Project | Package III - Construction of a check dam of height 1.80m across Periyar River at Thonithady |
---|---|
Project Code | IDKKIIFB1118653P3 |
Type | Package |
Main Project | KIIFB Project: TRAN 10: WRD025-06 - WSS to Ayyappankovil Panchayat in Idukki District |
Funding Agency | KIIFB |
Category | KIIFB WATER SUPPLY SCHEME |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Construction of a check dam of height 1.80m across Periyar River at Thonithady |
Status | On-going |
District | Idukki |
Executing Office | Kattappana Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 34200000 |
TS Number | TS/2021-2022/2020-16607 |
Technical specification | Construction of a check dam of height 1.80m across Periyar River at Thonithady |
Contractor | Muhammed Safvan.M.K (Mob: 9847332300) |
Review Date | Review Message | Review Attended By |
---|---|---|
29 Jul 2021 | Estimate still under scrutiny at CECR for TS |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 22/03/2022 |
---|---|
Scheduled date of Completion as per agreement | 20 Dec 2022 |
Expected date of Completion | 31/10/2023 |
TS Date | 28 Sep 2021 |
---|---|
Estimate Approval | 28 Sep 2021 |
NIT Approval | 02 Feb 2022 |
Tender Closing | 15 Feb 2022 |
Technichal Pre-Qualification | 26 Feb 2022 |
Price bid opening | 28 Feb 2022 |
Workorder Date | 21 Mar 2022 |
---|---|
NA | 11 Apr 2022 |
Kattappana AEE 1 |
Date: 04/05/2024 |
Work in progress | 3% Completed
KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Agreement pending from dam safety due to further clarification regarding the NOC since the work is under KIIFB, but NOC is under JJM. A letter has been sent to the contractor to restart the work at Thonithady. Time extension has given upto 5.6.2024. The work will start once the weather become favourable for weir construction..
Kattappana AEE 1 |
Date: 03/05/2024 |
Work in progress | 3% Completed
KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Agreement pending from dam safety due to further clarification regarding the NOC since the work is under KIIFB, but NOC is under JJM. A letter has been sent to the contractor to restart the work at Thonithady. Time extension has given upto 5.6.2024. The work will start once the weather become favourable for weir construction..