| Project | Sewage treatment plant Kureeppuzha(8569) |
|---|---|
| Project Code | KLMGOI0918482P1 |
| Type | Package |
| Main Project | 22 AMRUT ATAL MISSION FOR REJUVENATION AND URBAN TRA(75)-Sewage treatment plant Kureeppuzha(8569) & 50 KLD FSTP |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-Amrut 2015-17-Design, Supply,Construction,Erection,Testing and Commissioning of 12 MLD capacity Sewage Treatment Plant (STP) based on Moving Bed Bio Reactor( MBBR) Technology with provision for septage handling for co-treatment with sewage and Recycling System for the treated Water including Operation & Maintenance for 10 years at Kureepuzha in Kollam corporation |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 295600000 |
| TS Number | ORDER No. TS/2018-2019/2018/9433 Dated: 13-09-2018 |
| Technical specification | Supply,Construction,Erection,Testing and Commissioning of 12 MLD capacity Sewage Treatment Plant (STP) based on Moving Bed Bio Reactor( MBBR) Technology with provision for septage handling for co-treatment with sewage and Recycling System for the treated Water including Operation & Maintenance for 10 years at Kureepuzha in Kollam corporation |
| Contractor | M/s.ABM JV HYDROTECH PARYAVARAN INDIA PVT. LTD (Mob: 8129100459) |
| Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
|---|---|---|---|---|---|---|
| 01 Aug 2022 | Pending | Pending | Natural Calamities Related | Heavy rain delayed the concrete work | back to normal | Action Taken |
| 08 Nov 2021 | 08 Nov 2021 | 08 Nov 2021 | Approval/Permissions Related (from other departments excluding road cut permission and land related) | CRZ Clearance | As per the meeting date 8.11.2021..The CRZ clearance was issued by KCZMA on 28.04.2012. The CRZ clearance issued will remain valid for a period of 7 years, as per 4.2 (i) h (V) of CRZ notification, and it can be extended by a maximum of three years. The validity of CRZ Clearance will expire on 28.04.2022. | Solved |
| 01 Oct 2021 | 29 Nov 2021 | Pending | Natural Calamities Related | heavy rain -delayed the work | Condition is favaourable | Solved |
| 12 Aug 2021 | Pending | 12 Aug 2021 | Land Related Risk | 2.03 acres of land ( undisputed) handed over to KWA by Corporation Kollam and remaining portion of land to be handed over by the Kollam Corporation. | No comments added. | Action Taken |
| 06 Aug 2021 | 08 Nov 2021 | Pending | Approval/Permissions Related (from other departments excluding road cut permission and land related) | CRZ clearance approval extension from 2019 requested and clearance pending from KCZMA | As per the meeting date 8.11.2021..The CRZ clearance was issued by KCZMA on 28.04.2012. The CRZ clearance issued will remain valid for a period of 7 years, as per 4.2 (i) h (V) of CRZ notification, and it can be extended by a maximum of three years. The validity of CRZ Clearance will expire on 28.04.2022. | Solved |
| 04 Nov 2020 | Pending | 12 Aug 2021 | Land Related Risk | Due to public protest, land survey works was done on 4.11.2020 with police protection. As per the survey conducted on that day , boundary wall works was stopped by the public and identified about 2.03 acres is available out of 2.83 cents | No comments added. | Action Taken |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 04/11/2020 |
|---|---|
| Scheduled date of Completion as per agreement | 30 Sep 2022 |
| Expected date of Completion | 31/12/2024 |
| TS Date | 13 Sep 2018 |
|---|---|
| Estimate Approval | 13 Sep 2018 |
| NIT Approval | 14 Jan 2019 |
| Tender Closing | 08 Feb 2019 |
| Technichal Pre-Qualification | 13 Feb 2019 |
| Price bid opening | 15 Feb 2019 |
| Workorder Date | 27 Apr 2020 |
|---|---|
| NA | 28 Oct 2020 |
| Kollam Project Dn EE |
| Date: 28/10/2026 |