Sewage treatment plant Kureeppuzha(8569)

Project Sewage treatment plant Kureeppuzha(8569)
Project Code KLMGOI0918482P1
Type Package
Main Project 22 AMRUT ATAL MISSION FOR REJUVENATION AND URBAN TRA(75)-Sewage treatment plant Kureeppuzha(8569) & 50 KLD FSTP
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-Amrut 2015-17-Design, Supply,Construction,Erection,Testing and Commissioning of 12 MLD capacity Sewage Treatment Plant (STP) based on Moving Bed Bio Reactor( MBBR) Technology with provision for septage handling for co-treatment with sewage and Recycling System for the treated Water including Operation & Maintenance for 10 years at Kureepuzha in Kollam corporation
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 295600000
TS Number ORDER No. TS/2018-2019/2018/9433 Dated: 13-09-2018
Technical specification Supply,Construction,Erection,Testing and Commissioning of 12 MLD capacity Sewage Treatment Plant (STP) based on Moving Bed Bio Reactor( MBBR) Technology with provision for septage handling for co-treatment with sewage and Recycling System for the treated Water including Operation & Maintenance for 10 years at Kureepuzha in Kollam corporation
Contractor M/s.ABM JV HYDROTECH PARYAVARAN INDIA PVT. LTD (Mob: 8129100459)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
01 Aug 2022 Pending Pending Natural Calamities Related Heavy rain delayed the concrete work back to normal Action Taken
08 Nov 2021 08 Nov 2021 08 Nov 2021 Approval/Permissions Related (from other departments excluding road cut permission and land related) CRZ Clearance As per the meeting date 8.11.2021..The CRZ clearance was issued by KCZMA on 28.04.2012. The CRZ clearance issued will remain valid for a period of 7 years, as per 4.2 (i) h (V) of CRZ notification, and it can be extended by a maximum of three years. The validity of CRZ Clearance will expire on 28.04.2022. Solved
01 Oct 2021 29 Nov 2021 Pending Natural Calamities Related heavy rain -delayed the work Condition is favaourable Solved
12 Aug 2021 Pending 12 Aug 2021 Land Related Risk 2.03 acres of land ( undisputed) handed over to KWA by Corporation Kollam and remaining portion of land to be handed over by the Kollam Corporation. No comments added. Action Taken
06 Aug 2021 08 Nov 2021 Pending Approval/Permissions Related (from other departments excluding road cut permission and land related) CRZ clearance approval extension from 2019 requested and clearance pending from KCZMA As per the meeting date 8.11.2021..The CRZ clearance was issued by KCZMA on 28.04.2012. The CRZ clearance issued will remain valid for a period of 7 years, as per 4.2 (i) h (V) of CRZ notification, and it can be extended by a maximum of three years. The validity of CRZ Clearance will expire on 28.04.2022. Solved
04 Nov 2020 Pending 12 Aug 2021 Land Related Risk Due to public protest, land survey works was done on 4.11.2020 with police protection. As per the survey conducted on that day , boundary wall works was stopped by the public and identified about 2.03 acres is available out of 2.83 cents No comments added. Action Taken

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 04/11/2020
Scheduled date of Completion as per agreement 30 Sep 2022
Expected date of Completion 31/12/2024

Processing Dates

TS Date 13 Sep 2018
Estimate Approval 13 Sep 2018
NIT Approval 14 Jan 2019
Tender Closing 08 Feb 2019
Technichal Pre-Qualification 13 Feb 2019
Price bid opening 15 Feb 2019

Approval Dates

Workorder Date 27 Apr 2020
NA 28 Oct 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project Dn EE
Date: 28/10/2026

Work in progress | 98% Completed

Aerator tile work in progress , .

Attached images

img

Kollam Project Dn EE
Date: 27/10/2026

Work in progress | 98% Completed

Aerator tile work in progress.

Attached images

img