Providing Functional Household Tap Connections (Phase I & II - 4629 FHTCs)
|
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission
(JJM)-al Jeevan Mission - CWSS to Ottasekharamangalam - Water supply line extension & providing
water connections from existing and proposed pipelines to households of Ottasekharamangalam Grama
Panchayath. (Phase-2)-Design Supply erection and trail running of booster pumps and design, Construction of
0.25 LL Capacity OHSR at Anakuzhi colony. -General Civil Work |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Kattakada WS Sn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
4340608 |
TS Number |
WRD/KWA-CE(SR)/TR/16001/2023_5_8_7/1 |
Technical specification |
|
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
26/12/2022 |
Scheduled date of Completion as per agreement |
30 Mar 2024 |
Expected date of Completion |
31/12/2022 |
Processing Dates
TS Date |
28 Nov 2023 |
Estimate Approval |
01 Nov 2023 |
NIT Approval |
06 Nov 2023 |
Tender Closing |
31 Oct 2023 |
Technichal Pre-Qualification |
31 Oct 2023 |
Price bid opening |
20 Nov 2024 |
Approval Dates
Workorder Date |
29 Mar 2023 |
NA |
20 Mar 2023 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Neyyattinkara WS Dn EE |
Date: 26/06/2024 |
Work in progress | 40% Completed
on going.
Neyyattinkara WS Dn EE |
Date: 22/06/2024 |
Work in progress | 40% Completed
Work in progress.