JJM 2021-22 - Setting up/ Upgradation/ Operation of Laboratories - Setting up of new Sub District Laboratory at Adimali

Project JJM 2021-22 - Setting up/ Upgradation/ Operation of Laboratories - Setting up of new Sub District Laboratory at Adimali
Project Code IDKJJM09218467P1
Type Package
Main Project JJM 2021-22 - Setting up/ Upgradation/ Operation of Laboratories - Setting up of new Sub District Laboratory at Adimali
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Setting up/ Upgradation/ Operation of Laboratories - Setting up of new Sub District Laboratory at Adimali
Status Completed
District Idukki
Executing Office Idukki QC Sn
Agreement Number
Agreement Date
TS Amount (Rs) 2940141
TS Number TS/2021-2022/2021/34263
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/12/2021
Scheduled date of Completion as per agreement 21 Feb 2022
Expected date of Completion 30/04/2022

Processing Dates

TS Date 05 Nov 2021
Estimate Approval 05 Nov 2021
NIT Approval 08 Nov 2021
Tender Closing 20 Nov 2021
Price bid opening 24 Nov 2021

Approval Dates

Workorder Date 24 Nov 2021
NA 06 Dec 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Idukki QCDL - AE
Date: 19/07/2022

Work has been completed | 100% Completed

work completed .final bill under preparation.

Attached images

img

Idukki QCDL - AE
Date: 24/06/2022

Work has been completed | 100% Completed

work completed .final bill under preperation.