KIIFB Project: TRAN 10: WRD025-06 - WSS to Ayyappankovil Panchayat in Idukki District

Project KIIFB Project: TRAN 10: WRD025-06 - WSS to Ayyappankovil Panchayat in Idukki District
Project Code IDKKIIFB1118653
Type Main project
Funding Agency KIIFB
Category KIIFB WATER SUPPLY SCHEME
Type of scheme Water Supply
Scheme KIIFB
Description Completion of the poject 'ARP/NRDWP- WSS to Kattappana and Ayyappankovil villages'- Supplying, laying and commissioning 350mm, 300mm& 250mm DI pumping/ gravity main and 80mm GI pumping main, improvement work of Kalthotty sump& pump house, construction of pipe line bridge, design and construction of 1.00LL capacity sump& pump house at Nariyanpara, providing wash water disposal pipe line at WTP Alady and interconnection works etc. Design and construction of electrical control rooms at raw water pump house and treatment plant compound, supply, erection and commissioning of transformers and allied works (1) 500KVA at Thonithady raw water pump house,(2)400 KVA at WTP compound, supply erection and commissioning of motor pump sets at RWPH, treatment plant sump pump house, Kalthotty pump house and Nariyanpara intermediate P H etc. Construction of a check dam across Periyar river at Thonithady
Status On-going
District Idukki
Executing Office Kattappana Project Dn
AS Amount (Rs) 464240000
AS Number WRD025-06-PA-01-Dt.13-11-2018
TS Amount (Rs) 165180000
TS Number TS/2020-2021/2018/13980 Dated: 04-01-2021,. TS/2020-2021/2018/13138 Dated: 08-12-2020
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 112000
Capacity in MLD 7.00
Actual Project Completion Date Date is not specified
Coverage Ayyappankovil Panchayat, Kanchiyar Panchayat and Kattappana municipality
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Package III - Construction of a check dam of height 1.80m across Periyar River at Thonithady Project Division Kattapana
2 Package-I&II- Supplying, laying and commissioning 350mm, 300mm& 250mm DI pumping/ gravity main and 80mm GI pumping main, improvement work of Kalthotty sump& pump house, construction of pipe line bridge, design and construction of 1.00LL capacity sump& pump house at Nariyanpara, providing wash water disposal pipe line at WTP Alady and interconnection works etc. Design and construction of electrical control rooms at raw water pump house and treatment plant compound, supply, erection and commissioning of transformers and allied works (1) 500KVA at Thonithady raw water pump house,(2)400 KVA at WTP compound, supply erection and commissioning of motor pump sets at RWPH, treatment plant sump pump house, Kalthotty pump house and Nariyanpara intermediate P H etc. Project Division Kattapana

Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Apr 2024 Package I and II- arranged under JJM. KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Package III- Agreement pending from dam safety due to further clarification regarding the NOC since the work is under KIIFB, but NOC is under JJM. A letter has been sent to the contractor to restart the work at Thonithady. Time extension has given upto 5.6.2024. The work will start once the weather become favourable for weir construction. Kattappana AEE 1
23 Apr 2024 Package I and II were shifted to JJM. Package III- KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Even though NOC issued KSEB has not given approval for draft agreement. Police case withdrawal from KSEB side is also pending. Kattappana AEE 1
20 Apr 2024 Package I and II were shifted to JJM. Package III- KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Even though NOC issued KSEB has not given approval for draft agreement. Police case withdrawal from KSEB side is also pending. Kattappana AEE 1
17 Apr 2024 Package I and II were shifted to JJM. Package III- KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Even though NOC issued KSEB has not given approval for draft agreement. Police case withdrawal from KSEB side is also pending. Kattappana AEE 1
14 Apr 2024 Package I and II were shifted to JJM. Package III- KSEB gave NOC/ permissive sanction for construction of weir in July 2023. Even though NOC issued KSEB has not given approval for draft agreement. Police case withdrawal from KSEB side is also pending. Kattappana AEE 1

Project Review

See All Review messages
Review Date Review Message Review Attended By
29 Jul 2021 Only a single offer received till 4 pm on 28-07-2021, the last date for submitting offers. Hence proceeding to cancel the above tender and put to re-tender, as single tender not acceptable in the first call

Duration & Sanction dates

Date of start of Project 13/11/2018
Scheduled date of Completion of the Project 31 Dec 2022
Expected date of Completion 31/10/2023

Processing Dates

AS Date 13 Nov 2018
TS Date 08 Dec 2020

Other details

Project Officers View