Package III - Construction of a check dam of height 1.80m across Periyar River at Thonithady

Project Package III - Construction of a check dam of height 1.80m across Periyar River at Thonithady
Project Code IDKKIIFB1118653P3
Type Package
Main Project KIIFB Project: TRAN 10: WRD025-06 - WSS to Ayyappankovil Panchayat in Idukki District
Funding Agency KIIFB
Category KIIFB WATER SUPPLY SCHEME
Type of scheme Water Supply
Scheme KIIFB
Description Construction of a check dam of height 1.80m across Periyar River at Thonithady
Status On-going
District Idukki
Executing Office Kattappana Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 34200000
TS Number TS/2021-2022/2020-16607
Technical specification Construction of a check dam of height 1.80m across Periyar River at Thonithady
Contractor Muhammed Safvan.M.K (Mob: 9847332300)

Project Review

See All Review messages
Review Date Review Message Review Attended By
29 Jul 2021 Estimate still under scrutiny at CECR for TS

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/03/2022
Scheduled date of Completion as per agreement 20 Dec 2022
Expected date of Completion 31/10/2023

Processing Dates

TS Date 28 Sep 2021
Estimate Approval 28 Sep 2021
NIT Approval 02 Feb 2022
Tender Closing 15 Feb 2022
Technichal Pre-Qualification 26 Feb 2022
Price bid opening 28 Feb 2022

Approval Dates

Workorder Date 21 Mar 2022
NA 11 Apr 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kattappana AEE 1
Date: 04/05/2024

Work in progress | 3% Completed

KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Agreement pending from dam safety due to further clarification regarding the NOC since the work is under KIIFB, but NOC is under JJM. A letter has been sent to the contractor to restart the work at Thonithady. Time extension has given upto 5.6.2024. The work will start once the weather become favourable for weir construction..

Kattappana AEE 1
Date: 03/05/2024

Work in progress | 3% Completed

KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Agreement pending from dam safety due to further clarification regarding the NOC since the work is under KIIFB, but NOC is under JJM. A letter has been sent to the contractor to restart the work at Thonithady. Time extension has given upto 5.6.2024. The work will start once the weather become favourable for weir construction..