Project | KIIFB Project: TRAN 10: WRD025-06 - WSS to Ayyappankovil Panchayat in Idukki District |
---|---|
Project Code | IDKKIIFB1118653 |
Type | Main project |
Funding Agency | KIIFB |
Category | KIIFB WATER SUPPLY SCHEME |
Type of scheme | Water Supply |
Scheme | KIIFB |
Description | Completion of the poject 'ARP/NRDWP- WSS to Kattappana and Ayyappankovil villages'- Supplying, laying and commissioning 350mm, 300mm& 250mm DI pumping/ gravity main and 80mm GI pumping main, improvement work of Kalthotty sump& pump house, construction of pipe line bridge, design and construction of 1.00LL capacity sump& pump house at Nariyanpara, providing wash water disposal pipe line at WTP Alady and interconnection works etc. Design and construction of electrical control rooms at raw water pump house and treatment plant compound, supply, erection and commissioning of transformers and allied works (1) 500KVA at Thonithady raw water pump house,(2)400 KVA at WTP compound, supply erection and commissioning of motor pump sets at RWPH, treatment plant sump pump house, Kalthotty pump house and Nariyanpara intermediate P H etc. Construction of a check dam across Periyar river at Thonithady |
Status | On-going |
District | Idukki |
Executing Office | Kattappana Project Dn |
AS Amount (Rs) | 464240000 |
AS Number | WRD025-06-PA-01-Dt.13-11-2018 |
TS Amount (Rs) | 165180000 |
TS Number | TS/2020-2021/2018/13980 Dated: 04-01-2021,. TS/2020-2021/2018/13138 Dated: 08-12-2020 |
Total Bill Submitted (Rs) | 0 |
Total Bill Paid (Rs) | 0 |
Population Benefitted | 112000 |
Capacity in MLD | 7.00 |
Actual Project Completion Date | Date is not specified |
Coverage | Ayyappankovil Panchayat, Kanchiyar Panchayat and Kattappana municipality |
Implementation Schedule | Download |
Work Plan | Download |
No. | Project Name | Location | View |
---|---|---|---|
1 | Package III - Construction of a check dam of height 1.80m across Periyar River at Thonithady | Project Division Kattapana | |
2 | Package-I&II- Supplying, laying and commissioning 350mm, 300mm& 250mm DI pumping/ gravity main and 80mm GI pumping main, improvement work of Kalthotty sump& pump house, construction of pipe line bridge, design and construction of 1.00LL capacity sump& pump house at Nariyanpara, providing wash water disposal pipe line at WTP Alady and interconnection works etc. Design and construction of electrical control rooms at raw water pump house and treatment plant compound, supply, erection and commissioning of transformers and allied works (1) 500KVA at Thonithady raw water pump house,(2)400 KVA at WTP compound, supply erection and commissioning of motor pump sets at RWPH, treatment plant sump pump house, Kalthotty pump house and Nariyanpara intermediate P H etc. | Project Division Kattapana |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Apr 2024 | Package I and II- arranged under JJM. KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Package III- Agreement pending from dam safety due to further clarification regarding the NOC since the work is under KIIFB, but NOC is under JJM. A letter has been sent to the contractor to restart the work at Thonithady. Time extension has given upto 5.6.2024. The work will start once the weather become favourable for weir construction. | Kattappana AEE 1 | |
23 Apr 2024 | Package I and II were shifted to JJM. Package III- KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Even though NOC issued KSEB has not given approval for draft agreement. Police case withdrawal from KSEB side is also pending. | Kattappana AEE 1 | |
20 Apr 2024 | Package I and II were shifted to JJM. Package III- KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Even though NOC issued KSEB has not given approval for draft agreement. Police case withdrawal from KSEB side is also pending. | Kattappana AEE 1 | |
17 Apr 2024 | Package I and II were shifted to JJM. Package III- KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Even though NOC issued KSEB has not given approval for draft agreement. Police case withdrawal from KSEB side is also pending. | Kattappana AEE 1 | |
14 Apr 2024 | Package I and II were shifted to JJM. Package III- KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Even though NOC issued KSEB has not given approval for draft agreement. Police case withdrawal from KSEB side is also pending. | Kattappana AEE 1 |
Review Date | Review Message | Review Attended By |
---|---|---|
29 Jul 2021 | Only a single offer received till 4 pm on 28-07-2021, the last date for submitting offers. Hence proceeding to cancel the above tender and put to re-tender, as single tender not acceptable in the first call |
Date of start of Project | 13/11/2018 |
---|---|
Scheduled date of Completion of the Project | 31 Dec 2022 |
Expected date of Completion | 31/10/2023 |
AS Date | 13 Nov 2018 |
---|---|
TS Date | 08 Dec 2020 |
Project Officers | View |
---|