- Home
- JJM-2020-2021 Ottasekharamangalam Grama...
JJM-2020-2021 Ottasekharamangalam Grama Panchayath - Providing Functional Household Tap Connections (Phase I & II - 4629 FHTCs)
Project |
JJM-2020-2021 Ottasekharamangalam Grama Panchayath - Providing Functional Household Tap Connections (Phase I & II - 4629 FHTCs) |
Project Code |
TVMJJM08204599 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM-2020-2021 Ottasekharamangalam Grama Panchayath - Providing Functional Household Tap Connections (Phase I & II - 4629 FHTCs) |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Neyyattinkara WS Dn |
AS Amount (Rs) |
170521000
|
AS Number |
GO(RT No 541/2020 dtd 21/82020 |
TS Amount (Rs) |
1601500000 |
TS Number |
6423/2020-21 dtd 26/8/2020 |
Total Bill Submitted (Rs) |
1922182 |
Total Bill Paid (Rs) |
1809182 |
Population Benefitted |
10000 |
Capacity in MLD |
0.06 |
Actual Project Completion Date |
01 Mar 2024 |
Coverage |
JJM-2020-2021 Ottasekharamangalam Grama Panchayath - Providing Functional Household Tap Connections (Phase I & II - 4629 FHTCs) |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
E Jal Jeevan Mission (JJM)-Jal Jeevan Mission-2020-21-Ottasekharamangalam Panchayatah - Water supply line extension and providing FHTC of Ottasekharamangalam Panchayatah-Panchayatah road restoration of Tar and Concrete works.-General Civil Work-Nil |
Kattakada WS Sn |
|
2 |
Jal Jeevan Mission - CWSS to Kalippara - Water supply line extension & providing water connections from existing and proposed pipelines to households of Ottasekharamangalam Grama Panchayath under Kattakkada WS Section (Phase II - 4429 FHTCs) |
Kattakada WS Sn |
|
3 |
Jal Jeevan Mission (JJM)-al Jeevan Mission - CWSS to Ottasekharamangalam - Water supply line extension & providing water connections from existing and proposed pipelines to households of Ottasekharamangalam Grama Panchayath. (Phase-2)-Design Supply erection and trail running of booster pumps and design, Construction of 0.25 LL Capacity OHSR at Anakuzhi colony. -General Civil Work |
Kattakada WS Sn |
|
4 |
Jal Jeevan Mission - Topographical Survey at Ottasekharamangalam Grama Panchayath in Trivandrum District. |
Kattakada WS Sn |
|
5 |
JJM-2020-2021 Ottasekharamangalam Grama Panchayath - Providing Functional Household Tap Connections (Phase I - 200 FHTCs) |
Kattakada WS Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
26 Jun 2024 |
on going |
Neyyattinkara WS Dn EE |
|
22 Jun 2024 |
on going |
Neyyattinkara WS Dn EE |
|
13 Jun 2024 |
on going |
Neyyattinkara WS Dn EE |
|
10 Jun 2024 |
on going |
Neyyattinkara WS Dn EE |
|
04 Jun 2024 |
on going |
Neyyattinkara WS Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
28/09/2020 |
Scheduled date of Completion of the Project |
31 Dec 2022 |
Expected date of Completion |
31/12/2022 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
26 Aug 2020 |